LINDEN, NJ —
OSHA Inspection: CONOCOPHILLIPS BAYWAY REFINERY
Complaint inspection · Health discipline
At a glance
On , OSHA opened a complaint health inspection of CONOCOPHILLIPS BAYWAY REFINERY in 1400 PARK AVE., LINDEN, NJ 07036 (NAICS 324110). OSHA activity number 311913552.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- CONOCOPHILLIPS BAYWAY REFINERY
- Site address
- 1400 PARK AVE.
- City
- LINDEN
- State
- NJ
- ZIP
- 07036
- Mailing
- 1400 PARK AVE, LINDEN, NJ 07036
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Health
- Advance notice
- No
- Union status
- Y
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 324110
- SIC code (legacy)
- 2911
- Employees
- 830
- Ownership type
- A
Citations
6 citations on file for this inspection.
1910.119 F01
- Issued
- Oct 9, 2008
- Abate by
- Jan 31, 2009
- Penalty
- Initial $5,000
General-duty citation text
29 CFR 1910.119(f)(1): The employer did not develop and implement written operating procedures that provided clear instructions for safely conducting activities in each covered process consistent with the process safety information and which addressed the elements listed in 29 CFR 1910.119(f)(1)(i) through (f)(1)(iv): a) FCAT, Old Compressor Building - On or about 07/23/08 the FCCU experienced an upset condition requiring the use of the number 6 blower. Workers turned on the blower and were required to bring it into the unit after approximately 30 minutes of operation. This violated the employer's written procedure FCAT FCBW-Turbo Machinery Equipment Manual 02.02.02-1 Startup Procedure B-6 Discharge to B-4 Suction Jump over Open which required that the blower be vented to atmosphere for 60 minutes prior to opening the discharge to the unit.
Recent events (3)
- — R (O)
- — J (O)
- — Z (S) $5000.00
1910.119 J02
- Issued
- Oct 9, 2008
- Abate by
- Nov 21, 2008
- Penalty
- Initial $5,000
General-duty citation text
29 CFR 1910.119(j)(2): The employer did not establish and implement written procedures to maintain the on-going mechanical integrity of process equipment: a) ABW - The employer did not implement written procedures for the installation of epoxy coatings to the interior surfaces of piping. Such procedures shall include proper surface preparation, adequate number of coats and cure times between coatings, thickness measurement of coatings and necessary verification/documentation. On 04/09/08 approximately 2500 lbs. of butane was released from a hole in the E- 17C exchanger outlet piping. The epoxy lining on the interior of the pipe spool had failed allowing corrosion of the carbon steel pipe.
Recent events (3)
- — R (S)
- — J (S)
- — Z (S) $5000.00
1910.119 J04 II
- Issued
- Oct 9, 2008
- Abate by
- Nov 21, 2008
- Penalty
- Initial $5,000
General-duty citation text
29 CFR 1910.119(j)(4)(ii): Inspections and testing procedures performed on process equipment to maintain its mechanical integrity, did not follow recognized and generally accepted good engineering practices: a) ABW - On 04/09/08 approximately 2500 lbs. of butane leaked from a hole in the E-17C exchanger outlet piping. The epoxy lining on the interior of the pipe spool had failed allowing corrosion of the carbon steel. The employer failed to comply with API 574 Sections 6.3.6 and 6.3.8 in that effective NDE inspection methods to include but not limited to radiographic profile were not used and appropriate inspections were not performed of the corrosion-resistant lining.
Recent events (3)
- — R (S)
- — J (S)
- — Z (S) $5000.00
1910.119 J06 II
- Issued
- Oct 9, 2008
- Abate by
- Feb 16, 2009
- Penalty
- Current $5,000
General-duty citation text
29 CFR 1910.119(j)(6)(ii): Appropriate checks and inspections were not performed to assure that equipment is installed properly and consistent with design specifications and the manufacturer's instruction: a) ABW - The employer failed to perform checks and inspections on an epoxy coating applied to the interior of outlet piping for the E-17C exchanger in March 2005. The employer did not verify the correct number of coats and proper cure time between applications. In addition, appropriate thickness readings were not taken of the epoxy lining. On 04/09/08 approximately 2500 lbs. of butane was released from a hole in the above noted piping as the epoxy lining had failed allowing corrosion of the carbon steel.
Recent events (4)
- — R (S) $5000.00
- — P (S) $5000.00
- — J (S) $5000.00
1910.119 L01
- Issued
- Oct 9, 2008
- Abate by
- Jan 31, 2009
- Penalty
- Initial $5,000
General-duty citation text
29 CFR 1910.119(l)(1): The employer did not establish and implement written procedures to manage changes to process chemicals, technology, equipment, and procedures; and, changes to facilities that affect a covered process: a) FCAT - An MOC was not performed when workers were required to start the number 6 blower in response to a unit upset on 07/23/08 and bring it into the unit after approximately 30 minutes of operation. FCAT FCBW-Turbo Machinery Equipment Manual 02.02.02.1 Startup Procedure B-6 Discharge to B-4 Suction Jump over Open requires that the blower be vented to atmosphere for 60 minutes prior to opening the discharge to the unit. Condition noted on or about 07/25/08. b) ABW - In March 2005 an MOC was not performed when carbon steel outlet piping for the E-17C and E-18C exchangers was lined with epoxy. Piping interior had been lined in response to leaks caused by hydrochloric acid pitting on the carbon steel. Condition noted on or about 08/01/08.
Recent events (3)
- — R (O)
- — J (O)
- — Z (S) $5000.00
1910.119 M05
- Issued
- Oct 9, 2008
- Abate by
- Nov 21, 2008
- Penalty
- Initial $5,000
General-duty citation text
29 CFR 1910.119(m)(5): The employer did not establish a system to promptly address and resolve the incident investigation report findings and recommendations: a) ABW - The employer failed to adequately resolve recommendations found in incident investigation number 7578 concerning a butane leak at the E-17C outlet piping on 01/24/05 and related engineering analysis entitled ABW E-17C and E-18C Outlet Chloride Corrosion - Winter 2005 dated 05/25/05. The findings directly related to the butane release on 04/09/08 of the same piping noted above. The employer failed to look into the feasibility of the following recommendations: 1) switch from Univar's diaphragm grade caustic to the low-chloride grade caustic, 2) install a water purification system which removes chlorides on the BFW to D-11, the reactor effluent water wash settler, 3) add a chloride trap to the Vis-J spent feed stream which removes organic chlorides. Condition noted on or about 06/12/08.
Recent events (3)
- — R (S)
- — J (S)
- — Z (S) $5000.00
More inspections at Conocophillips Bayway Refinery
View Conocophillips Bayway Refinery's full OSHA safety record →
More inspections in this industry (NAICS 324110)
More inspections in NJ
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 311913552.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.