ADA, OH ·
OSHA Inspection: WILSON SPORTING GOODS CO.
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of WILSON SPORTING GOODS CO. in 217 N. LIBERTY ST., ADA, OH 45810 (NAICS 339920). OSHA activity number 313780520.
OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- WILSON SPORTING GOODS CO.
- Site address
- 217 N. LIBERTY ST.
- City
- ADA
- State
- OH
- ZIP
- 45810
- Mailing
- P.O. BOX 116, ADA, OH 45810
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- Union (Y)
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 339920
- SIC code (legacy)
- 3949
- Employees
- 116
- Ownership type
- Private (A)
- Industry flags
- Manufacturing safety.
Citations
20 citations on file for this inspection.
5(a)(1)
- Issued
- Aug 16, 2010
- Abate by
- Oct 19, 2015
- Penalty
- Initial $4,500 · Current $3,500 Reduced
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause serious physical harm to employees, in that employees were required to perform sewing and lacing tasks which exposed them to ergonomic risk factors including, but not limited to, excessive force or exertion, repetitive motions and awkward postures, some of which were maintained for prolonged periods of time, which have caused, are causing and are likely to cause serious musculoskeletal disorder (MSDs) injuries: (a)January 2005 to present - The Puritan Sewers who work at the Wilson Sporting Goods Company have repeatedly performed tasks involving the wrists and shoulders such as, but not limited to, grasping and pushing leather panels through sewing machines and trimming excess leather with awkward postures and repeated forceful exertions for an extended duration. (b)January 2005 to present - The Lacers who work at the Wilson Sporting Goods Company have repeatedly performed tasks involving the hands, wrists, and shoulders such as, but not limited to, pressing, pulling and pushing to insert the valve stems into footballs and lacing footballs with awkward postures and repeated forceful exertions for an extended duration. Abatement Methods: While some ergonomic related risk factors can be reduced or eliminated by implementing a single means of abatement, in most cases, a process using components, such as those which follow, will provide an effective method of addressing the factors. This process includes worksite analysis, training and education of employees in injury recognition and avoidance, hazard prevention and control, and medical management to provide the most effective method of addressing the factors. The employer may adopt any measures that are effective in reducing or eliminating the risk factors. Examples of such measures are as follows: Prioritized programmatic abatement measures include: 1.Minimize extended work hours to reduce the exposure to forceful, repetitive, awkward postures and localized muscle fatigue to provide sufficient physiological rest and recovery time. In 2007 the company changed the work schedule in an attempt to reduce overtime and eliminate the "peak" and "low" season work schedules. The incidence of injuries was drastically reduced and the MSD Days Away, Restricted or Transferred (DART) rate was zero. As demonstrated by the 2007 changes, the following measures are feasible: a.Significantly reduce overtime work. b.Adjust staffing schedules to eliminate the peak and low season. In addition, because the incidence of injuries in years other than 2007 was considerably higher for those workers producing at high rates, the piece rate wage system should be evaluated and adjusted, if necessary, to reduce employee exposures. 2.Training and education for all exposed employees, managers, safety/ergonomic committee members and employee representatives: a.Addressing the ergonomic risk factors present in the sewing and lacing tasks that can lead to MSDs, the signs and symptoms of MSDs, and how to prevent the recurrence of MSDs. 3.Work rotation schedule for the Puritan Sewers to minimize the duration of time performing the hazardous sewing tasks. 4.Work rotation schedule for the Lacers to minimize the duration of time performing the hazardous lacing tasks. Prioritized work practice controls are implemented to minimize ergonomic stressors. Controls applicable to this workplace may include: 1.Provide a method to warm the leather immediately prior to performing the Puritan sewing or lacing tasks. 