Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: ECHO LAKE FOODS INC.

Complaint inspection · Safety discipline

On , OSHA opened a complaint safety inspection of ECHO LAKE FOODS INC. in 33102 S HONEY LAKE ROAD, BURLINGTON, WI 53105 (NAICS 311412). OSHA activity number 338453830.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Echo Lake Foods INC. — free Get an email when a new federal OSHA severe-injury report for Echo Lake Foods INC. is published. One employer, no account, unsubscribe in one click.
Site address
33102 S HONEY LAKE ROAD
City
BURLINGTON
State
WI
ZIP
53105
Mailing
33102 SOUTH HONEY LAKE ROAD, BURLINGTON, WI 53105
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
311412
Employees
250
Ownership type
A

16 citations on file for this inspection.

1910.23 C01

Other-than-serious 1 instance 8 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $4,000 · Current $1,000 Reduced
29 CFR 1910.23(c)(1):     Open-sided floors and/or platforms four feet or more above adjacent floor or ground level were not guarded with standard railings (or equivalent):     (a) The path providing access to and egress from the West Engine Room (AKA: M & M Engine Room) was an open-sided platform that was 4 feet above ground level and was not guarded with standard railings, exposing workers to a potential fall hazard.
Recent events (3)
  • — F (O) $1000
  • — C (S) $4000
  • — Z (S) $4000

1910.24 F

Other-than-serious 1 instance 8 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $4,000 · Current $1,000 Reduced
29 CFR 1910.24(f): Rise height and tread width were not uniform throughout any flight of stairs including any foundation structure used as one or more treads of the stairs:     (a) The flight of stairs provided for the West Engine Room exit route did not have uniform rise height.  The top step had a rise of approximately 12 inches, whereas the bottom step had a rise of approximately 10 inches.
Recent events (3)
  • — F (O) $1000
  • — C (S) $4000
  • — Z (S) $4000

1910.36 G04

Serious Gravity 5 1 instance 8 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $5,000 · Current $4,300 Reduced
29 CFR 1910.36(g)(4): Objects that projected into the exit route reduced the width of the exit route to less than the minimum width requirements for exit routes:     (a) The exit route from the West Engine Room (AKA: M & M Engine Room) was reduced in width to less than 28 inches because of vessels, piping, and equipment involved with the West anhydrous ammonia system that projected into the exit route.  Specifically, the High Temperature Recirculation Tank and the Low Temperature Recirculation Tank, and associated structures were present and encroached upon this exit route.
Recent events (3)
  • — F (S) $4300
  • — C (S) $5000
  • — Z (S) $5000

1910.119 D02 I C

Serious Gravity 10 1 instance 300 exposed
Issued
Jul 23, 2013
Abate by
Aug 16, 2013
Penalty
Initial $7,000 · Current $7,000
29 CFR 1910.119(d)(2)(i)(C): Process safety information pertaining to the technology of the process did not include the maximum intended inventory:     (a) The employer's maximum intended inventory listed a design charge for the East Engine Room of 9,000 lbs.  During the OSHA inspection, the employer disclosed that on April 27, 2012, the East ammonia refrigeration system was (after a complete system pump down) recharged with 9,554 lbs anhydrous ammonia, which exceeded the listed design charge.  The employer also disclosed that their ammonia refrigeration system lost approximately 6.5 lbs ammonia per day due to leakage.  The East ammonia refrigeration system was additionally charged with 3058 lbs of ammonia on December 27, 2012.  After adding this 3058 lbs quantity of ammonia to the system which had contained 9,554 lbs (the quantity charged into it on April 27, 2012) and subtracting the quantity lost  due to leakage (approximately  1,560 lbs) during the 240 day time frame, the resultant quantity of ammonia in the system on December 27, 2012 was approximately 11,052 lbs, which exceeded both the listed design charge for the East Engine Room and the threshold quantity listed for anhydrous ammonia in Appendix A of this standard.  In summary, the employer's maximum intended inventory for the East Engine Room did not have a factual basis.
Recent events (3)
  • — F (S) $7000
  • — C (S) $7000
  • — Z (S) $7000

1910.119 D03 I D

Serious Gravity 10 1 instance 300 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $7,000 · Current $7,000
29 CFR 1910.119(d)(3)(i)(D): The employer did not include, in the process safety information compilation, the relief system design and the design basis:     (a) With regard to the East anhydrous ammonia refrigeration system at the Burlington facility, the process safety information compilation did not include the design basis for, but not limited to the pressure relief header system, pressure vessels, compressors, evaporators and condensers.
Recent events (3)
  • — F (S) $7000
  • — C (S) $7000
  • — Z (S) $7000

1910.119 D03 II

Serious Gravity 10 1 instance 300 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $7,000 · Current $0 Reduced
29 CFR 1910.119(d)(3)(ii): The employer did not document that equipment complies with recognized and generally accepted good engineering practices.    (a) Although the employer did have a document entitled, "Safety System Design - East Compressor Room", which included information regarding actuation of the emergency ventilation system by the ammonia detection system, the provided information was inadequate with regard to its description of the inlet louver, which did not take into account that this was a manually operated louver.  According to the provided document, the ventilation system was designed to meet and exceed the requirements of ANSI/IIAR 2 - 1999.  However, whereas ANSI/IIAAR 2 - 1999 specified that provision shall be made for inlet air to replace that being exhausted, the only provision for inlet air in the East Compressor Room was by means of a manually operated louver, which was normally in the closed position, consisting of a plywood board secured by a locking pin.  Since this manually operated louver would not be actuated by the ammonia detection system, in the event of an ammonia release the emergency ventilation system would not function in accordance to the design specifications as described by the document provided by the employer.   This condition could result in a hazardous accumulation of ammonia vapor in the East Compressor Room.
Recent events (3)
  • — F (S) $0
  • — C (S) $7000
  • — Z (S) $7000

