Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: CARDWELL LUMBER INC.

Planned inspection · Health discipline

On , OSHA opened a planned health inspection of CARDWELL LUMBER INC. in HIGHWAY 15 NORTH 2 MILES, NOVELTY, MO 63460 (NAICS 321113). OSHA activity number 337045983.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Cardwell Lumber INC. — free Get an email when a new federal OSHA severe-injury report for Cardwell Lumber INC. is published. One employer, no account, unsubscribe in one click.
Site address
HIGHWAY 15 NORTH 2 MILES
City
NOVELTY
State
MO
ZIP
63460
Mailing
PO BOX 117, NOVELTY, MO 63460
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Health
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
321113
Employees
65
Ownership type
A

8 citations on file for this inspection.

1910.212 A01

Serious Gravity 5 1 instance 4 exposed
Issued
Jan 15, 2013
Abate by
Feb 19, 2013
Penalty
Initial $2,975 · Current $1,488 Reduced
29 CFR 1910.212(a)(1): One or more methods of machine guarding was not provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, ingoing nip points, rotating parts, flying chips and sparks:    (a) In the maintenance shop, employees were exposed to the rotating chucks on the drill press JET 420; Mfg No 39754 which was not guarded and could operate up to 2400 rpm.
Recent events (2)
  • — I (S) $1487.5
  • — Z (S) $2975

1910.265 C18 I

Serious Gravity 5 2 instances 6 exposed
Issued
Jan 15, 2013
Abate by
Mar 5, 2013
Penalty
Initial $2,975 · Current $1,488 Reduced
29 CFR 1910.265(c)(18)(i): The operation of conveyors was not be in accordance with American National Standard B20.1-1957 which states that pulley(s), sprocket(s), sheave(s), drum(s) and block(s) of conveyor(s) be arranged to prevent the possibility of injury due to hands or parts of clothing being caught between the belt(s) and pulley(s) or chain(s) and sprocket(s) or cable(s) and sheave(s), drum(s) or block(s):    (a) In the Stave Mill, at the top of the stairs used to access to the platform near the resaws, the belt and pulley on the conveyor belt to the resaw was not guarded to prevent the possible injury to employees hands or from clothing being caught between the belt and pulley.     (b) In the Stave Mill at the conveyor from the quarter saw to the resaw feed, the chain and sprocket on the conveyor was not guarded where the employee stood.  The unguarded chain and sprocket created a caught between hazard to employee hands and/or clothing.
Recent events (2)
  • — I (S) $1487.5
  • — Z (S) $2975

1910.304 G05

Serious Gravity 5 2 instances 2 exposed
Issued
Jan 15, 2013
Abate by
Feb 19, 2013
Penalty
Initial $2,975 · Current $1,488 Reduced
29 CFR 1910.304(g)(5): The path to ground from circuits, equipment, and enclosures was not permanent and continuous:    (a)  In the Stave Mill, near the resaws, two Stanley/Lasko fans were supplied power using at least two prong household extension cords and adapters.  The adapters bypassed the grounding of the fans creating an electrical shock hazard to employees.
Recent events (2)
  • — I (S) $1487.5
  • — Z (S) $2975

1910.305 B01 II

Serious Gravity 5 1 instance 5 exposed
Issued
Jan 15, 2013
Penalty
Initial $2,023 · Current $1,012 Reduced
29 CFR 1910.305(b)(1)(ii): Unused openings in cabinets, boxes, and fittings were not effectively closed.    (a)  In the Stave Mill, near the Brewco halving saw, an electrical switch junction box had openings that were not used.
Recent events (2)
  • — I (S) $1011.5
  • — Z (S) $2023

1910.305 G01 IV A

Serious Gravity 5 2 instances 5 exposed
Issued
Jan 15, 2013
Abate by
Feb 19, 2013
Penalty
Initial $2,380 · Current $1,190 Reduced
29 CFR 1910.305(g)(1)(iv)(A): Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure:    (a)  In the Stave Mill, near the resaws, two Stanley/Lasko fans were supplied power using household (two prong type) extension cords and adapters that were run from below the raised floor through the grating and were affixed to the raised structure.  The cords were used in place of fixed wiring.
Recent events (2)
  • — I (S) $1190
  • — Z (S) $2380

1910.305 G01 IV B

Serious Gravity 5 2 instances 5 exposed
Issued
Jan 15, 2013
Abate by
Feb 19, 2013
Penalty
Initial $2,380 · Current $1,190 Reduced
29 CFR 1910.305(g)(1)(iv)(B): Flexible cords and/or cables were run through holes in walls, ceilings, or floors:    (a)  In the Stave Mill, near the resaws, two Stanley/Lasko fans were supplied power using two prong household extension cords and adapters.  At least two extension cords were used in series and were run from below the raised floor through the grating and were affixed to the raised structure.
Recent events (2)
  • — I (S) $1190
  • — Z (S) $2380

1910.305 G02 III

Serious Gravity 5 1 instance 3 exposed
Issued
Jan 15, 2013
Abate by
Feb 11, 2013
Penalty
Initial $2,975 · Current $1,488 Reduced
29 CFR 1910.305(g)(2)(iii): Flexible cords and cables were not connected to devices and fittings so that strain relief was provided that would prevent pull from being directly transmitted to joints or terminal screws:    (a) In the Maintenance Shop, a Schumacher portable battery charger had a flexible power cord that was pulled from the equipment housing creating a shock hazard to employees.
Recent events (2)
  • — I (S) $1487.5
  • — Z (S) $2975

1910.334 A02 II

Serious Gravity 5 1 instance 3 exposed
Issued
Jan 15, 2013
Abate by
Feb 11, 2013
Penalty
Initial $2,100 · Current $1,050 Reduced
29 CFR 1910.334(a)(2)(ii): There was a defect or evidence of damage that could have exposed an employee to injury and the defective or damaged item was not removed from service:    (a) In the Maintenance Shop, a Schumacher battery charger had damaged and defective leads where the lead handles had exposed copper wire.  Employees were exposed to shock hazard.
Recent events (2)
  • — I (S) $1050
  • — Z (S) $2100

View Cardwell Lumber INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 337045983.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.