Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: ARLAND TOOL & MANUFACTURING, INC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of ARLAND TOOL & MANUFACTURING, INC in 45 FREIGHT HOUSE RD, WEST BROOKFIELD, MA 01585 (NAICS 332721). OSHA activity number 346630296.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Arland Tool & Manufacturing, INC — free Get an email when a new federal OSHA severe-injury report for Arland Tool & Manufacturing, INC is published. One employer, no account, unsubscribe in one click.
Site address
45 FREIGHT HOUSE RD
City
WEST BROOKFIELD
State
MA
ZIP
01585
Mailing
421 MAIN STREET P.O. BOX 207, STURBRIDGE, MA 01566
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
332721
Employees
17
Ownership type
A

6 citations on file for this inspection.

1910.147 C04 I

Serious Gravity 10 1 instance 5 exposed
Issued
May 25, 2023
Abate by
Jul 14, 2023
Penalty
Initial $10,938 · Current $5,470 Reduced
29 CFR  1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section:   45 Freight House Rd, West Brookfield, MA:  On and before April 13, 2023, employees who set up machines, including the Kearny & Trecker machine, only pushed in the emergency stop buttons and did not utilize the written energy control procedures.
Recent events (2)
  • — I (S) $5470
  • — Z (S) $10938

1910.147 C07 I A

Serious Gravity 10 1 instance 5 exposed
Issued
May 25, 2023
Abate by
Jul 14, 2023
Penalty
Initial $0 · Current $0
29 CFR  1910.147(c)(7)(i)(A): Authorized employee(s) did not receive training in the recognition of applicable hazardous energy sources, the type and magnitude of the energy available in the workplace, and the methods and means necessary for energy isolation: 45 Freight House Rd, West Brookfield, MA:  On and before April 13, 2023, employees who set up machines, including the Kearny & Trecker machine, were not trained as authorized employees and were not specifically trained on the written energy control procedures they were expected to use.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.147 C04 II B

Serious Gravity 10 1 instance 5 exposed
Issued
May 25, 2023
Abate by
Jul 14, 2023
Penalty
Initial $10,938 · Current $5,470 Reduced
29 CFR  1910.147(c)(4)(ii)(B):The energy control procedures did not clearly and specifically outline the steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy. 45 Freight House Rd, West Brookfield, MA:  On and before April 13, 2023,  some machine specific energy control procedures did not outline the steps to control all the hazardous energy sources.   The Bliss Mechanical Power Press procedure did not include the stored/kinetic energy of the flywheel or the stored energy of the ram that would need to be blocked or restrained during set up, removal, or replacement of the die.
Recent events (2)
  • — I (S) $5470
  • — Z (S) $10938

1910.147 C04 II C

Serious Gravity 10 1 instance 2 exposed
Issued
May 25, 2023
Abate by
Jul 14, 2023
Penalty
Initial $0 · Current $0
29 CFR  1910.147(c)(4)(ii)(C):The energy control procedure did not clearly and specifically outline the steps for placement, removal and transfer of lockout devices or tagout devices and the responsibility for them. 45 Freight House Rd, West Brookfield, MA:  On and before April 13, 2023,  some machine specific energy control procedures did not identify appropriate lockout devices to control hazardous energy sources.   The energy control procedure for the Komo Asset number 1847 incorrectly listed a ball valve lockout device to lock out a pneumatic quick-disconnect.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.147 C04 II D

Serious Gravity 10 1 instance 7 exposed
Issued
May 25, 2023
Abate by
Jul 14, 2023
Penalty
Initial $0 · Current $0
29 CFR  1910.147(c)(4)(ii)(D):The energy control procedures did not clearly and specifically outline the requirements for testing a machine or equipment to determine and verify the effectiveness of lockout devices, tagout devices, and other energy control 45 Freight House Rd, West Brookfield, MA:  On and before April 13, 2023,  none of the machine specific energy control procedures listed the requirement, or any steps, to verify the effectiveness of the energy control measures.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.147 C06 I

Serious Gravity 10 1 instance 7 exposed
Issued
May 25, 2023
Abate by
Jul 14, 2023
Penalty
Initial $0 · Current $0
29 CFR  1910.147(c)(6)(i):The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: 45 Freight House Rd, West Brookfield, MA:  On and for three years before April 4, 2023, the employer had not performed a comprehensive periodic inspection of energy control procedures including, but not limited to the Kearny & Trecker machine, at least annually to verify that each procedure was adequate and being properly used by employees. *Abatement Notes:  A periodic inspection shall include the following elements:  - Appointment of an authorized employee to inspect each unique procedure for inaccuracies during an actual energy control task  - A review by inspector with each authorized employee, of that employee's responsibilities under each energy control procedure they are authorized to use - Certification that the periodic inspections have been performed by identifying the machines or equipment on which the energy control procedures were being utilized, the dates of the inspections, the employees included in the inspections, and the persons performing the inspections *Abatement notes are intended only to provide clarity regarding existing requirements under the law or agency policies. Abatement notes do not create (or diminish) legal obligations under the Occupational Safety and Health Act.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

View Arland Tool & Manufacturing, INC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 346630296.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.