CHARLOTTESVILLE, VA —
OSHA Inspection: ROLLING PLAINS CONSTRUCTION, INC.
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of ROLLING PLAINS CONSTRUCTION, INC. in 2055 BOULDERS ROAD NGIC RIVANNA STATION, CHARLOTTESVILLE, VA 22911 (NAICS 238990). OSHA activity number 346885536.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- ROLLING PLAINS CONSTRUCTION, INC.
- Site address
- 2055 BOULDERS ROAD NGIC RIVANNA STATION
- City
- CHARLOTTESVILLE
- State
- VA
- ZIP
- 22911
- Mailing
- 5136 SOUTH DESERT VIEW DRIVE, APACHE JUNCTION, AZ 85120
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238990
- Employees
- 36
- Ownership type
- A
Citations
4 citations on file for this inspection.
1926.21 B03
- Issued
- Dec 11, 2023
- Abate by
- Jan 8, 2024
- Penalty
- Initial $10,246 · Current $0 Reduced
General-duty citation text
29 CFR 1926.21(b)(3): Employees required to handle or use poisons, caustics, and other harmful substances were not instructed regarding the safe handling and use, and were not made aware of the potential hazards, personal hygiene, and personal protective measures required: a) NGIC Rivanna Station: On or about 07/28/2023, an employees was provided Steel Spec 1003 Shop Coat Primer to spray onto structural steel without being instructed on the safe use of the product. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $10246
1910.134 D01 III
- Issued
- Dec 11, 2023
- Abate by
- Jan 8, 2024
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.134(d)(1)(iii): The employer did not identify and evaluate the respiratory hazard(s) in the workplace; including a reasonable estimate of employee exposures to respiratory hazards and identification of the contaminant's chemical state and physical form: (Construction Reference 1926.103(a)) a) NGIC Rivanna Station: On or about 07/28/2023, the employer failed to assess the employees' workplace (by way of personnel air sampling, or mathematical modeling, or some other means) to determine what hazardous exposure exist when spraying Steel Spec 1003 Shop Coat Primer, what the exposure levels were, and what level of respiratory protection was necessary. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.1200 G08
- Issued
- Dec 11, 2023
- Penalty
- Initial $6,831 · Current $0 Reduced
General-duty citation text
29 CFR 1910.1200(g)(8): The employer did not maintain in the workplace copies of the required safety data sheets for each hazardous chemical, and did not ensure that they were readily accessible during each work shift to employees when they were in their work area(s): a) NGIC Rivanna Station: On or about 07/28/2023, the employer failed to maintain in the work area a copy of the Steel Spec 1003 Shop Coat Primer safety data sheet. No abatement certification or documentation required.
Recent events (2)
- — I (S) $0
- — Z (S) $6831
1910.1200 H01
- Issued
- Dec 11, 2023
- Abate by
- Jan 8, 2024
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.1200(h)(1): Employees were not provided effective information and training on hazardous chemicals in their work area at the time of their initial assignment and whenever a new hazard that the employees had not been previously trained about was introduced into their work area: (Construction Reference: 1926.59) a) NGIC Rivanna Station: On or about 07/28/2023, an employee was required to spray Steel Spec1003 Shop Coat Primer without provided training in the hazards assoicated with the primer. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
More inspections at Rolling Plains Construction, INC.
View Rolling Plains Construction, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 238990)
More inspections in VA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 346885536.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.