OSHA Inspection: GARCIAS EXTERIOR & INTERIOR REMODELING, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of GARCIAS EXTERIOR & INTERIOR REMODELING, INC. in 718 LAKE STREET, WILMETTE, IL 60091 (NAICS 236118). OSHA activity number 345046254.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Garcias Exterior & Interior Remodeling, INC. — free Get an email when a new federal OSHA severe-injury report for Garcias Exterior & Interior Remodeling, INC. is published. One employer, no account, unsubscribe in one click.
Site address
718 LAKE STREET
City
WILMETTE
State
IL
ZIP
60091
Mailing
6831 JUNIPER AVE., HANOVER PARK, IL 60133
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236118
Employees
9
Ownership type
A

6 citations on file for this inspection.

1903.19 C01

Other-than-serious 1 instance 1 exposed
Issued
Dec 6, 2021
Abate by
Jan 10, 2022
Penalty
Initial $361 · Current $361
29 CFR 1903.19(c)(1): The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated:   Garcias Exterior & Interior Remodeling, Inc. DBA Garcia's Exterior & Interior Remodeling, Inc., failed to certify to OSHA within 10 calendar days after the abatement date that each of the following cited violations had been corrected:   Citation Number            Item Number                    Abatement Date 01                                                          01                                06/10/2021 01                                                          02                                06/10/2021 01                                                          03a                              06/10/2021 01                                                          03b                              06/10/2021 01                                                          04                                06/10/2021                                   In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF THE CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (O) $361

1926.100 A

Serious Gravity 5 1 instance 10 exposed
Issued
May 14, 2021
Abate by
Jun 10, 2021
Penalty
Initial $2,575 · Current $2,575
29 CFR  1926.100(a):Employees working in areas where there was a possible danger of head injury from impact, or falling or flying objects, or from electrical shock and burns, were not protected by protective helmets:  a) On or about December 2, 2020, employees were exposed to the hazard of falling siding, windows, tools, and debris when working below employees that were installing windows and siding.  The employees were not observed wearing any hard hats.    In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
  • — Z (S) $2575

1926.451 E01

Serious Gravity 5 1 instance 2 exposed
Issued
May 14, 2021
Abate by
Jun 10, 2021
Penalty
Initial $2,575 · Current $2,575
29 CFR  1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used.    a) On or about December 2, 2020, at the above addressed jobsite, employees conducting siding and window installation operations from ladder jack scaffolding, fourteen (14') feet above the ground, were not provided with an access ladder, thereby exposing the employees to falls.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
  • — Z (S) $2575

1926.451 G01

Serious Gravity 10 1 instance 2 exposed
Issued
May 14, 2021
Abate by
Jun 10, 2021
Penalty
Initial $4,505 · Current $4,505
29 CFR  1926.451(g)(1):Employees on scaffolds more than 10 feet (3.1 m) above a lower level were not protected from falling to that lower level by fall protection established in paragraphs (g)(1)(i)-(vii) of this section:  a) On or about December 2, 2020, at the above addressed jobsite, employees conducting siding and window installation operations from a pump jack combo scaffolding at sixteen (16') feet above the ground, were not provided with guardrails, midrails, cross rails or other means of fall protection, thereby exposing the employee to fall hazards.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
  • — Z (S) $4505

1926.451 G01 I

Serious Gravity 10 2 instances 4 exposed
Issued
May 14, 2021
Abate by
Jun 10, 2021
Penalty
Initial $0 · Current $0
29 CFR  1926.451(g)(1)(i): Each employee on a boatswains' chair, catenary scaffold, float scaffold, needle beam scaffold, or ladder jack scaffold was not protected by a personal fall arrest system:  a) On or about December 2, 2020, at the above addressed jobsite, employees conducting window installation operations from ladder jack scaffolding at fourteen (14') feet above the ground, were not provided personal fall arrest systems or other means of fall protection, thereby exposing the employees to fall hazards.  b) On or about December 2, 2020, at the above addressed jobsite, employees conducting siding installation operations from a ladder jack and pump jack combo scaffolding at sixteen (16') feet above the ground, were not provided personal fall arrest systems or other means of fall protection, thereby exposing the employees to fall hazards.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
  • — Z (S) $0

1926.452 K05

Serious Gravity 10 1 instance 2 exposed
Issued
May 14, 2021
Abate by
Jun 10, 2021
Penalty
Initial $4,505 · Current $4,505
29 CFR  1926.452(k)(5): Scaffold platforms were bridged on to another.  a) On or about December 2, 2020, at the above addressed jobsite, employees were conducting window installation operations from a ladder jack scaffold, at fourteen (14') feet above the ground, that had two sections bridged together creating an uneven working surface, thereby exposing the employees to fall hazards.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
  • — Z (S) $4505