ERIE, PA —
OSHA Inspection: EMI COMPANY, INC.
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of EMI COMPANY, INC. in 603 WEST 12TH STREET, ERIE, PA 16501 (NAICS 000000). OSHA activity number 113345797.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- EMI COMPANY, INC.
- Site address
- 603 WEST 12TH STREET
- City
- ERIE
- State
- PA
- ZIP
- 16501
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- Y
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Data loaded
Establishment context
- NAICS code
- 000000
- SIC code (legacy)
- 3322
- Employees
- 330
- Ownership type
- A
- Industry flags
- Manufacturing safety.
Citations
127 citations on file for this inspection.
5(a)(1)
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $4,300 · Current $4,300
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to a crushing hazard due to being struck by a moving car conveyor or caught between the moving car conveyor and equipment structures when the conveyor is manually started: a) Roto-Pour Area - The roto-pour car conveyor was not provided with an audible and/or visual alarm device to alert employees that the conveyor is about to start, when operated from the remote override control station, during cleaning operations. Among other methods, one feasible and acceptable abatement method to correct this hazard is to: 1. Install a audible and/or visual alarm device which will be activated when the manual override control station is operated, that can be clearly heard and/or seen at all points along the car conveyor. Reference ANSI B.20.1, Section 5.112(b)(1) 1987. 2. Permit only trained employees to operate car conveyor. Reference ANSI B.20.1, Section 5.12(a) 1987.
5(a)(1)
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $4,300 · Current $4,300
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to a crushing hazard due to being struck by a moving car conveyor or caught between the moving car conveyor and equipment structures when the conveyor is manually started: a) Roto-Pour Area - The roto-pour cooling structure was not provided with a barrier guard on the West side approximately 63 inches high and 126 inches wide to prevent employee entry while the car conveyor was in motion. Among other methods, one feasible and acceptable abatement method to correct this hazard is to: 1. Provide barrier guards to prevent entry into shear points along the car conveyor. Reference ANSI B.20.1, Section 5.9.3, 1987. b) Roto-Pour Area - The car conveyor was not provided with a barrier guard to prevent employee contact with moving cars while setting core on the East side of the mold line.
5(a)(1)
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,650 · Current $1,650
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to a crushing hazard due to being caught in the rotating tail pulley and belt when cleaning the belt conveyor while the belt conveyor is in motion: a) Asico Unit - The tail pulley was not provided with a guard to prevent employee contact with rotating belt and tail pulley when cleaning the belt conveyor while the belt conveyor is in motion. Among other methods, one feasible and acceptable abatement method to correct this hazard is to: 1. Provide a guard for the tail pulley of the belt conveyor. Reference ANSI B.20.1, Section 6.1.1(a)(2), 1987.
5(a)(1)
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,650 · Current $1,650
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to a crushing hazard due to being caught in nip points along the belt conveyor when cleaning the belt area while the belt is in motion: a) Aisco Unit - The spill sand belt conveyor was not provided with an emergency pull cord to stop the belt conveyor in the event an employee was caught in the nip points along the conveyor during cleaning operations when the belt is in operation. Among other methods, one feasible and acceptable abatement method to correct this hazard is to: 1. Provide an emergency pull cord along the entire length of the belt conveyor. Reference ANSI B.20.1, Section 5.11.2(c), 1987. 2. When proper cleaning requires the conveyor to be in motion and a hazard exists, personnel should be made aware of the associated hazards. Reference ANSI B.20.1, Section 5.12(j), 1987. 3. Personnel working on or near a conveyor shall be instructed as to the location and operation of pertinent stopping devices. Reference ANSI B.20.1, Section 5.12(e), 1987.
5(a)(1)
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,650 · Current $1,650
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to a burn hazard from ignition of natural gas leaks due to an improper natural gas shut-off valve used in a gas torch assembly: a) Roto-Pour Area - The gas torch was not provided with an approved shut-off valve; the valve was an ordinary plumbing type shut-off valve. Among other methods, one feasible and acceptable abatement method to correct this hazard is to: 1. Install an approved shut-off valve in the gas torch assembly. Reference NFPA 54-1988/ANSI Z223.1, Section 2.12, 1988. THIS COMPANY WAS PREVIOUSLY CITED FOR A VIOLATION OF THE OCCUPATIONAL SAFETY AND HEALTH STANDARD OR ITS EQUIVALENT, 5(a)(1), WHICH WAS CONTAINED IN OSHA INSPECTION NUMBER 0785030, CITATION #1, ITEM #1, ISSUED ON APRIL 11, 1989.
5(a)(1)
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,650 · Current $1,650
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to a falling hazard due to the lack of a midrail on one side of the personnel platform and a gate for employee access: a) Transfer Ladle Area - The personnel platform used to elevate employees on a forklift truck approximately 12 feet above dsthe floor was not provided with a midrail on one side of the personel platform and a gate for employee access: Among other methods, one feasible and acceptable abatement method to correct this hazard is to: 1. Install a midrail on the platform and an access gate that provides protection equivalent to that provided by the guardrail system.
