Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: ADF CABLE CONSTRUCTION INC.

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of ADF CABLE CONSTRUCTION INC. in SAND HILL ROAD AND FOREST AVENUE, HERSHEY, PA 17033 (NAICS 237130). OSHA activity number 345068068.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch ADF Cable Construction INC. — free Get an email when a new federal OSHA severe-injury report for ADF Cable Construction INC. is published. One employer, no account, unsubscribe in one click.
Site address
SAND HILL ROAD AND FOREST AVENUE
City
HERSHEY
State
PA
ZIP
17033
Mailing
10105 JONESTOWN ROAD, GRANTVILLE, PA 17028
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
237130
Employees
9
Ownership type
A

6 citations on file for this inspection.

1926.416 A03

Serious Gravity 10 1 instance 9 exposed
Issued
May 19, 2021
Abate by
Jun 15, 2021
Penalty
Initial $0 · Current $0
29 CFR  1926.416(a)(3): When and where energized circuits existed, the employer failed to post and maintain proper warning signs, advise employees of the location, hazard involved and the proper protective measures to be taken:   (a) ADF Cable Construction, Sand Hill Road and Forest Avenue, Hershey, Pennsylvania - Where employees used a powered capstan winch and a powered reeler to wind up and remove whole a conductive aerial fiber optic telecommunication cable, which had a length (over 4,500 feet long) capable of contacting exposed energized overhead electrical conductors, comprising a 69kV system running above the fiber optic cable, the employer did not advise employees of the hazard of indirect contact with the exposed energized lines and the proper protective measures to take, such as wearing rubber insulated gloves and non-conductive protective footwear, on or about December 11, 2020.  Abatement certification and documentation is required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.20 B02

Serious Gravity 10 1 instance 9 exposed
Issued
May 5, 2021
Abate by
Jun 1, 2021
Penalty
Initial $9,557 · Current $5,000 Reduced
29 CFR  1926.20(b)(2): The employer did not initiate and maintain a safety program which provided for frequent and regular inspections of job sites, materials, and equipment to be made by a competent person (a competent person is defined as one who is capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them):   (a) ADF Cable Construction, Sand Hill Road and Forest Avenue, Hershey, Pennsylvania - The employer did not have a competent person on the job site in that nobody inspected the job site, identified predictable electrical hazards, and took immediate actions to correct the hazards.  As a result, employees used a powered capstan winch and a powered reeler to wind up and remove whole a conductive aerial fiber optic telecommunication cable, which had a length (over 4,500 feet long) capable of contacting exposed energized overhead electrical conductors, comprising a 69kV system running above the fiber optic cable, exposing employees to the hazard of contact with electrical current, as occurred on or about December 11, 2020, when the fiber optic cable came out of a supporting loop, flipped up, and contacted the energized primary.  The metallic foil wrapping inside the fiber optic cable carried the electrical current to the reeler truck, where the electrical current returned to ground, including through an employee, not wearing electrically rated personal protective equipment, standing on the ground operating the reeler.  Abatement certification and documentation is required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $5000
  • — Z (S) $9557

1926.95 A

Serious Gravity 10 1 instance 9 exposed
Issued
May 5, 2021
Abate by
Jun 1, 2021
Penalty
Initial $9,557 · Current $5,000 Reduced
29 CFR  1926.95(a): Protective equipment, including personal protective equipment for eyes, face, head, and extremities, protective clothing, respiratory devices, and protective shields and barriers, were not provided:  (a) ADF Cable Construction, West End of Forest Avenue, Hershey, Pennsylvania - Employees worked removing (wrecking out) seven aerial fiber optic telecommunication cables, each over 4,500 feet long, installed on 70-foot high metal utility poles.  These poles also had exposed energized power conductors, comprising a 69kV system, running above the fiber optic cables, which employees could contact indirectly, including through the fiber optic cables if the fiber optic cables whipped or flipped up during the wreck out process, and the employer did not require the employees to wear rubber insulated gloves designed for the voltages encountered and non-conductive footwear, and the employees did not wear rubber insulated gloves and non-conductive footwear, exposing employees to the hazard of contact with electrical current, on or about December 11, 2020  Abatement certification and documentation is required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $5000
  • — Z (S) $9557

1926.416 A01

Serious Gravity 10 1 instance 9 exposed
Issued
May 5, 2021
Abate by
Jun 1, 2021
Penalty
Initial $9,557 · Current $5,000 Reduced
29 CFR  1926.416(a)(1): Employees were permitted to work in proximity to electric power circuits and were not protected against electric shock by de-energizing and grounding the circuits or effectively guarding the circuits by insulation or other means:  (a) ADF Cable Construction, Sand Hill Road and Forest Avenue, Hershey, Pennsylvania - Employees worked removing (wrecking out) seven aerial fiber optic telecommunication cables, each over 4,500 feet long, installed on 70-foot high metal utility poles.  These utility poles also had exposed energized power conductors, comprising a 69kV system, running above the fiber optic cables, and the employer did not have the energized power conductors deenergized and grounded or guarded effectively by insulation or other means.  As the employees removed the first fiber optic cable using a powered reeler on the rear of an Altec A40P Aerial Cable Placer Bucket Truck, known as Truck 55, as well as a capstan winch on another truck, to wind this cable in full length onto a spool, the tail end of the fiber optic cable came out of a loop (one of many) used to temporarily suspend the seven fiber optic cables from the strand during the wreck out.  After coming out of the loop, the tail end of the cable flipped up contacting the energized primary.  The metallic foil wrapping around the optical fiber within the cable carried the electrical current about 1,500 feet through the cable to Truck 55, where the electric current returned to ground through the truck's two front tires and the rear driver side tire and through the employee standing on the ground operating the reeler at the truck's rear passenger side, resulting in electric shock and burns, on or about December 11, 2020.  Abatement certification and documentation is required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $5000
  • — Z (S) $9557

1904.4 A

Other-than-serious 1 instance 43 exposed
Issued
May 5, 2021
Penalty
Initial $0 · Current $0
29 CFR  1904.4(a): The employer did not record each work-related fatality, injury or illness case that resulted in the general recording criteria on the OSHA Form 300 or equivalent:  ADF Cable Construction, 10105 Jonestown Road, Grantville, Pennsylvania - On or about December 16, 2020, the employer did not record the following workplace injury and illness on the OSHA 300 Log for calendar year 2020:  (a) On or about December 11, 2020, while wrecking out a fiber optic cable, an employee received an electric shock, resulting in in-patient hospitalization for burns and at least 20 days away from work.  Corrected during the inspection.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

1904.39 A02

Other-than-serious 1 instance 43 exposed
Issued
May 5, 2021
Penalty
Initial $0 · Current $0
29 CFR  1904.39(a)(2):  The employer did not report within 24-hours a work-related incident resulting in in-patient hospitalization, amputation or the loss of an eye:  (a) ADF Cable Construction, West End of Forest Avenue, Hershey, Pennsylvania - While wrecking out a fiber optic cable on December 11, 2020, an employee suffered an electric shock, which resulted in injuries requiring in-patient hospitalization.  The employer did not report this work-related in-patient hospitalization to OSHA.  Corrected during the inspection.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345068068.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.