Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: BOISE CASCADE BUILDING MATERIALS DISTRIBUTION, LLC

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of BOISE CASCADE BUILDING MATERIALS DISTRIBUTION, LLC in 34 COUNCIL AVENUE, WHEATLAND, PA 16161 (NAICS 444190). OSHA activity number 348079237.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Boise Cascade Building Materials Distribution, LLC — free Get an email when a new federal OSHA severe-injury report for Boise Cascade Building Materials Distribution, LLC is published. One employer, no account, unsubscribe in one click.
Site address
34 COUNCIL AVENUE
City
WHEATLAND
State
PA
ZIP
16161
Mailing
34 COUNCIL AVENUE, WHEATLAND, PA 16161
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
444190
Employees
12
Ownership type
A

3 citations on file for this inspection.

1910.178 Q07

Serious Gravity 1 1 instance 9 exposed
Issued
Mar 26, 2025
Abate by
Apr 21, 2025
Penalty
Initial $6,029 · Current $4,220 Reduced
CFR 1910.178(q)(7): Industrial trucks were not examined before being placed into service:  a.)  Boise Cascade Building Materials Distribution, LLC dba Boise Cascade Company - on or about 3/4/25, and at times prior thereto,  overhead guard covers on forklifts including, but not limited to, Toyota forklift (serial #10292, Model #BFG5OU) were not included in the pre-shift examination inspection.  ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below).  This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $4220.3
  • — Z (S) $6029

1910.178 L03 I J

Serious Gravity 1 1 instance 9 exposed
Issued
Mar 26, 2025
Abate by
Apr 21, 2025
Penalty
Initial $0 · Current $0
29 CFR  1910.178(l)(3)(i)(J): The employer did not provide training for any vehicle inspection the operator will be required to perform.    a.)  Boise Cascade Building Materials Distribution, LLC dba Boise Cascade Company - on or about 3/4/25, and at times prior thereto,  the company had not provided training  on inspecting the straps for overhead guard covers on forklifts including, but not limited to, Toyota forklift (serial #10292, Model #BFG5OU).  ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below).  This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1904.29 B01

Other-than-serious 1 instance 7 exposed
Issued
Mar 26, 2025
Abate by
Apr 21, 2025
Penalty
Initial $0 · Current $0
29 CFR  1904.29(b)(1):A Log of all recordable work-related injuries and illnesses (OSHA Form 300 or equivalent), was not completed in the detail as required by the regulation.  a.)  Boise Cascade Building Materials Distribution, LLC dba Boise Cascade Company - On or about 3/4/25, and at times prior thereto,  Column F on the OSHA 300 Injury and Illness log did not list the injury sustained by the employee.  This occurred in Calendar Year 2025 on case #0490WC-25-0300031 which happened on 2/27/25.  ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below).  This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

View Boise Cascade Building Materials Distribution, LLC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 348079237.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.