REFUGIO, TX —
OSHA Inspection: D&J QUALITY CONSTRUCTION LLC
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of D&J QUALITY CONSTRUCTION LLC in 300 ALAMO, REFUGIO, TX 78377 (NAICS 238140). OSHA activity number 345365415.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- D&J QUALITY CONSTRUCTION LLC
- Site address
- 300 ALAMO
- City
- REFUGIO
- State
- TX
- ZIP
- 78377
- Mailing
- P.O BOX 12, GILMER, TX 75645
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 4
- Ownership type
- B
Citations
8 citations on file for this inspection.
1926.100 A
- Issued
- Sep 13, 2021
- Penalty
- Initial $2,926 · Current $2,926
General-duty citation text
29 CFR 1926.100(a): Employees working in areas where there is a possible danger of head injury from impact, or from falling or flying objects, or from electrical shock and burns, shall be protected by protective helmets. On or about June 8,2021 at this workplace, employees conducted masonry construction operations from scaffolding platforms and were not protected by protective helmets to protect from falling objects. Instant (A). At the North Wall of the building under construction at this workplace. Instant (B). At the West Wall of the building under construction at this workplace.
Recent events (2)
- — I (S) $2926
- — Z (S) $2926
1926.451 B01
- Issued
- Sep 13, 2021
- Penalty
- Initial $2,926 · Current $2,926
General-duty citation text
29 CFR 1926.451(b)(1): Platform(s) on all working levels of scaffolds, were not fully planked or decked between the front uprights and guardrail supports such that the space between adjacent units, and the space between the platform and the uprights. On or about June 8,2021 at this workplace, employees conducted masonry construction operations from scaffolding at the height of greater then ten feet above a lower level was not fully planked between uprights at the west wall of this structure under construction.
Recent events (2)
- — I (S) $2926
- — Z (S) $2926
1926.451 B10
- Issued
- Sep 13, 2021
- Penalty
- Initial $2,926 · Current $0 Reduced
General-duty citation text
29 CFR 1926.451(b)(10): Scaffold components manufactured by different manufacturers were intermixed such that the components fit together with force and the scaffold's structural integrity was not maintained by the user. On or about June 8,2021 at this workplace, employees conducted masonry construction operations from scaffolding platforms and scaffold components were manufactured by different manufactures, at the north wall of the building under construction.
Recent events (2)
- — I (S) $0
- — Z (S) $2926
1926.451 C02
- Issued
- Sep 13, 2021
- Penalty
- Initial $2,926 · Current $0 Reduced
General-duty citation text
29 CFR 1926.451(c)(2): Supported scaffold poles, legs, posts, frames, or uprights did not bear on base plates, mud sills or other adequate firm foundation: On or about June 8,2021 at this workplace, employees conducted masonry construction operations from scaffolding platforms and a support scaffold pole did not bear on base plates at the north wall of this building under construction.
Recent events (2)
- — I (S) $0
- — Z (S) $2926
1926.451 E01
- Issued
- Sep 13, 2021
- Penalty
- Initial $2,926 · Current $0 Reduced
General-duty citation text
29 CFR 1926.451(e)(1):When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Crossbraces were used as a means of access. On or about June 8,2021 at this workplace, employees conducted masonry construction operations from scaffolding platforms greater than two feet above or below a point of access and a means of access was not provided. Instant (A). At the North Wall of the building under construction at this workplace. Instant (B). At the West Wall of the building under construction at this workplace.
Recent events (2)
- — I (S) $0
- — Z (S) $2926
1926.451 H02 II
- Issued
- Sep 13, 2021
- Penalty
- Initial $2,926 · Current $0 Reduced
General-duty citation text
29 CFR 1926.451(h)(2)(ii): A toeboard was not erected along the edge of platforms more than 10 feet (3.1 m) above lower levels for a distance sufficient to protect employees below. On or about June 8,2021 at this workplace, employees conducted masonry construction operations from scaffolding platforms greater than ten feet without erected toeboards and employees were working below at the West Wall of the building under construction.
Recent events (2)
- — I (S) $0
- — Z (S) $2926
1926.451 F07
- Issued
- Sep 13, 2021
- Penalty
- Initial $2,926 · Current $2,926
General-duty citation text
29 CFR 1926.451(f)(7): Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration:; Such activities were not performed only by experienced and trained employees selected for such work by the competent person. On or about June 8,2021 at this workplace, employees conducted masonry construction operations from scaffolding platforms. The scaffolding was not erected by a competent person qualified in scaffold erection. Instant (A). At the North Wall of the building under construction at this workplace. Instant (B). At the West Wall of the building under construction at this workplace.
Recent events (2)
- — I (S) $2926
- — Z (S) $2926
1926.451 G01
- Issued
- Sep 13, 2021
- Penalty
- Initial $2,926 · Current $2,926
General-duty citation text
29 CFR 1926.451(g)(1): Employees on scaffolds more than 10 feet (3.1 m) above a lower level were not protected from falling to that lower level by fall protection established in paragraphs (g)(1)(i)-(vii) of this section. On or about June 8,2021 at this workplace, employees conducted masonry construction operations from scaffolding platforms greater than ten feet without a fall protection system in place at the west wall of the building under construction. .
Recent events (2)
- — I (S) $2926
- — Z (S) $2926
More inspections at D&J Quality Construction LLC
View D&J Quality Construction LLC's full OSHA safety record →
More inspections in this industry (NAICS 238140)
More inspections in TX
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345365415.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.