OSHA Inspection: PCIROADS, LLC

Planned inspection · Health discipline

On , OSHA opened a planned health inspection of PCIROADS, LLC in WI-70 BRIDGE WI-70, ST. CROIX RIVER BRIDGE PROJECT, GRANTSBURG, WI 54840 (NAICS 237310). OSHA activity number 347039323.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Pciroads, LLC — free Get an email when a new federal OSHA severe-injury report for Pciroads, LLC is published. One employer, no account, unsubscribe in one click.
Establishment
PCIROADS, LLC
Site address
WI-70 BRIDGE WI-70, ST. CROIX RIVER BRIDGE PROJECT
City
GRANTSBURG
State
WI
ZIP
54840
Mailing
14123 42ND STREET NE, SAINT MICHAEL, MN 55376
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
237310
Employees
368
Ownership type
A

8 citations on file for this inspection.

1926.100 A

Deleted Serious Gravity 1 1 instance 2 exposed
Issued
Dec 19, 2023
Penalty
Initial $5,122 · Current $0 Reduced
29 CFR 1926.100(a):  Employees working in areas where there was a possible danger of head injury from impact, or falling or flying objects, or from electrical shock and burns, were not protected by protective helmets:  (a) WI-70 bridge restoration site; Hardhats (protective helmets) were not worn by two workers while they worked beneath the bridge deck from inside a lift platform during bridge restoration activities.
Recent events (3)
  • — F (S) $0
  • — C (S) $5122
  • — Z (S) $5122

1926.106 A

Deleted Serious Gravity 10 1 instance 3 exposed
Issued
Dec 19, 2023
Abate by
Jan 19, 2024
Penalty
Initial $11,953 · Current $0 Reduced
29 CFR 1926.106(a): Employee(s) working over or near water where the danger of drowning existed, were not provided with U.S. Coast Guard approved life jacket(s) or buoyant work vest(s):  (a) WI-70 bridge restoration site; the employer failed to ensure that U.S. Coast Guard approved life jackets or buoyant work vests were worn by employees while they performed bridge rehabilitation activities over a body of water (Saint Croix River) from the platform of a truck mounted aerial lift.
Recent events (3)
  • — F (S) $0
  • — C (S) $11953
  • — Z (S) $11953

1926.106 C

Serious Gravity 10 1 instance 3 exposed
Issued
Dec 19, 2023
Abate by
Dec 1, 2025
Penalty
Initial $0 · Current $13,000
29 CFR 1926.106(c): Ring buoys with at least 90 feet of line were not provided and readily available for emergency rescue operations:  (a) WI-70 bridge restoration site; the employer failed to ensure that at least one ring buoy with 90 feet of line (rope) was readily available while employees performed bridge rehabilitation activities over a body of water (Saint Croix River).
Recent events (3)
  • — F (S) $13000
  • — C (S) $0
  • — Z (S) $0

1926.106 D

Deleted Serious Gravity 10 1 instance 3 exposed
Issued
Dec 19, 2023
Abate by
Jan 19, 2024
Penalty
Initial $0 · Current $0
29 CFR 1926.106(d): A lifesaving skiff was not immediately available at locations where employees were working over or adjacent to water:  (a) WI-70 bridge restoration site; The employer failed to ensure that a lifesaving skiff was readily available while employees performed bridge rehabilitation activities over a body of water (Saint Croix River).
Recent events (3)
  • — F (S) $0
  • — C (S) $0
  • — Z (S) $0

1926.1153 C01

Deleted Serious Gravity 5 1 instance 2 exposed
Issued
Dec 19, 2023
Abate by
Jan 4, 2024
Penalty
Initial $8,539 · Current $0 Reduced

Hazardous substances 9000

29 CFR 1926.1153(c)(1): For each employee engaged in a task identified on Table 1, the employer did not fully and properly implement the engineering controls, work practices, and respiratory protection specified for the task on Table 1, unless the employer assesses and limits the exposure of the employee to respirable crystalline silica in accordance with paragraph (d) of this section:  (a) WI-70 bridge restoration site; On or about October 17, 2023, the employer did not ensure the use of engineering controls and work practices from Table 1 ((xii) Handheld grinders for uses other than mortar removal), specifically a continuous water delivery system or a shroud and dust collection system, to reduce respirable crystalline silica exposures while workers used hand-held angle grinders to grind chamfers (grooves) into the underside of a concrete bridge deck during restoration operations.
Recent events (3)
  • — F (S) $0
  • — C (S) $8539
  • — Z (S) $8539

1904.29 B01

Deleted Other-than-serious 1 instance 3 exposed
Issued
Dec 19, 2023
Abate by
Jan 4, 2024
Penalty
Initial $1,707 · Current $0 Reduced
29 CFR  1904.29(b)(1): The log of occupational injuries and illnesses, (OSHA Form No. 300), was not completed in the detail provided in the form and the instructions contained therein:   PCI Roads, LLC - 14123 42nd St NE, Saint Michael, MN.  On or about October 17, 2023, the employer did not provide the required employee's name (column B) and/or injury or illness description (column F) on the OSHA Form 300 or equivalent for the calendar year 2023.  (a) On or about August 28, 2023, while working at job 21-047 tunnel, an employee identified by only two uppercase letters, slipped struck head, case no. 2023-87.
Recent events (3)
  • — F (O) $0
  • — C (O) $1707
  • — Z (O) $1707

1904.40 A

Other-than-serious 1 instance 3 exposed
Issued
Dec 19, 2023
Abate by
Dec 1, 2025
Penalty
Initial $1,707 · Current $13,000
29 CFR 1904.40(a):  The employer did not provide an authorized government representative the records within the four business hours:  (a) Throughout the establishment; On or about October 17, 2023, the employer failed to provide copies of the injury and illness records (OSHA Forms 300 and 300A) to OSHA within four hours of request for calendar years 2023 through 2018.
Recent events (3)
  • — F (O) $13000
  • — C (O) $1707
  • — Z (O) $1707

1910.1200 G08

Deleted Other-than-serious 1 instance 3 exposed
Issued
Dec 19, 2023
Abate by
Jan 4, 2024
Penalty
Initial $0 · Current $0
29 CFR 1910.1200(g)(8): The employer did not ensure that Safety Data Sheets were readily accessible during each work shift to employees when they were in their work area(s): (Construction Reference: 1926.59):  (a) WI-70 bridge restoration site; Safety data sheets were not available for chemicals being used at this site.
Recent events (3)
  • — F (O) $0
  • — C (O) $0
  • — Z (O) $0

View Pciroads, LLC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 347039323.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.