OSHA Inspection: GEORGE CAMPBELL PAINTING CORP.

Accident-driven inspection · Safety discipline

On , OSHA opened an accident-driven safety inspection of GEORGE CAMPBELL PAINTING CORP. in WALT WHITMAN BRIDGE, GLOUCESTER CITY, NJ 08030 (NAICS 000000). OSHA activity number 107356370.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch George Campbell Painting Corp. — free Get an email when a new federal OSHA severe-injury report for George Campbell Painting Corp. is published. One employer, no account, unsubscribe in one click.
Site address
WALT WHITMAN BRIDGE
City
GLOUCESTER CITY
State
NJ
ZIP
08030
Mailing
31-40 COLLEGE POINT BLVD., FLUSHING, NY 11354
Inspection type
Accident-driven (A)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
Y
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
000000
SIC code (legacy)
1721
Employees
18
Ownership type
A
Industry flags
Construction safety.

8 citations on file for this inspection.

5(a)(1)

Deleted Serious Gravity 10 1 instance 18 exposed
Issued
Mar 1, 1993
Abate by
Mar 4, 1993
Penalty
Initial $7,000 · Current $7,000
The alleged violations below have been  grouped  because  they  involve
%%
similar or related hazards that may increase the potential  for  injury
resulting from an accident.
1a
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not furnish employment and a place of employment which were
free from recognized hazards that were causing or likely to cause death
or serious physical harm to employees in that employees were exposed to
falls from an elevation where the load imposed on the manila rope being
used to suspend the scaffold exceeded the safe working load of the rope.
a)  N. J. side of the Walt Whitman Bridge, the 1st of nine
two point suspended scaffolds on the West side of the Jersey
Tower and North side of the bridge roadway.  The scaffold
was occupied by two employees engaged in blasting/painting
operations on the bridge's main suspension cable.  The
scaffold was approximately 365 feet above the adjacent ground/
water level.
Among other methods one feasible and acceptable method to correct
the hazard is to place the scaffold platform on a safe surface.
Recent events (2)
  • — F (S) $7000.00
  • — Z (S) $7000.00

5(a)(1)

Serious Gravity 10 1 instance 18 exposed
Issued
Mar 1, 1993
Abate by
Mar 4, 1993
Penalty
Initial $7,000 · Current $3,500 Reduced
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
%%
employer did not furnish employment and a place of employment which were
free from recognized hazasrds that were causing or likely to cause death
or serious physical harm to employees in that employees were exposed to
fall(s) from an elevation of approximately 365 feet.  Support wire rope
did not employ a thimble nor was the eye of the wire rope secured by "J"
clamps properly torqued.
a)  Walt Whitman Bridge, New Jersey side of the bridge West
side of the New Jersey Tower, north side of bridge.
Scaffoldings
occupied by employees that were supported by wire ropes
reeved through Sky Climber hoists and then looped around the
bridges main support cable and fashioned into an eye and
secured to itself.
Among other methods, one feasible and acceptable method to
correct the hazard would be to secure the wire rope to a
choker that would be looped around the main suspension cable.
The eye formed in the wire rope would then be fitted with a
thimble and the eye on the wire rope would be secured by a
"J" clamp properly installed and torqued as per manufacturer's
recommendations.
For assistance refer to:  Sky Climber Operating Manual and the
Rigging Manual compiled by the Construction Safety Association
of Ontario.
Recent events (2)
  • — F (S) $3500.00
  • — Z (S) $7000.00

5(a)(1)

Serious Gravity 10 1 instance 18 exposed
Issued
Mar 1, 1993
Abate by
Mar 4, 1993
Penalty
Initial $7,000 · Current $4,000 Reduced
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
%%
employer did not furnish employment and a place of employment which
were free from recognized hazards that were causing or likely to cause
death or serious physical harm to employees in that employees were
exposed to fall(s) from an elevation.  The hoist on the west side
of the scaffold nearest the Philadelphia side of the bridge was
supporting
a load that exceeded its" rated working load (RWL).
a)  New Jersey side of the Walt Whitman Bridge, the
first of nine two point suspended scaffolds on the
West Side of the New Jersey Tower and the North Side
of the bridge roadway.  The scaffold was occupied
by two employees engaged in blasting and painting
operations on teh bridge's main support cable.  The
scaffold was approximately 365' above ground level.
Among other methods, one feasible and acceptable abatement method
to correct this hazard is by lessening the load imposed on the
hoist and/or to evenly distribute the load between the two
supporting
hoists.  For assistance refer to:
1)  Sky Climber Manual
2)  SIA pamphlet.
Recent events (2)
  • — F (S) $4000.00
  • — Z (S) $7000.00

