OSHA Inspection: DEPARTMENT OF VETERANS AFFAIRS, PORTLAND HEALTH CARE SYSTEM, VANCOUVER CAMPUS, FACILITIES MANAGEMENT

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of DEPARTMENT OF VETERANS AFFAIRS, PORTLAND HEALTH CARE SYSTEM, VANCOUVER CAMPUS, FACILITIES MANAGEMENT in 1601 EAST FOURTH PLAIN BLVD., BUILDING 4, VANCOUVER, WA 98661 (NAICS 561210). OSHA activity number 346503873.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Department of Veterans Affairs, Portland Health Care System, Vancouver Campus, Facilities Management — free Get an email when a new federal OSHA severe-injury report for Department of Veterans Affairs, Portland Health Care System, Vancouver Campus, Facilities Management is published. One employer, no account, unsubscribe in one click.
Site address
1601 EAST FOURTH PLAIN BLVD., BUILDING 4
City
VANCOUVER
State
WA
ZIP
98661
Mailing
1601 EAST FOURTH PLAIN BLVD., BUILDING 17, SUITE C415, VANCOUVER, WA 98661
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
561210
Employees
5000
Ownership type
D

5 citations on file for this inspection.

1910.107 B09

Serious Gravity 1 1 instance 6 exposed
Issued
Apr 25, 2023
Abate by
Jun 12, 2023
Penalty
Initial $0 · Current $0
1910.107(b)(9): Spray booths were not installed so that all portions were readily accessible for cleaning and a clear space of not less than 3 feet on all sides was not kept free from storage or combustible construction:  a) Paint Shop, where a clear space was not maintained on all sides of the Binks paint booth due to the storage of metal shelving, wooden shelving, numerous 1-gallon paint cans, numerous 5-gallon buckets of paint, ladders, fans, cardboard boxes, and the placement of the permanent wall constructed of wood and sheetrock.
Recent events (1)
  • — Z (S) $0

1910.147 C04 I

Serious Gravity 5 1 instance 6 exposed
Issued
Apr 25, 2023
Abate by
Jun 12, 2023
Penalty
Initial $0 · Current $0
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section:  a) Facility, written procedures had not been developed for tasks including:  1. Where the employer utilized the lockout tagout program for safe electrical work practices no written procedures had been developed for tasks such as, repairing and installing lighting fixtures and replacing outlets.  2. Written procedures had not been developed where employees performed preventative maintenance and repairs on equipment with stored energy, including but not limited to, permanently installed air compressors.
Recent events (1)
  • — Z (S) $0

1910.147 C06 I

Serious Gravity 5 1 instance 6 exposed
Issued
Apr 25, 2023
Abate by
Jun 12, 2023
Penalty
Initial $0 · Current $0
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed:  a) Facility, where an annual review had not been performed. Employees performed preventative maintenance and repairs such as, but not limited to, repairing and installing lighting fixtures, replacing outlets, and servicing permanently installed air compressors.
Recent events (1)
  • — Z (S) $0

1910.305 G01 IV A

Serious Gravity 1 1 instance 6 exposed
Issued
Apr 25, 2023
Penalty
Initial $0 · Current $0
29 CFR 1910.305(g)(1)(iv)(A): Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure:  a)  Break Area, where an orange extension cord was used to supply power to the Sharp microwave oven.
Recent events (1)
  • — Z (S) $0

1960.8 A

Serious Gravity 5 1 instance 6 exposed
Issued
Apr 25, 2023
Abate by
Jun 12, 2023
Penalty
Initial $0 · Current $0
29 CFR 1960.8(a): The Agency head did not furnish employment and a place of employment to each employee that were free from recognized hazards that caused or were likely to cause death or serious physical harm:  a) Metal Shop, where employees were exposed to the hazard of being struck or crushed beneath a falling load while operating the overhead underhung crane equipped with the CM Series 627 hoist.
Recent events (1)
  • — Z (S) $0

View Department of Veterans Affairs, Portland Health Care System, Vancouver Campus, Facilities Management's full OSHA safety record →