Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: ZOTOS INTERNATIONAL, INC.

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of ZOTOS INTERNATIONAL, INC. in 300 FORGE AVE., GENEVA, NY 14456 (NAICS 325620). OSHA activity number 331914465.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Zotos International, INC. — free Get an email when a new federal OSHA severe-injury report for Zotos International, INC. is published. One employer, no account, unsubscribe in one click.
Site address
300 FORGE AVE.
City
GENEVA
State
NY
ZIP
14456
Mailing
P.O. BOX 71, GENEVA, NY 14456
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
325620
Employees
722
Ownership type
A

11 citations on file for this inspection.

1910.110 B06 VI

Serious Gravity 5 1 instance 5 exposed
Issued
May 24, 2012
Penalty
Initial $5,000 · Current $2,750 Reduced
29 CFR 1910.110(b)(6)(vi): Readily ignitable materials were not removed from within ten feet of any LP Gas container:        a) On or about 2/14/2012, Aerosol Area:   Wooden dunnage was stored underneath tank #5 which was labeled as a LPG tank.      Abatement certification is required for this item.
Recent events (3)
  • — J (S) $2750
  • — C (S) $5000
  • — Z (S) $5000

1910.119 D02 I A

Serious Gravity 5 1 instance 8 exposed
Issued
May 24, 2012
Penalty
Initial $5,000 · Current $2,750 Reduced
29 CFR 1910.119(d)(2)(i)(A): Information pertaining to the equipment in the process did not include a Block Flow Diagram of the process:    a) On or about 2/13/2012, Alcohol Area:   There was no Block Flow Diagram for the Alcohol unit.
Recent events (3)
  • — J (S) $2750
  • — C (S) $5000
  • — Z (S) $5000

1910.119 D03 I B

Serious Gravity 5 6 instances 12 exposed
Issued
May 24, 2012
Abate by
Jun 23, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.119(d)(3)(i)(B): Information pertaining to the equipment in the process did not include accurate Piping and Instrument Diagrams and did not represent equipment that was existing and was part of the process.    a) On or about 2/13/2012, Alcohol Area:  The existing P&ID's had discrepancies between the drawings and what was actually in place, such as, but not limited to:       1) The plans, drawing G-4, show that there should be three High capacity emergency vents, while there are only two on the tank.       2) There were two level indicators located on the tank, and they were not shown or addressed on the drawing G-4.       3) None of the valving for the filling and dispensing of alcohol on the main tank was shown on the drawing G-4 nor any other drawing.       4) None of the process valving or relief valving was shown on drawing M-1, depicting the batching room.       5) Two tanks in room 5a had been removed (T90 and T95), but were still on drawing M-1, while one tank was moved (T93) and one tank was added (HC5), which was not added to drawing M-1.     b) On or about 2/14/2012, Aerosol Area:  The existing P&ID's had discrepancies between the drawings and what was actually in place, such as, but not limited to:         1) On piping associated with tank numbers 1, 2, and 3, there was a valve and nipple with a plug that was located after PI-0-400, which did not appear on the drawings.    Abatement certification is required for this item.
Recent events (3)
  • — J (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.119 D03 I D

Serious Gravity 5 1 instance 8 exposed
Issued
May 24, 2012
Abate by
Jun 23, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.119(d)(3)(i)(D): Information pertaining to the equipment in the process did not include relief system design and design basis:    a) On or about 2/13/2012, Alcohol Area:  There were no design plans, or basis for the Alcohol room relief system.     Abatement certification is required for this item.
Recent events (3)
  • — J (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.119 D03 II

Serious Gravity 5 4 instances 8 exposed
Issued
May 24, 2012
Abate by
Sep 13, 2013
Penalty
Initial $5,000 · Current $2,750 Reduced
29 CFR 1910.119(d)(3)(ii): The employer did not document that equipment complies with recognized and generally accepted good engineering practices.    a) On or about 2/13/2012, Alcohol Area:  The employer did not ensure that all equipment complied with recognized and generally accepted good engineering practices such as not limited to the following consensus standards:         1) The tank venting system in use located after tank flame arrestors, was constructed with PVC piping that showed signs of heat exposure and failure.  Reference NFPA 30, Flammable and Combustible Liquids Code, section 27.4.4.1           2) The exterior Ethanol storage tank had emergency venting that was located below the roof line and vents of three surrounding buildings.  Reference NFPA 90A Installation of Air Conditioning and Ventilating Systems, section 2-2.1.1 and NFPA 69 Explosion Prevention Systems, section 3-3.3.1.         3) The room venting from building 5a was located in line with intake vents for building 2.  Reference NFPA 90A Installation of Air Conditioning and Ventilating Systems, section 2-2.1.1 and NFPA 69 Explosion Prevention Systems, section 3-3.3.1.         4) The spill containment area was provided with an unsecured valve to the waste water treatment plant.  Reference NFPA 30 Flammable and Combustible Liquids Code, section 5-4.1.2 and section 5-4.2.    Abatement certification is required for this item.
Recent events (3)
  • — J (S) $2750
  • — C (S) $5000
  • — Z (S) $5000