1926.21 B02

Serious Gravity 10 1 instance 18 exposed
Issued
Mar 1, 1993
Abate by
Mar 4, 1993
Penalty
Initial $7,000 · Current $4,000 Reduced
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
%%
employer did not furnish employment and a place of employment which
were free from recognized hazards that were causing or likely to cause
death or serious physical harm to employees in that employees were
exposed to fall(s) from an elevation while scaffold was being
transferred  along the main cable while being suspended in air rather
than being placed on a safe surface before making the move(s).
a)  N. J. side of the Walt Whitman Bridge, the first
of nine two point suspended scaffolds located between
bents number 68 and 50 on the West Side of the Jesey
Tower and the North Side of the bridge roadway.  The
scaffold was being used by employees engaged in blasting/
painting operations on the bridge's main suspension cable
approximately 367 feet above the adjacent ground/water
level.
Among other methods, one feasible and acceptable method
to correct the hazard is to lower the scaffold(s) to the
bridge roadway when performing transfer operations.
For assistance refer to Sky Climber, Inc. Instruction
Manual Model 4 Hoist Section 1.8.
Recent events (2)
  • — F (S) $4000.00
  • — Z (S) $7000.00

1926.451 A03

Serious Gravity 10 9 instances 8 exposed
Issued
Mar 1, 1993
Abate by
Mar 4, 1993
Penalty
Initial $70,000 · Current $7,000 Reduced
Recent events (2)
  • — F (S) $7000.00
  • — Z (W) $70000.00

1904.2 A

Other-than-serious Gravity 10 1 instance 10 exposed
Issued
Mar 1, 1993
Abate by
Mar 4, 1993
Penalty
Initial $1,000 · Current $500 Reduced
Recent events (2)
  • — F (O) $500.00
  • — Z (O) $1000.00

5(a)(1)

Deleted Willful Gravity 10 9 instances 8 exposed
Issued
Feb 2, 1993
Abate by
Feb 5, 1993
Penalty
Initial $70,000 · Current $70,000
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not furnish employment and a place of employment which
were free from recognized hazards that were causing or likely to cause
death or serious physical harm to employees in that employees were
exposed to falls from an elevation.  The work was being conducted from
scaffold(s) where the load imposed on the scaffold(s) exceeded the rated
load of the scaffold platform(s).
a)  N.J. side of the Walt Whitman Bridge, nine
two point suspended scaffolds on the west side
of the Jersey Tower and north side of the bridge
roadway.  The scaffold was occupied by employee(s)
engaged in blasting/painting operations on the
bridge's main suspension cable.  The scaffold(s)
were between 190 to 367 feet above the adjacent
ground/water level.
Among other methods, one feasible and acceptable method to correct
the hazard is to reduce the load on the scaffold(s) to at or below
the rated load of the scaffold platform(s) in use at the site or to
utilize scaffold platform(s) with a rated load that exceeds the
load(s) being applied to the scaffold(s).
For assistance refer to Sky Climbers Instruction manual Section
1-2-9 or to pamphlet entitled Guidelines for Safe Practices for
suspended powered scaffolds, Section E, Item 2 issued by the
Scaffold Industry Assn.  The company could also follow the Loading
Instructions contained in the scaffold platform(s) manufacturer's
specifications.
Recent events (2)
  • — F (W) $70000.00
  • — Z (W) $70000.00

5(a)(1)

Serious Gravity 10 18 instances 9 exposed
Issued
Feb 2, 1993
Abate by
Feb 5, 1993
Penalty
Initial $70,000 · Current $5,000 Reduced
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not furnish employment and a place of employment which
were free from recognized hazards that were causing or likely to cause
death or serious physical harm to employees in that employees were
exposed to falls from an elevation.  The scaffold(s) were between
190 to 367 feet above the adjacent ground/water level and the scaffold(s)
was/were being raised and lowered by the traction hoisting machines that
were being operated without secondary emergency brakes designed to act
directly on the suspension cables and are intended to automatically
prevent the decent of the hoist and its suspended load under overspeed
conditions.
a)  N.J. side of the Walt Whitman Bridge, nine 2 point
suspension scaffolds located between bents numbers 68 and
50 on the West Side of the Jersey Tower and the north
side of the bridge roadway.  The scaffolds were operated
by employees engaged in blasting/painting operations on
on the bridge's main suspension cable.
Among other methods, one feasible and acceptable method to correct
the hazard is to install Sky Lock Overspeed Brake Safety Devices
on each of the eighteen (18) Sky Climber Hoisting Machines being
used at the site.
For assistance refer to Sky Climber, Inc. Instruction Manual Model
4 Hoist Sections 2.1, 2:3, 3.1, 3.5 and 5.4.
Recent events (2)
  • — F (S) $5000.00
  • — Z (W) $70000.00

View George Campbell Painting Corp.'s full OSHA safety record →