On , OSHA opened a planned safety inspection of PALMER ENGINEERED PRODUCTS, INC. in 1310 W. MAIN ST., SPRINGFIELD, OH 45501 (NAICS 331524). OSHA activity number 335170585.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- PALMER ENGINEERED PRODUCTS, INC.
- Site address
- 1310 W. MAIN ST.
- City
- SPRINGFIELD
- State
- OH
- ZIP
- 45501
- Mailing
- P.O. BOX 1593, SPRINGFIELD, OH 45501
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 331524
- Employees
- 2
- Ownership type
- A
Citations
7 citations on file for this inspection.
1910.147 C04 I
- Issued
- Jul 25, 2012
- Abate by
- Aug 24, 2012
- Penalty
- Initial $2,200 · Current $2,200
General-duty citation text
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: (a) The written lockout program did not include provisions for conducting periodic or at least annual inspections of the energy control (lockout) procedures and how the company would deal with outside contractors.
Recent events (2)
- — I (S) $2200
- — Z (S) $2200
1910.147 C06 I
- Issued
- Jul 25, 2012
- Abate by
- Aug 24, 2012
- Penalty
- Initial $2,200 · Current $0 Reduced
General-duty citation text
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: (a) There had not been any periodic or at least annual inspections conducted of the energy control (lockout) procedures with records kept.
Recent events (2)
- — I (S) $0
- — Z (S) $2200
1910.147 C07 IV
- Issued
- Jul 25, 2012
- Abate by
- Aug 24, 2012
- Penalty
- Initial $2,200 · Current $0 Reduced
General-duty citation text
29 CFR 1910.147(c)(7)(iv): The employer did not certify that employee training had been accomplished and kept up to date: (a) The company did not certify that employee training on the energy control (lockout) had been accomplished and kept up to date.
Recent events (2)
- — I (S) $0
- — Z (S) $2200
1910.178 L01 II
- Issued
- Jul 25, 2012
- Abate by
- Aug 24, 2012
- Penalty
- Initial $1,760 · Current $800 Reduced
General-duty citation text
29 CFR 1910.178(l)(1)(ii): The employer did not ensure that each operator had successfully completed the training required by paragraph (l), except as permitted by paragraph (l)(5), prior to permitting an employee to operate a powered industrial vehicle (forklift): (a) The foundry man/pour off guy was not trained initially on the forklifts.
Recent events (2)
- — I (S) $800
- — Z (S) $1760
1910.178 L04 III
- Issued
- Jul 25, 2012
- Abate by
- Aug 24, 2012
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.178(l)(4)(iii): An evaluation of each powered industrial truck operator's performance was not being conducted at least once every three years: (a) The foundry man/pour off guy had not been evaluated on the forklifts in the last 3 years.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.178 L06
- Issued
- Jul 25, 2012
- Abate by
- Aug 24, 2012
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.178(l)(6): The employer did not certify that each operator has been trained and evaluated as required by this paragraph (l): (a) There were no records maintained that certified that forklift operator(s) had been trained and evaluated.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.212 A01
- Issued
- Jul 25, 2012
- Abate by
- Aug 24, 2012
- Penalty
- Initial $3,080 · Current $1,540 Reduced
General-duty citation text
29 CFR 1910.212(a)(1): One or more methods of machine guarding was not provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, ingoing nip points, rotating parts, pinch points, etc.: (a) On the Palmer Tilt mold machine, the pinch point created by the closing cycle of the mold was not guarded.
Recent events (2)
- — I (S) $1540
- — Z (S) $3080
More inspections at Palmer Engineered Products, INC.
View Palmer Engineered Products, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 331524)
More inspections in OH
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 335170585.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.