STEELTON, PA —
OSHA Inspection: MILLER PIPELINE LLC
Complaint inspection · Safety discipline
At a glance
On , OSHA opened a complaint safety inspection of MILLER PIPELINE LLC in 250 WEST FRANKLIN STREET, STEELTON, PA 17113 (NAICS 237120). OSHA activity number 345618409.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- MILLER PIPELINE LLC
- Site address
- 250 WEST FRANKLIN STREET
- City
- STEELTON
- State
- PA
- ZIP
- 17113
- Mailing
- 250 WEST FRANKLIN STREET, STEELTON, PA 17113
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- A
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 237120
- Employees
- 60
- Ownership type
- A
Citations
4 citations on file for this inspection.
1910.37 B02
- Issued
- Jan 26, 2022
- Abate by
- May 2, 2022
- Penalty
- Initial $5,283 · Current $4,500 Reduced
General-duty citation text
29 CFR 1910.37(b)(2): Each exit was not clearly visible and marked by a sign reading "Exit": a. Yard, the supervisor trailer - On or about November 04, 2021, the two "exit doors were not marked with "Exit" signs, exposing employees to a fire hazard. b. Yard, the administrative trailer - On or about November 04, 2021, the two exit doors were not marked with "Exit" signs, exposing employees to a fire hazard. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (O) $4500
- — Z (S) $5283
1910.38 B
- Issued
- Jan 26, 2022
- Abate by
- May 2, 2022
- Penalty
- Initial $7,044 · Current $4,500 Reduced
General-duty citation text
29 CFR 1910.38(b): An emergency action plan was not in writing, kept in the workplace, and available to employees for review: a. Yard, Supervisor and Administrative trailers - On or about November 4, 2021, the employer had no developed written emergency action plan for the yard staff operations, exposing employees to a fire or other emergency hazards. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (O) $4500
- — Z (S) $7044
1910.147 C08
- Issued
- Jan 26, 2022
- Abate by
- Feb 7, 2022
- Penalty
- Initial $5,283 · Current $0 Reduced
General-duty citation text
29 CFR 1910.147(c)(8): Lockout or tagout was not performed only by the authorized employees who are performing the servicing or maintenance: a. Field - On or about November 4, 2021, employees work on gas pipelines while they are being locked out and under the control of another's lock, exposing employees to a fire hazard. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $5283
1910.147 F03 II D
- Issued
- Jan 26, 2022
- Abate by
- Feb 7, 2022
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.147(f)(3)(ii)(D): Each authorized employee did not affix a personal lockout or tagout device to the group lockout device before working on the machine or equipment: a. Field - On or about November 4, 2021, employees work on gas pipelines under group work conditions were not applying individual locks per authorized employee and the equipment was being locked out and under the control of a single lock applied by another organization, exposing employees to a fire hazard. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
More inspections at Miller Pipeline LLC
View Miller Pipeline LLC's full OSHA safety record →
More inspections in this industry (NAICS 237120)
More inspections in PA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345618409.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.