OSHA Inspection: ONA POLYMERS

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of ONA POLYMERS in 2326 LONNECKER DRIVE, GARLAND, TX 75041 (NAICS 325211). OSHA activity number 347779217.

What this inspection record means

OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch ONA Polymers for free Get an email when a new federal OSHA severe-injury report for ONA Polymers is published. One employer, no account, unsubscribe in one click.
Establishment
ONA POLYMERS
Site address
2326 LONNECKER DRIVE
City
GARLAND
State
TX
ZIP
75041
Mailing
2326 LONNECKER DRIVE, GARLAND, TX 75041
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
Non-union (B)
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
325211
Employees
45
Ownership type
Private (A)

3 citations on file for this inspection.

1910.119 J02

Serious Gravity 10 9 instances 5 exposed
Issued
Mar 21, 2025
Abate by
Apr 9, 2025
Penalty
Initial $11,585 · Current $11,545 Reduced
29 CFR 1910.119(j)(2): The employer did not implement written procedures to maintain the on-going integrity of process equipment   On or about 09/24/2024, at Ona Polymers the employer failed to fully document the 5/10-year written testing and inspection procedures for portions of the process safety management (PSM) covered equipment including, but not limited to the following:  a) Mixed monomer tank 1 (MMT-1/C-201-R) (PID 74155-1-43, rev 1).  b) Vinyl Acetate Tank M-1 (PID GA-M1-L-101-1, rev 1).  c) Mixed monomer tank 4 (C-360) (PID GA-MMT4-P-362-1, rev 4).  d) Reactor 1 (C-205) (PID GA-RX1-P-205-3 rev. 3).  e) Reactor 4 (C-365) (PID GA-RX4-H-367-1, rev 2)  f) Piping segments from Monomer Mixed Tank 4 (C-360) 4"P-7A10-6C12 to 11/2" P-7A11-6C12 to Reactor #4 (C-365) (PID: GA-MMT4-P326-1)  g) Piping segment from Reactor 4(C-365) 6"P-7B10-6C12 To heat exchanger E-366 (PID GA-RX4-H-367-1, rev 2).  h) Piping segments from Reactor 3 (C-265) 4"P-6C12 to Heat Exchanger (E-266) (PID GA-RX3-H-275-1, rev. 1)  i) Piping segment from Monomer Mixed Tank (MMT-3) to Reactor 3 (C-265) (PID GA-MMT3-P-262-1, rev. 4)
Recent events (2)
  • · I (S) $11545
  • · Z (S) $11585

1910.119 J04 I

Serious Gravity 10 9 instances 45 exposed
Issued
Mar 21, 2025
Abate by
Apr 9, 2025
Penalty
Initial $11,585 · Current $0 Reduced
29 CFR 1910.119(j)(4)(i): The employer did not perform inspection and tests on process equipment  On or about 09/24/2024, at Ona Polymers, the employer did not perform inspections and tests on equipment in its PSM-covered process, such as but not limited to the following process equipment:  a) Mixed monomer tank 1 (MMT-1/C-201-R) (PID 74155-1-43, rev 1).  b) Vinyl Acetate Tank M-1 (PID GA-M1-L-101-1, rev 1).  c) Mixed monomer tank 4 (C-360) (PID GA-MMT4-P-362-1, rev 4).  d) Reactor 1 (C-205) (PID GA-RX1-P-205-3 rev. 3).  e) Reactor 4 (C-365) (PID GA-RX4-H-367-1, rev 2)  f) Piping segments from Monomer Mixed Tank 4 (C-360) 4"P-7A10-6C12 to 11/2" P-7A11-6C12 to Reactor #4 (C-365) (PID: GA-MMT4-P326-1)  g) Piping segment from Reactor 4(C-365) 6"P-7B10-6C12 To heat exchanger E-366 (PID GA-RX4-H-367-1, rev 2).  h) Piping segments from Reactor 3 (C-265) 4"P-6C12 to Heat Exchanger (E-266) (PID GA-RX3-H-275-1, rev. 1)  i) Piping segment from Monomer Mixed Tank (MMT-3) to Reactor 3 (C-265) (PID GA-MMT3-P-262-1, rev. 4)
Recent events (2)
  • · I (S) $0
  • · Z (S) $11585

1910.119 J04 III

Serious Gravity 10 1 instance 5 exposed
Issued
Mar 21, 2025
Abate by
Apr 9, 2025
Penalty
Initial $11,585 · Current $6,955 Reduced
29 CFR  1910.119(j)(4)(iii):The frequency of inspections and tests of process equipment shall be consistent with applicable manufacturers' recommendations and good engineering practices, and more frequently if determined to be necessary by prior operating experience.  On or about 09/24/2024, at Ona Polymers, the employer did not perform tests on Vinyl Acetate Tank (M-1) consistent with applicable manufacturers' recommendations and good engineering practices, such as but not limited to American Petroleum Institute 510 and more frequently if determined to be necessary by prior operating experience.
Recent events (2)
  • · I (S) $6955
  • · Z (S) $11585