5(a)(1)
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1994
- Penalty
- Initial $1,650 · Current $1,650
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to a crushing hazard due to being caught between a moving elevator car and the fixed structures of the hoistway while the elevator was operated by an employee inside the car: a) Shipping Area, The #1 Freight Elevator - The elevator car was not provided with a door or gate to keep rider's body parts away from the nip points created by the moving car frame and the hoistway walls and floors. Among other methods, one feasible and acceptableabatement method to correct this hazard is to: 1. Install elevator car doors or gates. Reference ANSI A17.1, 1965, Rule 204.4.
5(a)(1)
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,650 · Current $1,650
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to crushing injuries due to unexpected shifting of loads or falling hoist parts when lifting and moving material with the overhead hoists: a) Quality Control Department - A jib hoist was extensively repaired, not load tested, and the welding was done by in house personnel. b) Patter Shop - The two overhead hoists were not certified as to the capacity of the hoist beam and supporting structures. c) Rock Pile Department - The overhead hoist was operated with the hoist beam damaged, and not taken out of service. Among other methods, one feasible and acceptable abatement method to correct his hazard is to: 1. All clamps, hanger rods, bolts or other suspension fittings and supporting structure shall be designed to support the rated loads in accordance with specifications in the AISC Manual of Steel Construction. Reference ANSI B.30.11-1973, Section 11.1.3.2. 2. All welding shall conform to the recommended practices of the American Welding Society as outlined in AWS D14.1 for Industrial and Mill Cranes. Reference ANSI B.30.11-1973, Section 11.1.3.4. 3. Prior to initial use, all new, extensively repaired, or altered equipment shall be tested by or under the direction of an appointed person and a written report furnished by such person, confirming the load rating of the system. Reference ANSI B.30.11-1973, Section 11-2.2.2. 4. An unsafe condition disclosed by the inspection requirements of Section 11.2.1 shall be corrected before operation of the underhung crane or monorail system is resumed. Reference ANSI B.30.11-1973, Section 11.2.3.3.
1910.22 A01
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.22 A02
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.22 B01
- Issued
- May 26, 1993
- Abate by
- Aug 15, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.23 A02
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,650 · Current $1,650
1910.23 A07
- Issued
- May 26, 1993
- Abate by
- Mar 31, 1994
Recent events (2)
- — P (S)
- — Z (S)
1910.23 A09
- Issued
- May 26, 1993
- Abate by
- Aug 15, 1993
1910.23 C01
- Issued
- May 26, 1993
- Abate by
- Aug 18, 1994
- Penalty
- Initial $2,100 · Current $2,100
Recent events (2)
- — P (S) $2100.00
- — Z (S) $2100.00
1910.23 C02
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.23 C03
- Issued
- May 26, 1993
- Abate by
- Aug 15, 1993
- Penalty
- Initial $3,000 · Current $3,000
1910.27 D03
- Issued
- May 26, 1993
- Abate by
- Jul 18, 1993
- Penalty
- Initial $1,650 · Current $1,650
1910.36 B06
- Issued
- May 26, 1993
- Abate by
- Dec 18, 1993
- Penalty
- Initial $2,100 · Current $2,100
1910.37 F05
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.37 K02
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $2,100 · Current $2,100
1910.37 Q01
- Issued
- May 26, 1993
- Abate by
- Dec 18, 1993
- Penalty
- Initial $2,100 · Current $2,100
1910.37 Q05
- Issued
- May 26, 1993
- Abate by
- Dec 18, 1993
1910.37 Q06
- Issued
- May 26, 1993
- Abate by
- Dec 18, 1993
1910.38 A02
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $2,250 · Current $2,250
Recent events (2)
- — I (S) $2250.00
- — Z (S) $2250.00
1910.38 A05 II
- Issued
- May 26, 1993
- Abate by
- Jan 18, 1994
- Penalty
- Initial $1,350 · Current $1,350
Recent events (2)
- — P (S) $1350.00
- — Z (S) $1350.00
1910.38 B02
- Issued
- May 26, 1993
- Abate by
- Jan 18, 1994
Recent events (2)
- — P (S)
- — Z (S)
1910.38 B04 III
- Issued
- May 26, 1993
- Abate by
- Jan 18, 1994
Recent events (2)
- — P (S)
- — Z (S)
1910.157 G02
- Issued
- May 26, 1993
- Abate by
- Jan 18, 1994
Recent events (2)
- — P (S)
- — Z (S)
1910.106 D03 II
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.106 E02 IIB2
- Issued
- May 26, 1993
- Abate by
- Aug 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.106 E02 IVA
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.106 E02 IVD
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.106 E06 I
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.106 E06 II
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.107 B01
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
- Penalty
- Initial $1,650 · Current $1,650
1910.107 B04
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.107 B06
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.107 C07
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.107 D02
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.107 G02
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.107 G07
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.107 B05 I
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,250 · Current $1,250
1910.107 B09
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.107 B10
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
Recent events (2)
- — I (S)
- — Z (S)
1910.107 C05
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
Recent events (2)
- — I (S)
- — Z (S)
1910.107 C06
- Issued
- May 26, 1993
- Abate by
- Aug 18, 1993
1910.107 E09 I
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.107 F04
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.107 G02
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.107 B10
