OSHA Inspection: SOUTHWINDS CONTRACTING, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of SOUTHWINDS CONTRACTING, INC. in 1ST AND WICKHAM, BLDG. 2601, FORT CAMPBELL, KY 42223 (NAICS 236220). OSHA activity number 345187595.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Southwinds Contracting, INC. — free Get an email when a new federal OSHA severe-injury report for Southwinds Contracting, INC. is published. One employer, no account, unsubscribe in one click.
Site address
1ST AND WICKHAM, BLDG. 2601
City
FORT CAMPBELL
State
KY
ZIP
42223
Mailing
1000 GATE 7 ROAD LOT A, OAK GROVE, KY 42262
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236220
Employees
5
Ownership type
A

5 citations on file for this inspection.

1926.150 C01 VIII

Serious Gravity 5 1 instance 2 exposed
Issued
Apr 28, 2021
Penalty
Initial $3,121 · Current $3,121
29 CFR  1926.150(c)(1)(viii): Portable fire extinguishers were not inspected periodically and maintained in accordance with maintenance and use of portable fire extinguishers, N.F.P.A. No. 10A-1970:   a) Fort Campbell - Salt Shed - Building 5160: On or about 3/09/2021 and days prior, a portable fire extinguisher mounted on an Arial lift (SN# 0300266554) had been discharged and was not charged and ready for use.
Recent events (3)
  • — A (S) $3121
  • — I (S) $0
  • — Z (S) $3121

1926.403 B01

Serious Gravity 5 1 instance 2 exposed
Issued
Apr 28, 2021
Penalty
Initial $3,121 · Current $1,000 Reduced
29 CFR  1926.403(b)(1): Employer did not ensure that electrical equipment is free from recognized hazards that are likely to cause death or serious physical harm to employees:   a) Fort Campbell - Salt Shed - Building 5160: On or about 3/9/2021 and days prior, the flexible cord to a portable circular saw workers were using was damaged exposing workers to the hazard of electric shock from unprotected energized conductors.
Recent events (2)
  • — I (S) $1000
  • — Z (S) $3121

1926.416 E01

Serious Gravity 5 1 instance 2 exposed
Issued
Apr 28, 2021
Penalty
Initial $0 · Current $0
29 CFR  1926.416(e)(1): Worn or frayed electric cords or cables were used:(a)Salt Shack, power saw cord was frayed   a) Fort Campbell - Salt Shed - Building 5160: On or about 3/9/2021 and days prior, the employer exposed employees to an electrical hazard, the flexible cord on a portable circular saw was damaged exposing energized conductors.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.453 A02

Serious Gravity 10 1 instance 1 exposed
Issued
Apr 28, 2021
Penalty
Initial $5,461 · Current $4,900 Reduced
29 CFR  1926.453(a)(2): Field modification of the aerial lift was not certified in writing by the manufacturer or by any other equivalent entity, such as a nationally recognized testing laboratory, to be in conformity with all applicable provisions of ANSI A92.2-1969 and this section and to be at least as safe as the equipment was before modification:   In the alternative:  29 CFR  1926.20(b)(3): Machinery, tool(s), material(s), or equipment which was not in compliance with the applicable requirement(s) of 29 CFR 1926 was not prohibited, and/or was not either identified as unsafe by tagging, or locking the controls to render them inoperable, or physically removed from its place of operation:  a) Fort Campbell - Salt Shed - Building 5160: On or about 3/9/2021 and days prior, the employer exposed workers to potential fall and crushing hazards, Workers were working from an JLG Model 450AJ articulating boom aerial lift (SN# 03002700348) and the emergency stop safety cable had been modified/rigged after being damaged bypassing the safety mechanism and  to enabling the machine to fully operate.
Recent events (2)
  • — I (S) $4900
  • — Z (S) $5461

1926.451 G04 IV

Other-than-serious 1 instance 2 exposed
Issued
Apr 28, 2021
Penalty
Initial $0 · Current $0
29 CFR  1926.451(g)(4)(iv): Midrails were not installed at a height approximately midway between the top edge of the guardrail system and the platform surface:   a) Fort Campbell - Salt Shed - Building 5160: On or about 3/9/2021 and days prior, the employer exposed employees to a fall hazard, the scissor lift midrail was not installed halfway between the guardrail and platform.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

View Southwinds Contracting, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345187595.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.