OSHA Inspection: MATERIAL SCIENCES CORPORATION

Complaint inspection · Safety discipline

On , OSHA opened a complaint safety inspection of MATERIAL SCIENCES CORPORATION in 2250 E. PRATT BLVD., ELK GROVE VILLAGE, IL 60007 (NAICS 332812). OSHA activity number 348360207.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Material Sciences Corporation — free Get an email when a new federal OSHA severe-injury report for Material Sciences Corporation is published. One employer, no account, unsubscribe in one click.
Site address
2250 E. PRATT BLVD.
City
ELK GROVE VILLAGE
State
IL
ZIP
60007
Mailing
2250 E. PRATT BLVD., ELK GROVE VILLAGE, IL 60007
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
332812
Employees
70
Ownership type
A

5 citations on file for this inspection.

1910.28 B01 I

Serious Gravity 5 1 instance 1 exposed
Issued
Aug 26, 2025
Abate by
Sep 29, 2025
Penalty
Initial $8,513 · Current $7,000 Reduced
29 CFR  1910.28(b)(1)(i): Except as provided elsewhere in this section 29 CFR 1910.28, the employer did not ensure that each employee on a walking-working surface with an unprotected side or edge that is 4 feet (1.2 m) or more above a lower level is protected from falling by one or more of the systems described in 29 CFR 1910.28(b)(1)(i):  (a) Line 4 - On or about July 22, 2025, employees working on the Line 4 film under winder platform were approximately 10 feet above the ground with unprotected edges exposing employees to fall hazards.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $7000
  • — Z (S) $8513

1910.146 D03 III

Serious Gravity 10 2 instances 2 exposed
Issued
Aug 26, 2025
Abate by
Sep 29, 2025
Penalty
Initial $11,916 · Current $9,500 Reduced
29 CFR  1910.146(d)(3)(iii): Under the permit-required confined space program required by 29 CFR 1910.146(c)(4), the employer did not develop and implement the means, procedures, and practices necessary for safe permit space entry operations, including isolating the permit space:   (a) Line 4 : On March 4, 2025,  the employer did not develop and implement the means, procedures, and practices necessary to isolate gas valves on Line 4 prior to oven entries by employees for strip repairs.  (b) Line 4 : On March 22, 2025,  the employer did not develop and implement the means, procedures, and practices necessary to isolate gas valves on Line 4 prior to oven entries by employees for strip repairs.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $9500
  • — Z (S) $11916

1910.146 K01

Serious Gravity 10 2 instances 2 exposed
Issued
Aug 26, 2025
Abate by
Sep 29, 2025
Penalty
Initial $11,916 · Current $5,983 Reduced
29 CFR 1910.146(k)(1)(i):  When designating rescue and emergency services pursuant to 29 CFR 1910.146(d)(9), the employer did not evaluate the prospective rescuer's ability to respond to a rescue summons in a timely manner, considering the hazard(s) identified:  (a) Line 4 - On March 4, 2025, the employer did not evaluated the Elk Grove Fire Department's ability to respond to a rescue summons in a timely manner for oven entries prior to entry into those spaces.  (b) Line 4 - On March 22, 2025, the employer did not evaluate the Elk Grove Fire Department's ability to respond to a rescue summons in a timely manner for oven entries prior to entry into those spaces.    In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $5982.7
  • — Z (S) $11916

1910.178 M02

Serious Gravity 10 1 instance 1 exposed
Issued
Aug 26, 2025
Abate by
Oct 1, 2025
Penalty
Initial $11,916 · Current $8,500 Reduced
29 CFR  1910.178(m)(2): Employee(s) stood under or passed under the elevated portion of a powered industrial truck(s):  (a) Line 4: On July 22, 2022, employees assigned to change out laminating roll passed under elevated forks to gain access to areas on the line during the removal and installation of the laminating roll.   In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $8500
  • — Z (S) $11916

1910.178 A04

Other-than-serious 1 instance 1 exposed
Issued
Aug 26, 2025
Abate by
Oct 14, 2025
Penalty
Initial $0 · Current $0
29 CFR  1910.178(a)(4): Modifications or additions which affect capacity and safe operation of powered industrial truck were performed by the employer without the manufacturer's prior written approval:  (a) Facility Wide- On or about July 9, 2025, the employer did not ensure  manufacturer's written approval was received prior to the use of the Hercules Model B6-48 boom attachment on powered industrial vehicles.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

View Material Sciences Corporation's full OSHA safety record →