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,650 · Current $1,650
1910.107 C02
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.107 C05
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.107 G02
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.107 B05 II
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,650 · Current $1,650
1910.107 C02
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.107 G05
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.108 C01
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.108 D
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.132 A
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,350 · Current $1,350
Recent events (2)
- — I (S) $1350.00
- — Z (S) $1350.00
1910.132 A
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $675 · Current $675
1910.133 A01
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.133 A06
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.141 D02 I
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.151 B
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
Recent events (2)
- — I (O)
- — Z (O)
1910.147 D04 II
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,800 · Current $1,800
Recent events (2)
- — I (S) $1800.00
- — Z (S) $1800.00
1910.333 B02 I
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.151 C
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.178 G02
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.178 G10
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.178 L
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.178 Q06
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.179 C02
- Issued
- May 26, 1993
- Abate by
- Aug 15, 1993
- Penalty
- Initial $1,350 · Current $1,350
1910.179 C04
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.179 E05 II
- Issued
- May 26, 1993
- Abate by
- Aug 15, 1993
1910.179 I
- Issued
- May 26, 1993
- Abate by
- Aug 15, 1993
1910.179 J02 III
- Issued
- May 26, 1993
- Abate by
- Aug 15, 1993
1910.179 L03
- Issued
- May 26, 1993
- Abate by
- Aug 15, 1993
1910.179 M01
- Issued
- May 26, 1993
- Abate by
- Aug 15, 1993
1910.179 O03
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.212 A01
- Issued
- May 26, 1993
- Abate by
- Sep 15, 1993
- Penalty
- Initial $2,100 · Current $2,100
1910.212 A01
- Issued
- May 26, 1993
- Abate by
- Aug 15, 1993
1910.212 A01
- Issued
- May 26, 1993
- Abate by
- Oct 8, 1993
Recent events (2)
- — P (S)
- — Z (S)
1910.212 A03 II
- Issued
- May 26, 1993
- Abate by
- Mar 14, 1994
- Penalty
- Initial $2,100 · Current $2,100
Recent events (2)
- — P (S) $2100.00
- — Z (S) $2100.00
1910.212 A05
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.212 A05
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.219 C02
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.219 C04 I
- Issued
- May 26, 1993
- Abate by
- Jul 18, 1993
1910.219 C04 II
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.219 D01
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.219 E03 I
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.219 O01 IA
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.219 F01
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.219 F03
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.219 I02
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.243 C01
- Issued
- May 26, 1993
- Abate by
- Aug 15, 1993
- Penalty
- Initial $1,650 · Current $1,650
1910.253 B02 IV
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,650 · Current $1,650
1910.253 B04 III
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.303 B01
- Issued
- May 26, 1993
- Abate by
- Jul 18, 1993
- Penalty
- Initial $1,650 · Current $1,650
1910.304 F05 V
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
- Penalty
- Initial $2,100 · Current $2,100
1910.303 G02 I
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $3,000 · Current $3,000
1910.305 J04 IVA
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $2,100 · Current $2,100
1910.332 B01
- Issued
- May 26, 1993
- Abate by
- Jan 18, 1994
- Penalty
- Initial $900 · Current $900
Recent events (2)
- — P (O) $900.00
- — Z (O) $900.00
1910.332 B03
- Issued
- May 26, 1993
- Abate by
- Jan 18, 1994
Recent events (2)
- — P (O)
- — Z (O)
1910.1200 F05 I
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
- Penalty
- Initial $1,200 · Current $1,200
1910.1200 F05 II
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.22 D01
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.23 D01 IV
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.24 F
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.94 B04 III
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.106 G03 II
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.145 F03
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.147 C06 II
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.184 E01
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.215 B09
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.242 A
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.242 B
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.253 B05 IIE
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.253 E05 III
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.303 B02
- Issued
- May 26, 1993
- Abate by
- Jul 18, 1993
1910.303 F
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.303 G01 II
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.303 G02 II
- Issued
- May 26, 1993
- Abate by
- Jul 18, 1993
1910.304 E01 IV
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
1910.305 G02 III
- Issued
- May 26, 1993
- Abate by
- Jul 18, 1993
1910.305 J02 II
- Issued
- May 26, 1993
- Abate by
- Jun 18, 1993
1910.334 A02 I
- Issued
- May 26, 1993
- Abate by
- Jun 1, 1993
More inspections at EMI Company, INC.
View EMI Company, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 000000)
More inspections in PA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 113345797.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.