1910.119 E03 IV

Serious Gravity 5 1 instance 4 exposed
Issued
May 24, 2012
Abate by
Jun 23, 2012
Penalty
Initial $5,000 · Current $2,750 Reduced
29 CFR 1910.119(e)(3)(iv): The process hazard analysis did not address the consequences of failure of engineering and administrative controls:     a) On or about 2/14/2012, Aerosol Area:  The PHA did not consider the consequences of failure of the engineering and administrative controls, such as, but not limited to the failure of the interlocks on the doors to the gas houses.    Abatement certification is required for this item.
Recent events (3)
  • — J (S) $2750
  • — C (S) $5000
  • — Z (S) $5000

1910.119 E05

Serious Gravity 5 1 instance 8 exposed
Issued
May 24, 2012
Abate by
Jun 23, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.119(e)(5): The employer did not develop a written schedule of actions to resolve Process Hazard Analysis (PHA) recommendations.    a) On or about 2/13/2012, Alcohol Area:    There was no written schedule to address items identified in the August 2011 PHA.    Abatement certification is required for this item.
Recent events (3)
  • — J (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.119 E04

Serious Gravity 5 1 instance 6 exposed
Issued
May 24, 2012
Abate by
Jun 23, 2012
Penalty
Initial $5,000 · Current $2,750 Reduced
29 CFR 1910.119(e)(4): The team performing the process hazard analyses did not include at least one employee who had experience and knowledge specific to the process being evaluated.    a) On or about 2/13/2012, Alcohol Area:  Employees were not included in the Process Hazard Analysis (PHA)  process.       Abatement certification is required for this item.
Recent events (3)
  • — J (S) $2750
  • — C (S) $5000
  • — Z (S) $5000

1910.119 F01 I D

Serious Gravity 5 1 instance 8 exposed
Issued
May 24, 2012
Abate by
Jun 23, 2012
Penalty
Initial $5,000 · Current $2,750 Reduced
29 CFR 1910.119(f)(1)(i)(d): The employer had not developed and implemented written operating procedures that provided clear instructions for safely conducting activities involved in the covered process:    a) On or about 2/13/2012, Alcohol Area:   There were no written procedures for the start up, operation, shutdown and emergency shutdown of the Ethanol unit.    Abatement certification is required for this item.
Recent events (3)
  • — J (S) $2750
  • — C (S) $5000
  • — Z (S) $5000

1910.119 J05

Serious Gravity 5 10 instances 12 exposed
Issued
May 24, 2012
Abate by
Jun 23, 2012
Penalty
Initial $5,000 · Current $2,750 Reduced
29 CFR 1910.119(j)(5): The employer did not correct deficiencies in equipment that was outside acceptable limits (defined by the process safety information on paragraph (d) of this section) before use or in a safe and timely manner:    a) On or about 2/13/2012 and 3/14/2012, Alcohol Area:  In the Ethanol unit the following deficiencies were noted:         1) Tank 77 had a valve control arm that was being held closed with a large rubber band.         2) A bottom low pressure thermo couple and conduit, was not supported.         3) The main pump control had been pulled free from a column and was solely supported by its own conduit.         4) The bracket holding one of two LEL meters was broken, and the meter was suspended by conduit.          5) The second LEL meter was not secured, and suspended on the end of a piece of conduit.         6) A section of the PVC vent system was missing a support strap.           7)  None of the valving (shut off, emergency or bypass) was identified and labeled.         8) An emergency stop for the main alcohol pump, located outside of room 5a,  was lacking the entire stop button.    b) On or about 2/14/2012, Propellant Unit:  In the Propellant Unit the following deficiencies were noted:         1) A grounding strap leading from the flammable gas bulkhead to a tanker truck was not attached to bare metal of the tanker truck.          2) A product inlet valve for tank number 3 had a manufacturers flow direction opposite of what direction the product was flowing.    Abatement certification is required for this item.
Recent events (3)
  • — J (S) $2750
  • — C (S) $5000
  • — Z (S) $5000

1910.119 O01

Serious Gravity 5 1 instance 8 exposed
Issued
May 24, 2012
Abate by
Jun 15, 2012
Penalty
Initial $5,000 · Current $2,750 Reduced
29 CFR 1910.119(o)(1):  The employer did not certify that they have evaluated compliance with the provisions of this section at least every three years:    a) On or about 2/13/2012, Alcohol Area:   No Compliance Audits had been performed for the Alcohol Unit.    Abatement certification is required for this item.
Recent events (3)
  • — J (S) $2750
  • — C (S) $5000
  • — Z (S) $5000

View Zotos International, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 331914465.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.