SPRING, TX —
OSHA Inspection: AGUILAR STUCCO AND ROCK
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of AGUILAR STUCCO AND ROCK in 3140 FM 2920, SPRING, TX 77388 (NAICS 238140). OSHA activity number 346681216.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- AGUILAR STUCCO AND ROCK
- Site address
- 3140 FM 2920
- City
- SPRING
- State
- TX
- ZIP
- 77388
- Mailing
- 3815 WATER CANYON ROAD, BAYTOWN, TX 77521
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 8
- Ownership type
- A
Citations
6 citations on file for this inspection.
1926.25 A
- Issued
- Jun 16, 2023
- Abate by
- Aug 4, 2023
- Penalty
- Initial $4,018 · Current $4,018
General-duty citation text
29 CFR 1926.25(a):During the course of construction, alteration, or repairs, form or scrap lumber with protruding nails was not kept clear from work areas. On or about May 4, 2023, at the construction site, employees were performing stucco work near debris with protruding nails was not kept clear from work areas.
Recent events (1)
- — Z (S) $4018
1926.451 B01
- Issued
- Jun 16, 2023
- Abate by
- Jul 28, 2023
- Penalty
- Initial $4,688 · Current $4,688
General-duty citation text
29 CFR 1926.451(b)(1):Platform(s) on all working levels of scaffolds, were not fully planked or decked between the front uprights and guardrail supports such that the space between adjacent units, and the space between the platform and the uprights is no( On or about May 4, 2023, the employees were performing stucco work on the 2nd level of a scaffold without the working platform being fully planked or decked between the front uprights and the guardrail supports.
Recent events (1)
- — Z (S) $4688
1926.451 C02 I
- Issued
- Jun 16, 2023
- Abate by
- Jul 7, 2023
- Penalty
- Initial $4,688 · Current $4,688
General-duty citation text
29 CFR 1926.451(c)(2)(i): Footings shall be level, sound, rigid, and capable of supporting the loaded scaffold without settling or displacement. On or about May 4, 2023, on the west side of building, the employees were performing stucco work on exterior wall of building from a scaffold with footings unlevel and not capable of supporting the loaded scaffold without settling or displacement.
Recent events (1)
- — Z (S) $4688
1926.451 E01
- Issued
- Jun 16, 2023
- Abate by
- Jul 7, 2023
- Penalty
- Initial $3,349 · Current $3,349
General-duty citation text
29 CFR 1926.451(e)(1):When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Crossbraces were used as a means of access. On or about May 4, 2023, on a construction site located in Conroe, Texas, two employees were working from a scaffold platform without a proper point of access, the employees used the cross bracing as a ladder.
Recent events (1)
- — Z (S) $3349
1926.451 G01 V
- Issued
- Jun 16, 2023
- Abate by
- Jul 7, 2023
- Penalty
- Initial $4,688 · Current $4,688
General-duty citation text
29 CFR 1926.451(g)(1)(v):Each employee on a walkway located within a scaffold was not protected by a guardrail system (with a minimum 200 pound top rail capacity) installed within 9.5 inches (24.1 cm) of and along at least one side of the walkway. On or about May 4, 2023, two employees were performing stucco work to the exterior while using a walkway that was not protected by a guardrail system.
Recent events (1)
- — Z (S) $4688
1926.451 G01 VII
- Issued
- Jun 16, 2023
- Abate by
- Jul 7, 2023
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.451(g)(1)(vii):Each employee on a scaffold, not otherwise specified in paragraphs (g)(1)(i) through (g)(1)(vi) of this section, more than 10 feet (3.1 m) above lower level was not protected from falls by the use of personal fall arrest systems or guardrail systems meeting the requirements of paragraph (g)(4) of this section. On or about May 4, 2023, at a construction site in Spring, Texas, two employees were conducting stucco work on the exterior wall from a scaffold platform more than 10 above a lower lever that was not protected by a personal fall arrest systems or guardrail systems.
Recent events (1)
- — Z (S) $0
More inspections at Aguilar Stucco and Rock
View Aguilar Stucco and Rock's full OSHA safety record →
More inspections in this industry (NAICS 238140)
More inspections in TX
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 346681216.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.