RINCON, GA —
OSHA Inspection: MORRIS-SHEA BRIDGE COMPANY, INC.
Accident-driven inspection · Safety discipline
At a glance
On , OSHA opened an accident-driven safety inspection of MORRIS-SHEA BRIDGE COMPANY, INC. in BAKER HILL RD FORT HOWARD PAPER CO., RINCON, GA 31326 (NAICS 000000). OSHA activity number 101054229.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- MORRIS-SHEA BRIDGE COMPANY, INC.
- Site address
- BAKER HILL RD FORT HOWARD PAPER CO.
- City
- RINCON
- State
- GA
- ZIP
- 31326
- Mailing
- P. O. BOX 7446-A, BIRMINGHAM, AL 35253
What kind of inspection was it?
- Inspection type
- Accident-driven (A)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- N
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 000000
- SIC code (legacy)
- 1629
- Employees
- 6
- Ownership type
- A
- Industry flags
- Construction safety.
Citations
1 citation on file for this inspection.
5(a)(1)
- Issued
- Jul 13, 1988
- Abate by
- Jul 16, 1988
- Penalty
- Initial $640 · Current $640
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to the uncontrolled toppling of free-standing waste sections of prestressed precast reinforced concrete piling that had been partially sheared at elevation grade with a model 2400 Hydraulic Power Systems Inc., "Pile Beaver" hydraulic cutter at the Pulp Processing Building No. 35 area by Building No. 5 on or about 6/4/88. Among other methods, one feasible and acceptable abatement method to correct this hazard is: a) In one complete operation, so that employees are not required to work in proximity to any free-standing partially sheared piling, REMOVE ONE WASTE SECTION OF PILING AT A TIME; b) During use of a hydraulic cutter at grade elevation to shear a piling employees must be required to stay out of the trajectory, unless the employer can secure the waste section in such a manner (such as with the crane) that would prevent toppling; c) For a partially sheared piling that requires oxy-acetylene burning of the strands to complete a cut, the waste section of the standing piling must be secured in such a manner that oxy-acetylene burning will not cause the waste section of piling to topple until the employee who is using the torch can withdraw from the trajectory around the piling.
More inspections at Morris-Shea Bridge Company, INC.
View Morris-Shea Bridge Company, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 000000)
More inspections in GA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 101054229.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.