OSHA Inspection: SUNWOOD BUILDERS, INC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of SUNWOOD BUILDERS, INC in 23 FORDS CROSSING, NORTHAMPTON, MA 01060 (NAICS 236220). OSHA activity number 345312052.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Sunwood Builders, INC — free Get an email when a new federal OSHA severe-injury report for Sunwood Builders, INC is published. One employer, no account, unsubscribe in one click.
Site address
23 FORDS CROSSING
City
NORTHAMPTON
State
MA
ZIP
01060
Mailing
84 POTWINE LANE, AMHERST, MA 01002
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236220
Employees
8
Ownership type
A

5 citations on file for this inspection.

1926.403 E

Serious Gravity 5 4 instances 2 exposed
Issued
Aug 10, 2021
Abate by
Aug 16, 2021
Penalty
Initial $2,926 · Current $1,463 Reduced
29 CFR  1926.403(e):Conductors were not spliced or joined with splicing devices designed for the use or by brazing, welding, or soldering with a fusible metal or alloy. All splices and joints and the free ends of conductors were not covered with an insulation equivalent to that of the conductors or with an insulating device designed for the purpose:  23 Fords Crossing., Northampton, MA: On or about May 17, 2021,  employees were observed using electrical powered tools which were receiving power through electrical cords that had not been improperly spliced.
Recent events (2)
  • — I (S) $1463
  • — Z (S) $2926

1926.404 B01 III D 1

Serious Gravity 5 1 instance 2 exposed
Issued
Aug 10, 2021
Abate by
Aug 16, 2021
Penalty
Initial $2,341 · Current $0 Reduced
29 CFR  1926.404(b)(1)(iii)(D)(1):All equipment grounding conductors was not tested for continuity and was not  electrically continuous:  23 Fords Crossing., Northampton, MA: On or about May 17, 2021, the employer had not established  or implemented an assured grounding conductor program for this job site which included testing equipment for continuity exposing employees to electrical shock and burn hazards.  Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29CFR1903.19(d)(1).
Recent events (2)
  • — I (S) $0
  • — Z (S) $2341

1926.404 B01 III

Deleted Serious Gravity 10 1 instance 2 exposed
Issued
Aug 10, 2021
Abate by
Aug 16, 2021
Penalty
Initial $4,096 · Current $0 Reduced
29 CFR  1926.404(b)(1)(iii): The employer did not establish and/or implement an assured equipment grounding conductor program on construction sites covering all cord sets, receptacles which are not a part of the building or structure, and equipment connected by cord and plug which are available for use or used by employees:  23 Fords Crossing., Northampton, MA: On or about May 17, 2021, the employer had not established  or implemented an assured grounding conductor program for this job site.  Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29CFR1903.19(d)(1).
Recent events (2)
  • — I (S) $0
  • — Z (S) $4096

1926.405 G02 IV

Serious Gravity 5 1 instance 1 exposed
Issued
Aug 10, 2021
Abate by
Aug 16, 2021
Penalty
Initial $2,341 · Current $1,171 Reduced
29 CFR  1926.405(g)(2)(iv): Flexible cords were not connected to devices and fittings so that strain relief is provided which will prevent pull from being directly transmitted to joints or terminal screws:  23 Fords Crossing., Northampton, MA: On or about May 17, 2021, an employee was observed using a grinding tool powered by an extension cord that the sheath had pulled away from the electrical socket head due to the lack of strain relief.
Recent events (2)
  • — I (S) $1170.5
  • — Z (S) $2341

1926.453 B02 V

Other-than-serious Gravity 10 1 instance 1 exposed
Issued
Aug 10, 2021
Abate by
Aug 16, 2021
Penalty
Initial $4,096 · Current $0 Reduced
29 CFR  1926.453(b)(2)(v):A body belt was not  worn and a lanyard  was not attached to the boom or basket when working from an aerial lift:  23 Fords Crossing., Northampton, MA: On or about May 17, 2021, an employee was observed working from a raised aerial lift and was not attached to the basket by a harness and lanyard system.  Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29CFR1903.19(d)(1).
Recent events (2)
  • — I (O) $0
  • — Z (S) $4096

View Sunwood Builders, INC's full OSHA safety record →