2.Ensure the quality of leather is soft to facilitate manipulating the leather while assembling the football. 3.Provide a scissor sharpening program to include daily sharpening and as needed throughout the work shift. 4.Provide powered scissors for the Puritan Sewers to facilitate cutting the leather at the seams. 5.Develop a clamp, guide or fixture to aid the Puritan Sewers in leather manipulation. Develop a device for the Lacers to assist in the insertion of the valve stem into the football cavity. 6.Provide an effective lubricant for the Lacers to use for inserting the valve stem into the football and pulling the lace. The application of the lubricant should be under the control of the lacer. 7.Develop tool management policies and procedures such as, but not limited to: a.Include employee participation in the evaluation and selection of new tools, lubricant, fixtures, and assistive devices. Additional Hazard Prevention and Control Measures Hazard prevention and control includes feasible engineering, administrative, and work practices controls. Examples of engineering controls for Puritan Sewers include: 1.An adjustable workstation under employee control, set up to reduce the risk of MSDs. 2.An adjustable chair with adjustable arm rests. 3.Tools designed and fit to each worker. 4.Work table space to stage product, equipment and tools. 5.Product staging to reduce extended reaching by the employee to the side or behind. 6.Product staging bins slightly below elbow height and tilted to improve access. Examples of engineering controls for Lacers include:1.An adjustable workstation under employee control, set up to reduce the risk of MSDs. 2.Provide a sit/stand chair or an adjustable chair for use during bladder and valve insertion. 3.Tools designed and fit to each worker. 4.Product staging to reduce extended side or behind reaching by the employee 5.Antifatigue matting (3/8th to 5/8th inches) for all standing workstations at the air insertion and lacing fixtures. 6.Product staging bins slightly below elbow height and tilted to improve access. Examples of administrative controls for both Puritan Sewers and Lacers include: 1.A product flow schedule to heat and moisturize the leather immediately prior to the performance of sewing or lacing tasks. a.Move product immediately from the Turner (moisturized warming box) to the Puritan Sewer for the closing. The closed football then should be immediately moved to the Lacer for bladder and valve stem insertion and lacing. Immediate movement of the product between stations will aid in keeping the leather warm, flexible, and supple. 2.Develop a scheduled preventive maintenance policy and procedures to address the following, such as, but not limited to: a.All workstation adjustment controls b.All chair adjustment controls c.Treadle trigger and speed control adjustment s d.Air trigger pedal and control adjustments e.Fixture stability f.Task and overhead lighting. 3.Implement a ramp-up conditioning program or a phase-in rotation schedule for new employees and employees returning to work from leave or other absences. Examples of the work site analysis include: a.Work site analysis conducted by persons with the appropriate education, expertise, and experience to identify and evaluate ergonomic stressors and engineering, administrative and work practice controls needed for abatement. b.Work site analysis includes analysis of all tasks and work place procedures to identify all ergonomic stressors and the body part(s) affected. c.Employee participation in this analysis process is strongly encouraged. Examples of occupational medical management include: 1.Schedule a systematic review of the root cause of MSD injuries by safety/ergonomics committee members trained in site specific ergonomics. 2.Develop a list of risk factors presented by the Puritan Sewers and Lacer jobs. 3.Develop a surveillance system for the purpose of preventing occupational injuries. a.Use the OSHA 300 Logs, third party administrator injury claim information, first aid treatment data, and accident records to identify trends. 4.Take corrective action to reduce exposure to physical hazards. a.Determine if the task in question can be performed a better way. b.Following the implementation of corrective action, assess the effectiveness of the intervention(s) used to correct the identified problem(s). 5.Assess the effectiveness of the ergonomics program process on an annual basis.
