ELK GROVE VILLAGE, IL —
OSHA Inspection: MATERIAL SCIENCES CORPORATION
Complaint inspection · Safety discipline
At a glance
On , OSHA opened a complaint safety inspection of MATERIAL SCIENCES CORPORATION in 2250 E. PRATT BLVD., ELK GROVE VILLAGE, IL 60007 (NAICS 332812). OSHA activity number 348360207.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- MATERIAL SCIENCES CORPORATION
- Site address
- 2250 E. PRATT BLVD.
- City
- ELK GROVE VILLAGE
- State
- IL
- ZIP
- 60007
- Mailing
- 2250 E. PRATT BLVD., ELK GROVE VILLAGE, IL 60007
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- A
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 332812
- Employees
- 70
- Ownership type
- A
Citations
5 citations on file for this inspection.
1910.28 B01 I
- Issued
- Aug 26, 2025
- Abate by
- Sep 29, 2025
- Penalty
- Initial $8,513 · Current $7,000 Reduced
General-duty citation text
29 CFR 1910.28(b)(1)(i): Except as provided elsewhere in this section 29 CFR 1910.28, the employer did not ensure that each employee on a walking-working surface with an unprotected side or edge that is 4 feet (1.2 m) or more above a lower level is protected from falling by one or more of the systems described in 29 CFR 1910.28(b)(1)(i): (a) Line 4 - On or about July 22, 2025, employees working on the Line 4 film under winder platform were approximately 10 feet above the ground with unprotected edges exposing employees to fall hazards. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- — I (S) $7000
- — Z (S) $8513
1910.146 D03 III
- Issued
- Aug 26, 2025
- Abate by
- Sep 29, 2025
- Penalty
- Initial $11,916 · Current $9,500 Reduced
General-duty citation text
29 CFR 1910.146(d)(3)(iii): Under the permit-required confined space program required by 29 CFR 1910.146(c)(4), the employer did not develop and implement the means, procedures, and practices necessary for safe permit space entry operations, including isolating the permit space: (a) Line 4 : On March 4, 2025, the employer did not develop and implement the means, procedures, and practices necessary to isolate gas valves on Line 4 prior to oven entries by employees for strip repairs. (b) Line 4 : On March 22, 2025, the employer did not develop and implement the means, procedures, and practices necessary to isolate gas valves on Line 4 prior to oven entries by employees for strip repairs. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- — I (S) $9500
- — Z (S) $11916
1910.146 K01
- Issued
- Aug 26, 2025
- Abate by
- Sep 29, 2025
- Penalty
- Initial $11,916 · Current $5,983 Reduced
General-duty citation text
29 CFR 1910.146(k)(1)(i): When designating rescue and emergency services pursuant to 29 CFR 1910.146(d)(9), the employer did not evaluate the prospective rescuer's ability to respond to a rescue summons in a timely manner, considering the hazard(s) identified: (a) Line 4 - On March 4, 2025, the employer did not evaluated the Elk Grove Fire Department's ability to respond to a rescue summons in a timely manner for oven entries prior to entry into those spaces. (b) Line 4 - On March 22, 2025, the employer did not evaluate the Elk Grove Fire Department's ability to respond to a rescue summons in a timely manner for oven entries prior to entry into those spaces. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- — I (S) $5982.7
- — Z (S) $11916
1910.178 M02
- Issued
- Aug 26, 2025
- Abate by
- Oct 1, 2025
- Penalty
- Initial $11,916 · Current $8,500 Reduced
General-duty citation text
29 CFR 1910.178(m)(2): Employee(s) stood under or passed under the elevated portion of a powered industrial truck(s): (a) Line 4: On July 22, 2022, employees assigned to change out laminating roll passed under elevated forks to gain access to areas on the line during the removal and installation of the laminating roll. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- — I (S) $8500
- — Z (S) $11916
1910.178 A04
- Issued
- Aug 26, 2025
- Abate by
- Oct 14, 2025
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.178(a)(4): Modifications or additions which affect capacity and safe operation of powered industrial truck were performed by the employer without the manufacturer's prior written approval: (a) Facility Wide- On or about July 9, 2025, the employer did not ensure manufacturer's written approval was received prior to the use of the Hercules Model B6-48 boom attachment on powered industrial vehicles. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- — I (O) $0
- — Z (O) $0
More inspections at Material Sciences Corporation
View Material Sciences Corporation's full OSHA safety record →
More inspections in this industry (NAICS 332812)
More inspections in IL
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 348360207.