Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: R III CONSTRUCTION INCORPORATED

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of R III CONSTRUCTION INCORPORATED in 643 SENECA STREET, HARRISBURG, PA 17110 (NAICS 237110). OSHA activity number 345953467.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch R III Construction Incorporated — free Get an email when a new federal OSHA severe-injury report for R III Construction Incorporated is published. One employer, no account, unsubscribe in one click.
Site address
643 SENECA STREET
City
HARRISBURG
State
PA
ZIP
17110
Mailing
600 CREAMERY ROAD, NAZARETH, PA 18064
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
237110
Employees
5
Ownership type
A

7 citations on file for this inspection.

1926.52 D01

Other-than-serious Gravity 5 1 instance 2 exposed
Issued
Aug 24, 2022
Abate by
Oct 14, 2022
Penalty
Initial $2,735 · Current $0 Reduced
29 CFR  1926.52(d)(1): In all cases where the sound levels exceeded the values shown in Table D-2 of 29 CFR 1926.52, a continuing, effective hearing conservation program was not administered:  a. 643 Seneca Street - On or about May 12, 2022, employees were exposed to hazardous noise while working inside a build a box trench shielding device. The employees were operating jackhammer/air hammers to break up concrete that encapsulated the sewer pipe. The employees were not wearing hearing protection and no sampling had been done to determine the need for hearing conservation or protection.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (O) $0
  • — Z (S) $2735

1926.404 F06

Serious Gravity 5 1 instance 3 exposed
Issued
Aug 24, 2022
Penalty
Initial $3,419 · Current $2,250 Reduced
29 CFR  1926.404(f)(6):The path to ground from circuits, equipment, or enclosures was not permanent and continuous:  a. 643 Seneca Street - On or about May 12, 2022, the employees were exposed to an electrical hazard from the use of an ungrounded extension cord that was plugged into a portable generator.  Corrected During Inspection - No Abatement Required
Recent events (2)
  • — I (S) $2250
  • — Z (S) $3419

1926.405 G02 IV

Serious Gravity 5 1 instance 3 exposed
Issued
Aug 24, 2022
Abate by
Oct 14, 2022
Penalty
Initial $0 · Current $0
29 CFR  1926.405(g)(2)(iv): Flexible cords were not connected to devices and fittings so that strain relief is provided to prevent pull from being directly transmitted to joints or terminal screws:  a. 643 Seneca Street - On or about May 12, 2022, the employees were exposed to an electrical hazard from the use of an electric jack hammer that was not provided strain relief at the plug, which was then plugged into an extension cord that was not grounded.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.651 B04

Serious Gravity 5 1 instance 2 exposed
Issued
Aug 24, 2022
Abate by
Oct 14, 2022
Penalty
Initial $3,419 · Current $2,250 Reduced
29 CFR  1926.651(b)(4):While the excavation was opened, underground installations were not protected, supported or removed as necessary to safeguard employees:  a. 643 Seneca Street - On or about May 12, 2022, employees were working in a trench where underground utilities had been disrupted and water line had been damaged resulting in a steady trickle of water into the trench, which posed a risk of further deterioration or the trench walls and a cave in struck by hazard.   Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $2250
  • — Z (S) $3419

1926.651 C02

Serious Gravity 5 1 instance 2 exposed
Issued
Aug 24, 2022
Abate by
Oct 14, 2022
Penalty
Initial $3,419 · Current $2,250 Reduced
29 CFR  1926.651(c)(2):A stairway, ladder, ramp or other safe means of egress was not located in trench excavations that were 4 feet (1.22m) or more in depth so as to require no more than 25 feet (7.62m) of lateral travel for employees:  a. Trench Box - On or about May 12, 2022, employees working inside a trench were not provided with a means of safe egress from a trench approximately 10 feet deep, exposing employees to a caught in hazard.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $2250
  • — Z (S) $3419

1926.651 K01

Serious Gravity 5 1 instance 2 exposed
Issued
Aug 24, 2022
Abate by
Oct 14, 2022
Penalty
Initial $3,419 · Current $2,250 Reduced
29 CFR  1926.651(k)(1):An inspection of the excavations, the adjacent areas, and protective systems was not conducted by the competent person prior to the start of work and as needed throughout the shift:  a. 643 Seneca Street - On or about May 12, 2022, the  employees were exposed to a caught in hazard from a trench box that was installed and being utilized without the inspection of a competent person.   Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $2250
  • — Z (S) $3419

1926.652 C03 III

Serious Gravity 5 1 instance 2 exposed
Issued
Aug 24, 2022
Abate by
Oct 14, 2022
Penalty
Initial $0 · Current $0
29 CFR  1926.652(c)(3)(iii):At least one copy of the tabulated data, which identifies the registered professional engineer who approved the data, was not maintained at the jobsite during construction of the protective system:  a. 643 Seneca Street - On or about May 12, 2022, the employer built a 6'x4' modular build a box shield without the presence of the tabulated data during the construction of the protective system, exposing employees to  caught in and struck by hazards related to engulfment.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

View R III Construction Incorporated's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345953467.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.