On , OSHA opened an accident-driven safety inspection of TEWKSBURY INDUSTRIES, INC. in 860 EAST STREET, TEWKSBURY, MA 01876 (NAICS 000000). OSHA activity number 109627174.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- TEWKSBURY INDUSTRIES, INC.
- Site address
- 860 EAST STREET
- City
- TEWKSBURY
- State
- MA
- ZIP
- 01876
What kind of inspection was it?
- Inspection type
- Accident-driven (A)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- N
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 000000
- SIC code (legacy)
- 5093
- Employees
- 60
- Ownership type
- A
Citations
39 citations on file for this inspection.
5(a)(1)
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $5,000 · Current $5,000
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to: severe traumatic injuries secondary to untimely emergency response. (a) Location: Shredder/Cyclone Separator; Employees working near conveyors did not know the location of emergency stop devices. In an emergency situation employees would be unable to stop the conveyor which could significantly increase the severity of an in running nip point injury. One feasible and acceptable method to correct this hazard is to instruct employees as to the location of emergency stop devices in accordance with ANSI B20.1 -1990. (b) The emergency stop device for the feed conveyor was inoperable in that the red contact button was missing. In an emergency situation employees would be unable to stop the conveyor which could significantly increase the severity of an in running nip point injury. One feasible and acceptable method to correct this hazard is to conduct routine inspections and corrective maintenance to ensure guards and safety devices are functioning properly in accordance with ANSI standard B 20. 1-1990.
Recent events (2)
- — Z (S) $5000.00
- — I (U) $5000.00
5(a)(1)
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,000 · Current $2,000
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The %% employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to: loads or slings slipping from hooks on hoisting equipment. Among other methods, one feasible and acceptable method to correct this hazard is to inspect hoists in accordance with ANSI standard B30.16-1987. (a) Shredder Area: The Employer did not inspect the overhead hoist for damage or defects.
Recent events (2)
- — Z (S) $2000.00
- — I (U) $2000.00
1910.23 A09
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $1,500 · Current $1,500
Recent events (2)
- — Z (S) $1500.00
- — I (U) $1500.00
1910.23 C01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,000 · Current $2,000
Recent events (2)
- — Z (S) $2000.00
- — I (U) $2000.00
1910.23 C01
- Issued
- Jan 25, 1995
- Abate by
- Feb 10, 1995
Recent events (2)
- — Z (S)
- — I (U)
1910.23 D01 III
- Issued
- Jan 25, 1995
- Abate by
- Feb 10, 1995
- Penalty
- Initial $1,500 · Current $1,500
Recent events (2)
- — Z (S) $1500.00
- — I (U) $1500.00
1910.24 F
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $1,500 · Current $1,500
Recent events (2)
- — Z (S) $1500.00
- — I (U) $1500.00
1910.146 C01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,500 · Current $2,500
Recent events (2)
- — Z (S) $2500.00
- — I (U) $2500.00
1910.146 C02
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,500 · Current $2,500
Recent events (2)
- — Z (S) $2500.00
- — I (U) $2500.00
1910.146 C04
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,500 · Current $2,500
Recent events (2)
- — Z (S) $2500.00
- — I (U) $2500.00
1910.146 D09
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,500 · Current $2,500
Recent events (2)
- — Z (S) $2500.00
- — I (U) $2500.00
1910.146 G01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,500 · Current $2,500
Recent events (2)
- — Z (S) $2500.00
- — I (U) $2500.00
1910.147 C08
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,500 · Current $2,500
Recent events (2)
- — Z (S) $2500.00
- — I (U) $2500.00
1910.180 D04
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,000 · Current $2,000
Recent events (2)
- — Z (S) $2000.00
- — I (U) $2000.00
1910.180 D06
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,000 · Current $2,000
Recent events (2)
- — Z (S) $2000.00
- — I (U) $2000.00
1910.180 G01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,000 · Current $2,000
Recent events (2)
- — Z (S) $2000.00
- — I (U) $2000.00
1910.184 F05 III
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,000 · Current $2,000
Recent events (2)
- — Z (S) $2000.00
- — I (U) $2000.00
1910.212 A01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $5,000 · Current $5,000
Recent events (2)
- — Z (S) $5000.00
- — I (U) $5000.00
1910.212 A01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
Recent events (2)
- — Z (S)
- — I (U)
1910.219 C04 I
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $1,500 · Current $1,500
Recent events (2)
- — Z (S) $1500.00
- — I (U) $1500.00
1910.219 F03
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,000 · Current $2,000
Recent events (2)
- — Z (S) $2000.00
- — I (U) $2000.00
1910.303 B02
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $2,000 · Current $2,000
Recent events (2)
- — Z (S) $2000.00
- — I (U) $2000.00
1910.304 F04
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $1,500 · Current $1,500
Recent events (2)
- — Z (S) $1500.00
- — I (U) $1500.00
1910.305 B01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $1,500 · Current $1,500
Recent events (2)
- — Z (S) $1500.00
- — I (U) $1500.00
1910.305 B01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
Recent events (2)
- — Z (S)
- — I (U)
1910.305 G01 I
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $1,500 · Current $1,500
Recent events (2)
- — Z (S) $1500.00
- — I (U) $1500.00
1910.305 G02 II
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $1,500 · Current $1,500
Recent events (2)
- — Z (S) $1500.00
- — I (U) $1500.00
1910.95 B01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $57,000 · Current $57,000
8111
Recent events (2)
- — Z (W) $57000.00
- — I (U) $57000.00
1910.95 D01
- Issued
- Jan 25, 1995
- Abate by
- Feb 25, 1995
8111
Recent events (2)
- — Z (W)
- — I (U)
1910.95 G01
- Issued
- Jan 25, 1995
- Abate by
- Jun 25, 1995
8111
Recent events (2)
- — Z (W)
- — I (U)
1910.95 K01
- Issued
- Jan 25, 1995
- Abate by
- Feb 25, 1995
8111
Recent events (2)
- — Z (W)
- — I (U)
1910.147 C04 I
- Issued
- Jan 25, 1995
- Abate by
- Feb 25, 1995
- Penalty
- Initial $70,000 · Current $70,000
Recent events (2)
- — Z (W) $70000.00
- — I (U) $70000.00
1910.147 C07 I
- Issued
- Jan 25, 1995
- Abate by
- Feb 25, 1995
Recent events (2)
- — Z (W)
- — I (U)
1910.212 A01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $70,000 · Current $70,000
Recent events (2)
- — Z (W) $70000.00
- — I (U) $70000.00
1910.212 A01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $70,000 · Current $70,000
Recent events (2)
- — Z (W) $70000.00
- — I (U) $70000.00
1910.212 A01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $70,000 · Current $70,000
Recent events (2)
- — Z (W) $70000.00
- — I (U) $70000.00
1910.212 A01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $70,000 · Current $70,000
Recent events (2)
- — I (U) $70000.00
- — Z (W) $70000.00
1910.212 A01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $70,000 · Current $70,000
Recent events (2)
- — Z (W) $70000.00
- — I (U) $70000.00
1910.212 A01
- Issued
- Jan 25, 1995
- Abate by
- Feb 3, 1995
- Penalty
- Initial $70,000 · Current $70,000
Recent events (2)
- — Z (W) $70000.00
- — I (U) $70000.00
More inspections at Tewksbury Industries, INC.
View Tewksbury Industries, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 000000)
More inspections in MA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 109627174.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.