Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: RQ CONSTRUCTION, LLC

Unprogrammed Related inspection · Safety discipline

On , OSHA opened an unprogrammed Related safety inspection of RQ CONSTRUCTION, LLC in 9359 VIRGINIA AVE NORFOLK NAVAL STATION, NORFOLK, VA 23511 (NAICS 236220). OSHA activity number 345482012.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch RQ Construction, LLC — free Get an email when a new federal OSHA severe-injury report for RQ Construction, LLC is published. One employer, no account, unsubscribe in one click.
Site address
9359 VIRGINIA AVE NORFOLK NAVAL STATION
City
NORFOLK
State
VA
ZIP
23511
Mailing
1620 FARADAY AVENUE, CARLSBAD, CA 92008
Inspection type
Unprogrammed Related (G)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236220
Employees
500
Ownership type
A

7 citations on file for this inspection.

1926.34 B

Other-than-serious Gravity 5 1 instance 90 exposed
Issued
Oct 19, 2021
Abate by
Nov 15, 2021
Penalty
Initial $8,778 · Current $8,778
29 CFR 1926.34(b): Exits and access to exits were not marked by a readily visible sign:  a)	P-1120 Mariners Skills Training Center: On or about 08/16/2021, exit signs were not visible or marked throughout the building.   Abatement certification required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
  • — R (O) $8778
  • — C (S) $8778
  • — Z (S) $8778

1926.34 C

Other-than-serious Gravity 5 1 instance 90 exposed
Issued
Oct 19, 2021
Abate by
Nov 15, 2021
Penalty
Initial $0 · Current $0
29 CFR  1926.34(c): Means of egress was not continually maintained free of all obstructions or impediments to full instant use in the case of fire or other emergency:   a)	P-1120 Mariners Skills Training Center: On or about 08/16/2021, means of egress was not continually maintained free of all obstructions in that electrical conduits were installed on the floor of the main corridors thereby exposing personnel to a possible trip hazard:  Abatement certification required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
  • — R (O) $0
  • — C (S) $0
  • — Z (S) $0

1926.501 B03

Other-than-serious Gravity 5 1 instance 1 exposed
Issued
Oct 19, 2021
Abate by
Nov 15, 2021
Penalty
Initial $8,778 · Current $8,778
29 CFR  1926.501(b)(3): Each employee in a hoist area was not protected from falling 6 feet (1.8m) or more to lower levels by guardrail systems or personal fall arrest systems:  a)	P-1120 Mariners Skills Training Center: On or about 08/16/2021,  CSHO observed an employee pour piles of water from a hoist area approximately 20ft from the ground without fall protection.    Abatement certification required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
  • — R (O) $8778
  • — C (S) $8778
  • — Z (S) $8778

1926.503 A02

Other-than-serious Gravity 5 1 instance 1 exposed
Issued
Oct 19, 2021
Abate by
Nov 15, 2021
Penalty
Initial $0 · Current $0
29 CFR  1926.503(a)(2): The employer did not assure that each employee exposed to fall hazards was trained by a competent person qualified in the areas specified in 29 CFR 1926.503 (a)(2)(i) through (viii):  a)	P-1120 Mariners Skills Training Center: On or about 08/16/2021, an employee exposed to a fall hazard was not provide with fall protection training.  Abatement certification required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
  • — R (O) $0
  • — C (S) $0
  • — Z (S) $0

1926.1051 A

Other-than-serious Gravity 1 1 instance 90 exposed
Issued
Oct 19, 2021
Abate by
Nov 15, 2021
Penalty
Initial $5,266 · Current $5,266
29 CFR  1926.1051(a): Stairway(s) or ladder(s) were not provided at all personnel points of access where there was a break in elevation of 19 inches (48 cm) or more, or no ramp, runway, sloped embankment, or personnel hoist was provided:  a)	P-1120 Mariners Skills Training Center: On or about 08/16/2021, accesses available to subcontractors' employees had a break in elevation of approximately 41 inches.    Abatement certification required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
  • — R (O) $5266
  • — C (S) $5266
  • — Z (S) $5266

1926.150 C01 I

Deleted Other-than-serious 1 instance 1 exposed
Issued
Oct 19, 2021
Abate by
Nov 15, 2021
Penalty
Initial $0 · Current $0
29 CFR  1926.150(c)(1)(i): A fire extinguisher, rated not less than 2A, was not provided for each 3,000 square feet of the protected building area, or major fraction thereof:  a)	P-1120 Mariners Skills Training Center: On or about 08/16/2021, a fire extinguisher was not provided for each 3000 feet of building in that sections E and F of the building did not contain a fire extinguisher.   Abatement certification required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
  • — R (O) $0
  • — C (O) $0
  • — Z (O) $0

1926.150 C01 IV

Other-than-serious 1 instance 90 exposed
Issued
Oct 19, 2021
Abate by
Nov 15, 2021
Penalty
Initial $0 · Current $0
29 CFR  1926.150(c)(1)(iv): There was not at least one fire extinguisher located adjacent to stairways on each floor of a multistory building:  a)	P-1120 Mariners Skills Training Center: On or about 08/16/2021, a fire extinguisher was not located adjacent  to each enclosed level of stairway.  Abatement certification required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (3)
  • — R (O) $0
  • — C (O) $0
  • — Z (O) $0

View RQ Construction, LLC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345482012.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.