OSHA Inspection: AMERICAN WOOD FIBERS, INC.

Planned inspection · Health discipline

On , OSHA opened a planned health inspection of AMERICAN WOOD FIBERS, INC. in 2500 OWENS ROAD, CIRCLEVILLE, OH 43113 (NAICS 321999). OSHA activity number 313155889.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch American Wood Fibers, INC. — free Get an email when a new federal OSHA severe-injury report for American Wood Fibers, INC. is published. One employer, no account, unsubscribe in one click.
Site address
2500 OWENS ROAD
City
CIRCLEVILLE
State
OH
ZIP
43113
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
N
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
321999
SIC code (legacy)
2499
Employees
30
Ownership type
A

4 citations on file for this inspection.

5(a)(1)

Serious Gravity 03 3 instances 30 exposed
Issued
Jun 9, 2010
Abate by
Jul 9, 2010
Penalty
Initial $2,250 · Current $1,575 Reduced

Hazardous substances E101E200

Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not furnish employment
and a place of employment which were free from recognized hazards that
were causing or likely to cause
death or serious physical harm to employees in that employees were exposed
to wood dust explosion,
deflagration, or other fire hazards:
a.On or about May 13, 2010, in the raw material storage building, a
section of flexible plastic ducting
which was used to pneumatically transfer wood dust between the metallic
ductwork to baghouse 3 and
the dust enclosure was not metallic, conductive, bonded and grounded.
ABATEMENT NOTE:  Among other methods, one feasible and acceptable method
to correct these
hazards include following NFPA 664, Standard for the Prevention of Fires
and Explosions in Wood
Processing and Woodworking Facilities (2007 Edition), Section 8.2.2.2.1.1,
8.2.2.2.1.2, and
8.2.2.2.1.8 including, but not limited to, installing ductwork which was
metallic, conductive, bonded
and grounded.
b.On or about May 13, 2010, in the raw material storage building, a
section of flexible plastic ducting
which was used to pneumatically transfer wood dust between the metallic
ductwork to baghouse 3 and
the screw conveyor was not metallic, conductive, bonded and grounded.
ABATEMENT NOTE:  Among other methods, one feasible and acceptable method
to correct these
hazards include following NFPA 664, Standard for the Prevention of Fires
and Explosions in Wood
Processing and Woodworking Facilities (2007 Edition), Section 8.2.2.2.1.1,
8.2.2.2.1.2, and
8.2.2.2.1.8 including, but not limited to, installing ductwork which was
metallic, conductive, bonded
and grounded.
c.On or about May 13, 2010, surfaces were not cleaned in a manner that
minimized the generation of
wood dust clouds due to employees blowing down with compressed air (60-80
psi) in locations such as
the raw material storage building, system 1, and system 2, and the
employer did not assure that all
ignition sources were controlled.
ABATEMENT NOTE:  Among other methods, one feasible and acceptable method
to correct these
hazards include following NFPA 664, Standard for the Prevention of Fires
and Explosions in Wood
Processing and Woodworking Facilities (2007 Edition), Section 11.2.1.1
including, but not limited to,
discontinuing the use of compressed air or reducing the compressed air to
15 psi and taking additional
precautions such as vacuuming prior to blowdown, shutting down electrical
power and other sources of
ignition, removing open flames, spark-producing equipment or hot surfaces,
and ensuring that all fire
equipment is in service.t
Recent events (2)
  • — I (S) $1575.00
  • — Z (S) $2250.00

1910.242 B

Serious Gravity 03 3 instances 12 exposed
Issued
Jun 9, 2010
Abate by
Jul 9, 2010
Penalty
Initial $2,250 · Current $1,575 Reduced
Recent events (2)
  • — I (S) $1575.00
  • — Z (S) $2250.00

1910.307 C

Deleted Serious Gravity 10 3 instances 12 exposed
Issued
Jun 9, 2010
Abate by
Jul 9, 2010
Penalty
Initial $4,500 · Current $4,500

Hazardous substances E101E200

Recent events (2)
  • — I (S) $4500.00
  • — Z (S) $4500.00

1910.145 C03

Other-than-serious Gravity 01 1 instance 30 exposed
Issued
Jun 9, 2010
Abate by
Jul 9, 2010

Hazardous substances E101E200

Recent events (2)
  • — I (O)
  • — Z (O)

View American Wood Fibers, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 313155889.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.