On , OSHA opened an unprogrammed Other safety inspection of R&A STONE & STUCCO, LLC in 1653 W STATE STREET, EAGLE, ID 83616 (NAICS 238140). OSHA activity number 346962723.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- R&A STONE & STUCCO, LLC
- Site address
- 1653 W STATE STREET
- City
- EAGLE
- State
- ID
- ZIP
- 83616
- Mailing
- 3511 E DOROTHY LN, NAMPA, ID 83651
What kind of inspection was it?
- Inspection type
- Unprogrammed Other (I)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 4
- Ownership type
- A
Citations
6 citations on file for this inspection.
1926.451 B01
- Issued
- Jan 3, 2024
- Abate by
- Jan 16, 2024
- Penalty
- Initial $4,018 · Current $2,009 Reduced
General-duty citation text
29 CFR 1926.451(b)(1):Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii) (a): On September 7th, 2023 and times prior, employees were working on scaffolding which was only half planked. Note: Abatement certification is required for this item. See enclosed "Certification of Corrective Actions Worksheet."
Recent events (2)
- — I (S) $2009
- — Z (S) $4018
1926.451 G04 I
- Issued
- Jan 3, 2024
- Abate by
- Jan 16, 2024
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.451(g)(4)(i):Guardrail systems were not installed along all open sides and ends of platforms. (a): On September 7th, 2023 and times prior, employees were working on scaffolding that did not have guardrails on open sides, leading to potential falls of 13.5 feet. Abatement Note: Abatement certification and documentation is required for this item. See enclosed "Certification of Corrective Actions Worksheet."
Recent events (2)
- — I (S) $0
- — Z (S) $0
1926.451 E01
- Issued
- Jan 3, 2024
- Abate by
- Jan 23, 2024
- Penalty
- Initial $4,688 · Current $2,344 Reduced
General-duty citation text
29 CFR 1926.451(e)(1):When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Crossbraces were used as a means of access. (a): On September 7th, 2023 and times prior, employees accessed the scaffolding by use of crossbraces, buckets, and the ends of the scaffold. Abatement Note: Abatement certification is required for this item. See enclosed "Certification of Corrective Actions Worksheet."
Recent events (2)
- — I (S) $2344
- — Z (S) $4688
1926.451 E09 IV
- Issued
- Jan 3, 2024
- Abate by
- Jan 16, 2024
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.451(e)(9)(iv):Cross braces on tubular welded frame scaffolds were used as a means of access or egress. (a) On September 7th, 2023 and times prior, employees accessed the scaffolding using the frames instead of ladders or other appropriate measures of access and egress so that they could perform stucco activities. Abatement Note: Abatement certification is required for this item. See enclosed "Certification of Corrective Actions Worksheet."
Recent events (2)
- — I (S) $0
- — Z (S) $0
1926.451 H02 II
- Issued
- Jan 3, 2024
- Abate by
- Jan 30, 2024
- Penalty
- Initial $2,009 · Current $1,005 Reduced
General-duty citation text
29 CFR 1926.451(h)(2)(ii): A toeboard was not erected along the edge of platforms more than 10 feet (3.1 m) above lower levels for a distance sufficient to protect employees below:Note: This requirement does not apply to float (ship) scaffolds where an edging of 3/4 inch x 1 1/2 inch (2 x 4 cm) wood or equivalent was used in lieu of toeboards. (a) On September 7th, 2023 and times prior, employees that were working below the scaffold were not protected from falling materials such as a bucket with stucco and application tools. Abatement Note: Abatement certification is required for this item. See enclosed "Certification of Corrective Actions Worksheet."
Recent events (2)
- — I (S) $1004.5
- — Z (S) $2009
1926.452 C02
- Issued
- Jan 3, 2024
- Abate by
- Jan 16, 2024
- Penalty
- Initial $4,018 · Current $2,009 Reduced
General-duty citation text
29 CFR 1926.452(c)(2):Tubular welded frames and panels were not braced by cross, horizontal, or diagonal braces, or combination thereof, which would have secured vertical members together laterally: (a) On September 7th, 2023 and times prior, employees were working on a scaffold applying stucco that was not fully braced in multiple areas throughout the scaffold. Abatement Note: Abatement certification is required for this item. See enclosed "Certification of Corrective Actions Worksheet."
Recent events (2)
- — I (S) $2009
- — Z (S) $4018
More inspections in this industry (NAICS 238140)
More inspections in ID
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 346962723.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.