MILFORD, DE —
OSHA Inspection: ZACK EXCAVATING, INC
Unprogrammed Other inspection · Safety discipline
At a glance
On , OSHA opened an unprogrammed Other safety inspection of ZACK EXCAVATING, INC in NE 4TH STREET AND DE ROUTE 14 - NEW MILFORD POLICE DEPARTMENT, MILFORD, DE 19963 (NAICS 238910). OSHA activity number 346200306.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- ZACK EXCAVATING, INC
- Site address
- NE 4TH STREET AND DE ROUTE 14 - NEW MILFORD POLICE DEPARTMENT
- City
- MILFORD
- State
- DE
- ZIP
- 19963
- Mailing
- 2935 SOUTH DUPONT BOULEVARD, SMYRNA, DE 19977
What kind of inspection was it?
- Inspection type
- Unprogrammed Other (I)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238910
- Employees
- 7
- Ownership type
- A
Citations
8 citations on file for this inspection.
1910.1200 E01
- Issued
- Mar 3, 2023
- Abate by
- Mar 29, 2023
- Penalty
- Initial $6,250 · Current $0 Reduced
General-duty citation text
29 CFR 1910.1200(e)(1): The employer did not develop, implement, and maintain at the workplace a written hazard communication program which describes how the criteria specified in paragraphs (f), (g), & (h) of this section for labels and other forms of warning, safety data sheets, and employee information and training will be met, and which also includes items (i) and (ii) of this subparagraph: a) North of NE 4th Street and DE Route 14, New Milford Police Department, Milford, DE 19963: On or about September 7, 2022, the employer did not provide or maintain a hazardous communication program to include labels and other forms of warning, safety data sheets, and employee information and training as required. ABATEMENT NOTE: A written program shall include description of how the criteria for the following will be met: 1. Labeling and other forms of warning; 2. Material Safety Data Sheets; 3. Employee information and training Additionally, a list of hazardous chemicals known to be preset in the workplace must be compiled. Methods used to inform employees of the hazards associated with non-routine tasks and the informing of contractors of workplace hazards, including a description of the labeling system used in the facility and of the availability of material safety data sheets, must also be addressed. The written program must be made available upon request.
Recent events (3)
- — F (S) $0
- — C (S) $6250
- — Z (S) $6250
1910.1200 E01 I
- Issued
- Mar 3, 2023
- Abate by
- Mar 29, 2023
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.1200(e)(1)(i): The employer did not compile a list of the hazardous chemicals known to be present using a product identifier that was referenced on the appropriate safety data sheet. a) North of NE 4th Street and DE Route 14, New Milford Police Department, Milford, DE 19963: On or about September 7, 2022, the employer did not develop nor maintain a chemical inventory list identifying the hazardous chemicals being used by their employees.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1910.1200 H01
- Issued
- Mar 3, 2023
- Abate by
- Mar 29, 2023
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.1200(h)(1): Employees were not provided effective information and training on hazardous chemicals in their work area at the time of their initial assignment and whenever a new hazard that the employees had not been previously trained about was introduced into their work area: a) North of NE 4th Street and DE Route 14, New Milford Police Department, Milford, DE 19963: On or about September 7, 2022, employees were not provided training on hazardous chemicals to be used on the site nor did the employer provide SDS sheets for the employees to reference in case their was an exposure.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1926.21 B02
- Issued
- Mar 3, 2023
- Abate by
- Mar 29, 2023
- Penalty
- Initial $6,250 · Current $3,063 Reduced
General-duty citation text
29 CFR 1926.21(b)(2): The employer did not instruct each employee in the recognition and avoidance of unsafe condition(s) and the regulation(s) applicable to this work environment to control or eliminate any hazard(s) or other exposure to illness or injury: a) North of NE 4th Street and DE Route 14, New Milford Police Department, Milford, DE 19963: On or about September 7, 2022, employees engaged in trenching/excavation activities were not instructed to recognize hazards associated with working in trenches resulting in exposure to a potential collapse during installation of a commercial water connection pipe and a drain system during wet/rainy conditions. The trench did not have any means of egress or protective systems in place.
Recent events (3)
- — F (O) $3062.5
- — C (S) $6250
- — Z (S) $6250
1926.651 C02
- Issued
- Mar 3, 2023
- Penalty
- Initial $10,938 · Current $5,360 Reduced
General-duty citation text
29 CFR 1926.651(c)(2): A stairway, ladder, ramp or other safe means of egress was not located in trench excavations that were 4 feet (1.22m) or more in depth so as to require no more than 25 feet (7.62m) of lateral travel for employees: a) North of NE 4th Street and DE Route 14, New Milford Police Department, Milford, DE 19963: On or about September 7, 2022, employees observed installing a water line did not have a ladder or other safe means of egress while working in a trench/excavation that was 5 foot 2 inches deep and more than 20 feet long. b) North of NE 4th Street and DE Route 14, New Milford Police Department, Milford, DE 19963: On or about September 7, 2022, employees observed installing a drain pipe did not have a ladder or other safe means of egress while working in a trench/excavation that was 6 foot 8 inches deep and more than 20 feet long.
Recent events (3)
- — F (O) $5359.61
- — C (S) $10938
- — Z (S) $10938
1926.651 J02
- Issued
- Mar 3, 2023
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.651(j)(2): Protection was not provided by placing and keeping excavated or other materials or equipment at least 2 feet (.61m) from the edge of the excavations, or by the use of retaining devices that were sufficient to prevent materials or equipment from falling or rolling into excavations, or by a combination of both if necessary. a) North of NE 4th Street and DE Route 14, New Milford Police Department, Milford, DE 19963: On or about September 7, 2022, employees were exposed to excavated materials immediately above the work area where several inches of excavated soil was present along an unprotected trench/excavation. The soil at the site was wet and created an additional load on the walls of the trench/excavation adding to the potential of an exposure to a collapse.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1926.651 K01
- Issued
- Mar 3, 2023
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.651(k)(1): An inspection of the excavations, the adjacent areas, and protective systems was not made after every rainstorm or other hazard increasing occurrence: a) North of NE 4th Street and DE Route 14, New Milford Police Department, Milford, DE 19963: On or about September 7, 2022, inspection of the excavation was not conducted by a competent person to remove employees from hazardous conditions. The competent person required employees to enter and work in a trench/excavation without any protective means in place to prevent collapse, means of egress, and the excavated soil along the edge of the trench/excavation while it was raining, exposing employees to hazards associated with a potential trench/excavation collapse.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1926.652 A01
- Issued
- Mar 3, 2023
- Penalty
- Initial $10,938 · Current $5,360 Reduced
General-duty citation text
29 CFR 1926.652(a)(1): Each employee in an excavation was not protected from cave-ins by an adequate protective system designed in accordance paragraph (b) or (c) of 29 CFR 1926.652: a) North of NE 4th Street and DE Route 14, New Milford Police Department, Milford, DE 19963: On or about September 7, 2022, employees observed working in an unprotected trench/excavation. Employees were installing a new commercial water connection and storm water drainage system on a newly built police station project. Employees were required to enter and work in a trench/excavation during rainy conditions without any type of protective means. The rain increased the potential of collapse exponentially with the continued use of the excavator being used to assist the employee in the trench/excavation.
Recent events (3)
- — F (O) $5359.62
- — C (S) $10938
- — Z (S) $10938
More inspections at Zack Excavating, INC
View Zack Excavating, INC's full OSHA safety record →
More inspections in this industry (NAICS 238910)
More inspections in DE
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 346200306.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.