Recent events (2)
- · F (S) $3500.00
- · Z (S) $4500.00
1910.132 D01 I
- Issued
- May 4, 2010
- Abate by
- Jun 4, 2010
- Penalty
- Initial $4,500 · Current $2,500 Reduced
Recent events (2)
- · J (S) $2500.00
- · Z (S) $4500.00
1910.132 D02
- Issued
- May 4, 2010
- Abate by
- May 27, 2010
Recent events (2)
- · J (O)
- · Z (S)
1910.133 A03
- Issued
- May 4, 2010
- Abate by
- Jun 4, 2010
- Penalty
- Initial $4,500 · Current $2,500 Reduced
Recent events (2)
- · J (S) $2500.00
- · Z (S) $4500.00
1910.147 C04 II
- Issued
- May 4, 2010
- Abate by
- Jun 4, 2010
- Penalty
- Initial $2,250 · Current $2,250
Recent events (2)
- · J (S) $2250.00
- · Z (S) $2250.00
1910.147 C06 I
- Issued
- May 4, 2010
- Abate by
- Jun 4, 2010
- Penalty
- Initial $2,250 · Current $1,500 Reduced
Recent events (2)
- · J (S) $1500.00
- · Z (S) $2250.00
1910.147 C07 I
- Issued
- May 4, 2010
- Abate by
- Jun 4, 2010
- Penalty
- Initial $2,250 · Current $1,500 Reduced
Recent events (2)
- · J (S) $1500.00
- · Z (S) $2250.00
1910.147 D03
- Issued
- May 4, 2010
- Abate by
- Jun 4, 2010
- Penalty
- Initial $2,250 · Current $1,500 Reduced
Recent events (2)
- · J (S) $1500.00
- · Z (S) $2250.00
1910.178 A04
- Issued
- May 4, 2010
- Abate by
- Jun 4, 2010
- Penalty
- Initial $2,250 · Current $1,500 Reduced
Recent events (2)
- · J (S) $1500.00
- · Z (S) $2250.00
1910.212 A03 II
- Issued
- May 4, 2010
- Abate by
- Jun 18, 2010
- Penalty
- Initial $4,500 · Current $2,500 Reduced
Recent events (2)
- · J (S) $2500.00
- · Z (S) $4500.00
1910.217 C02 IA
- Issued
- May 4, 2010
- Abate by
- May 20, 2010
- Penalty
- Initial $2,250 · Current $1,500 Reduced
Recent events (2)
- · J (O) $1500.00
- · Z (S) $2250.00
1910.217 E01 I
- Issued
- May 4, 2010
- Abate by
- Jun 4, 2010
Recent events (2)
- · J (O)
- · Z (S)
1910.219 D01
- Issued
- May 4, 2010
- Abate by
- May 7, 2010
- Penalty
- Initial $4,500 · Current $2,500 Reduced
Recent events (2)
- · J (S) $2500.00
- · Z (S) $4500.00
1904.7 B03
- Issued
- May 4, 2010
- Abate by
- May 27, 2010
- Penalty
- Initial $900 · Current $500 Reduced
Recent events (2)
- · J (O) $500.00
- · Z (O) $900.00
1904.7 B04
- Issued
- May 4, 2010
- Abate by
- May 27, 2010
- Penalty
- Initial $900 · Current $500 Reduced
Recent events (2)
- · J (O) $500.00
- · Z (O) $900.00
1904.29 B01
- Issued
- May 4, 2010
- Abate by
- May 27, 2010
- Penalty
- Initial $900 · Current $500 Reduced
Recent events (2)
- · F (O) $500.00
- · Z (O) $900.00
1904.29 B01
- Issued
- May 4, 2010
- Abate by
- May 27, 2010
- Penalty
- Initial $900
Recent events (2)
- · F (O)
- · Z (O) $900.00
1904.29 B01
- Issued
- May 4, 2010
- Abate by
- May 27, 2010
- Penalty
- Initial $900
Recent events (2)
- · F (O)
- · Z (O) $900.00
1904.29 B01
- Issued
- May 4, 2010
- Abate by
- May 27, 2010
- Penalty
- Initial $900
Recent events (2)
- · F (O)
- · Z (O) $900.00
1904.29 B01
- Issued
- May 4, 2010
- Abate by
- May 27, 2010
- Penalty
- Initial $900
Recent events (2)
- · F (O)
- · Z (O) $900.00
More inspections at Wilson Sporting Goods CO.
View Wilson Sporting Goods CO.'s full OSHA safety record →
More inspections in this industry (NAICS 339920)
More inspections in OH
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). OSHA publishes its own view of this case as inspection number 313780520.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.