OSHA Inspection: CPC LABORATORIES, INC.

Complaint inspection · Health discipline

On , OSHA opened a complaint health inspection of CPC LABORATORIES, INC. in 9300 S. SANGAMON ST, CHICAGO, IL 60620 (NAICS 325611). OSHA activity number 335363594.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch CPC Laboratories, INC. — free Get an email when a new federal OSHA severe-injury report for CPC Laboratories, INC. is published. One employer, no account, unsubscribe in one click.
Site address
9300 S. SANGAMON ST
City
CHICAGO
State
IL
ZIP
60620
Mailing
9300 S. SANGAMON ST, CHICAGO, IL 60620
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
325611
Employees
250
Ownership type
A

9 citations on file for this inspection.

1910.22 A02

Serious Gravity 1 3 instances 15 exposed
Issued
Oct 11, 2012
Abate by
Nov 26, 2012
Penalty
Initial $1,964 · Current $1,375 Reduced
29 CFR 1910.22(a)(2):     The floor of every workroom shall be maintained in a clean and, so far as possible, a dry condition. Where wet processes are used, drainage shall be maintained, and false floors, platforms, mats, or other dry standing places should be provided where practicable.    a. White Room/ East Wall - On or about July 30, 2012, employees were required to work in an area where the metal grid on the drainage was not properly maintained. The conditions of the metal grid found were the following;    1. A portion of the metal grid of 1 1/2" lenght by 4" wdth was broken.    2. A portion of the metal grid of 2" length by 4" width was broken.     3. Some other portions of the metal grid were removed from their locations and were placed on the floor or leaning against the wall.
Recent events (2)
  • — I (S) $1374.8
  • — Z (S) $1964

1910.23 C01

Serious Gravity 1 1 instance 15 exposed
Issued
Oct 11, 2012
Abate by
Nov 26, 2012
Penalty
Initial $1,964 · Current $1,375 Reduced
29 CFR 1910.23(c)(1):     Every open-sided floor or platform 4 feet or more above adjacent floor or ground level shall be guarded by a standard railing (or the equivalent as specified in paragraph (e)(3) of this section) on all open sides except where there is entrance to a ramp, stairway, or fixed ladder. The railing shall be provided with a toeboard wherever, beneath the open sides,    a. West side of Blending Building - On or about July 23, 2012, employees were required to enter and leave the building through an outdoor walking platform at above 4 feet of the ground level. The walking platform was not guarded by a standard railing system on all open sides . Employees were thereby exposed to fall hazards.
Recent events (2)
  • — I (S) $1374.8
  • — Z (S) $1964

1910.23 D01 III

Serious Gravity 1 1 instance 15 exposed
Issued
Oct 11, 2012
Abate by
Nov 26, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.23(d)(1)(iii):     Every flight of stairs with more than 4 risers and at less than 44 inches wide shall be equipped with an standard railings on both open sides:      a. West side of Blending Building - On or about July 23, 2012, employees were required to enter and leave the building through an outdoor platform that had its staiway at less than 44 inches wide and was not equipped with railings on each side. Employees were thereby exposed to fall hazards.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.23 E01

Serious Gravity 1 1 instance 15 exposed
Issued
Oct 11, 2012
Abate by
Nov 26, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.23(e)(1):     A standard railing shall consist of top rail, intermediate rail, and posts, and shall have a vertical height of 42 inches nominal from upper surface of top rail to floor, platform, runway, or ramp level. The top rail shall be smooth-surfaced throughout the length of the railing. The intermediate rail shall be approximately halfway between the top rail and the floor, platform, runway, or ramp.     a. West side of Blending Building - On or about July 23, 2012, employees were required to enter and leave the building from a 52 inches metal platform that had its guardrailing system missing their intermediate railings. Employees were thereby exposed to the hazards of falls.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.132 D01 I

Serious Gravity 1 1 instance 15 exposed
Issued
Oct 11, 2012
Abate by
Nov 26, 2012
Penalty
Initial $1,964 · Current $1,375 Reduced

Hazardous substances 9908

29 CFR 1910.132(d)(1)(i):     Select, and have each affected employee use, the types of PPE that will protect the affected employee from the hazards identified in the hazard assessment;      a. Blending Department - On or about May 16, 2012, employee(s) were required to perform sanitizing operations with  the incorrect type selection on hand protection. Employees were thereby exposed to physical contact hazards with hot liquids.
Recent events (2)
  • — I (S) $1374.8
  • — Z (S) $1964

1910.132 D02

Serious Gravity 5 1 instance 15 exposed
Issued
Oct 11, 2012
Abate by
Nov 26, 2012
Penalty
Initial $0 · Current $0

Hazardous substances 22609908

29 CFR 1910.132(d)(2):     The employer shall verify that the required workplace hazard assessment has been performed through a written certification that identifies the workplace evaluated; the person certifying that the evaluation has been performed; the date(s) of the hazard assessment; and, which identifies the document as a certification of hazard assessment.    a. Blending Department - On or about July 23, 2012, the employees were required to perform sanitazion operations and to wear personal protective equipment (PPE) such as cloth gloves and other equipment. The employer did not verify that the required department's hazard assessment had been performed through a written certification.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.151 C

Serious Gravity 1 2 instances 5 exposed
Issued
Oct 11, 2012
Abate by
Nov 26, 2012
Penalty
Initial $1,964 · Current $1,375 Reduced

Hazardous substances 2260

29 CFR 1910.151(c):     Where the eyes or body of any person may be exposed to injurious corrosive materials, suitable facilities for quick drenching or flushing of the eyes and body shall be provided within the work area for immediate emergency use.  [63 FR 33450, June 18, 1998]    a. Blending Building - On or about July 30, 2012, employees required to work with corrosive chemicals, such as but not limited to sodium hydroxide, were not provided with adequate eye wash stations. The defficiencies found regarding eye wash stations and their locations were the following;    1. The Pre - weight room did not have an eye wash station.    2. The White room had an eye wash station that was not operable (low water flow).
Recent events (2)
  • — I (S) $1374.8
  • — Z (S) $1964

1910.37 A03

Other-than-serious 1 instance 10 exposed
Issued
Oct 11, 2012
Abate by
Oct 18, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.37(a)(3):     Exit routes must be free and unobstructed. No materials or equipment may be placed, either permanently or temporarily, within the exit route. The exit access must not go through a room that can be locked, such as a bathroom, to reach an exit or exit discharge, nor may it lead into a dead-end corridor. Stairs or a ramp must be provided where the exit route is not substantially level.    a.South Building Area/South side/Line #1/Exit Door # 3 - On or about July 23, 2012, the exit route of the building was obstructed with a wooden pallet containing carboard boxes. Employees were thereby potentially exposed to the hazard of fire.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

1910.303 B01 IV

Other-than-serious 1 instance 15 exposed
Issued
Oct 11, 2012
Abate by
Nov 26, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.303(b)(1)(iv):     Examination, Installation, and use of Equipment - Electric equipment shall be free from recognized hazards such as electrical insulation;    a. Enzyme Room/S-CMM-T - On or about July 23, 2012, the insulation on the electrical cord to the light indicator for the valve position (Open/Closed) was pulled away from its fitting.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

View CPC Laboratories, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 335363594.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.