OSHA Inspection: FEDERAL-MOGUL POWERTRAIN LLC

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of FEDERAL-MOGUL POWERTRAIN LLC in 401 INDUSTRIAL AVE, WAUPUN, WI 53963 (NAICS 332911). OSHA activity number 346674880.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Federal-Mogul Powertrain LLC — free Get an email when a new federal OSHA severe-injury report for Federal-Mogul Powertrain LLC is published. One employer, no account, unsubscribe in one click.
Site address
401 INDUSTRIAL AVE
City
WAUPUN
State
WI
ZIP
53963
Mailing
401 INDUSTRIAL AVE, WAUPUN, WI 53963
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
332911
Employees
170
Ownership type
A

8 citations on file for this inspection.

1910.147 C04 I

Serious Gravity 5 1 instance 1 exposed
Issued
Jun 23, 2023
Abate by
Jul 28, 2023
Penalty
Initial $12,278 · Current $12,278
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section.   a) On or about April 25, 2023, at the previously addressed inspection site, procedures were not utilized to control hazardous energies when employees were servicing, inspecting, and troubleshooting machinery (Cryogenic Chamber #21).
Recent events (2)
  • — I (S) $12278
  • — Z (S) $12278

1910.147 C06 I

Serious Gravity 5 1 instance 1 exposed
Issued
Jun 23, 2023
Abate by
Nov 1, 2023
Penalty
Initial $12,278 · Current $12,278
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed.  a) On or about April 25, 2023, at the previously addressed inspection site, periodic inspections of the energy control procedure for the cryogenic chambers were not conducted at least annually.
Recent events (2)
  • — I (S) $12278
  • — Z (S) $12278

1910.147 D

Deleted Serious Gravity 5 1 instance 1 exposed
Issued
Jun 23, 2023
Abate by
Jul 10, 2023
Penalty
Initial $12,278 · Current $0 Reduced
29 CFR  1910.147(d): The established procedure for the application of energy control (the lockout or tagout procedures) did not cover the actions listed in and was not done in sequence as required by 29 CFR 1910.147(d)(1)-(6).  a) On or about April 25, 2023, at the previously addressed inspection site, employees servicing, inspecting, and troubleshooting machinery (Cryogenic Chamber #21) were exposed to hazardous energies because the steps of an energy control procedure were not performed and applied.
Recent events (2)
  • — I (S) $0
  • — Z (S) $12278

1910.147 D02

Serious Gravity 5 1 instance 1 exposed
Issued
Jun 23, 2023
Abate by
Jul 28, 2023
Penalty
Initial $0 · Current $0
29 CFR 1910.147(d)(2): The machine or equipment was not turned off or shut down using the procedures established for the machine or equipment.  a) On or about April 25, 2023, at the previously addressed inspection site, the Cryogenic chamber #21 was not turned off or shut down using the energy control procedure when employees were servicing, inspecting, and troubleshooting the equipment.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.147 D03

Deleted Serious Gravity 5 1 instance 1 exposed
Issued
Jun 23, 2023
Abate by
Jul 10, 2023
Penalty
Initial $0 · Current $0
29 CFR  1910.147(d)(3): All energy isolating devices that were needed to control the energy to the machine or equipment were not physically located and operated in such a manner as to isolate the machine or equipment from the energy source(s).  a) On or about April 25, 2023, at the previously addressed inspection site, energy isolating devices were not operated in a manner to isolate the Cryogenic Chamber #21 from energy sources when employees were servicing, inspecting, and troubleshooting the machinery.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.147 D04 I

Deleted Serious Gravity 5 1 instance 1 exposed
Issued
Jun 23, 2023
Abate by
Jul 10, 2023
Penalty
Initial $0 · Current $0
29 CFR  1910.147(d)(4)(i): Lockout or tagout devices were not affixed to each energy isolating device by authorized employees.  a) On or about April 25, 2023, at the previously addressed inspection site, lockout devices were not affixed to each energy isolating device when employees were servicing, inspecting, and troubleshooting the machinery (Cryogenic Chamber #21).
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.147 D05 I

Deleted Serious Gravity 5 1 instance 1 exposed
Issued
Jun 23, 2023
Abate by
Jul 10, 2023
Penalty
Initial $0 · Current $0
29 CFR  1910.147(d)(5)(i): All potentially hazardous stored or residual energy was not relieved, disconnected, restrained or otherwise rendered safe after the application of lockout or tagout devices to energy isolating devices.  a) On or about April 25, 2023, at the previously addressed inspection site, stored or residual energy was not relieved, disconnected, restrained, and otherwise rendered safe   when employees were servicing, inspecting, and troubleshooting machinery (Cryogenic Chamber #21).
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.147 D06

Deleted Serious Gravity 5 1 instance 1 exposed
Issued
Jun 23, 2023
Abate by
Jul 10, 2023
Penalty
Initial $0 · Current $0
29 CFR  1910.147(d)(6): Prior to starting work on machines or equipment that had been locked out or tagged out, the authorized employee did not verify that isolation and deenergization of the machine or equipment had been accomplished.  a) On or about April 25, 2023, at the previously addressed inspection site, verification that isolation and deenergization of the machine or equipment was not accomplished when employees were servicing, inspecting, and troubleshooting machinery (Cryogenic Chamber #21).
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

View Federal-Mogul Powertrain LLC's full OSHA safety record →