1910.119 E03 IV

Serious Gravity 10 4 instances 300 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $7,000 · Current $0 Reduced
29 CFR 1910.119(e)(3)(iv): The process hazard analysis did not address the consequences of failure of engineering and administrative controls.    (a) Process Hazard Analysis (PHA) item #4.13 did not address the consequence of failures of engineering or administrative controls [as referenced in 1910.119(e)(3)(iv)].  PHA #4.13 addressed: "What if there is a high level in the vessel?"  The PHA described the resulting scenario: "NH3 carries over to compressor. Slugging of compressor occurs...resulting in an NH3 release."  Regarding engineering and/or administrative controls, the PHA stated that: "Compressor shutdown interlocks."   The consequences of failure of the interlocks to effect compressor shutdown, in the event of a high level in the vessel, were not addressed as required by 1910.119(e)(3)(iv).    (b) Process Hazard Analysis (PHA) item #12.5 did not address the consequence of failures of engineering or administrative controls  [as referenced in 1910.119(e)(3)(iv)].  PHA #12.5 addressed: "What if the emergency ventilation system is non existent, inadequate or inoperable during an emergency situation ?"  Regarding engineering and/or administrative controls, the PHA stated that "Current ventilation is adequate."  However, this PHA did not take into account that the make-up air for the emergency ventilation system in the East Compressor Room depended on a manually operated inlet louver, and thus would not be automatically activated by the ammonia detection system.  The consequences of failure of the manually operated inlet louver to be opened, in an ammonia release emergency situation, were not addressed as required by 1910.119(e)(3)(iv).     (c) Process Hazard Analysis (PHA) item #16.8 did not address the consequence of failures of engineering or administrative controls [as referenced in 1910.119(e)(3) (iv)].  PHA #16.8 addressed: "What if ignition sources are present in a machinery/vessel room with an explosive mixture of NH3?" Regarding engineering and/or administrative controls, the PHA stated that "Detection and ventilation systems are designed to evacuate NH3 and shutdown system if necessary."  However, this PHA did not take into account that the make-up air for the emergency  ventilation system in the  East Compressor Room depended on a manually operated inlet louver, and thus would not be automatically activated by the ammonia detection  system.  The consequences of failure of the manually operated inlet louver to be opened, in an ammonia release emergency situation, were not addressed as required by 1910.119(e)(3)(iv).    (d) Process Hazard Analysis (PHA) item #17.1 did not address the consequence of failures of engineering or administrative controls [as referenced in 1910.119(e)(3)(iv)].  PHA #17 identified a previous ammonia release incident in the East Compressor Room when a shaft seal on #6 Booster leaked, saturating the room  with ammonia and the ventilation was inadequate.  The PHA indicated that a wall louver, an engineering control, was installed next to #6 Booster, allowing replacement of air being exhausted.  Also the PHA indicated the existing engineering controls included an ammonia detection system that would activate the ventilation, and that no further mitigation action was required.  However, this PHA did not take into that the referenced wall louver required manual operation, and thus would not be automatically be activated by the ammonia detection system.  The consequences of failure of the manually operated inlet louver to be opened, in an ammonia release emergency situation, were not addressed as required by 1910.119(e)(3)(iv).
Recent events (3)
  • — F (S) $0
  • — C (S) $7000
  • — Z (S) $7000

1910.119 E05

Serious Gravity 10 4 instances 300 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $7,000 · Current $0 Reduced
29 CFR 1910.119(e)(5): The employer did not assure that PHA recommendations were resolved in a timely manner:     The following items were not corrected as soon as possible:    (a) PHA 4.8 relating to the hazard of external corrosion on vessels listed the corrective action as "Ensure mechanical integrity inspections include vessel inspection."  The original due date of 11/30/2012 was extended to 5/1/2013 and the item status was listed as: "In progress."     (b) PHA 5.6, relating to the hazard of additional weight of ice on evaporator breaks/deflects structural support listed corrective action as "Ensure mechanical integrity inspections include evaporator support inspections."  the original due dated of 11/30/12 was extended to 5/1/13, and the item status was listed as: "In progress."     (c) PHA 7.1, relating to the hazard of external corrosion on ammonia pump piping, listed the corrective action as: "Ensure MI inspections address piping conditons."  The original due date of 11/30/2012 was extended to 5/1/2013 and the item status was listed as: "In progress."     (d) PHA 7.14, relating to the hazard of pump valves left in the shut or open position for a long period of time without cycling, listed corrective action as "Add valve inspections to PM system."  The original due date of 8/30/2012 was extended to 5/1/2013 and the item status was listed as: "Incomplete."
Recent events (3)
  • — F (S) $0
  • — C (S) $7000
  • — Z (S) $7000

1910.119 F01 I B

Other-than-serious 7 instances 300 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $5,000 · Current $1,000 Reduced
29 CFR 1910.119(f)(1)(i)(B): The employer did not develop and implement written operating procedures that provide clear instructions for safely conducting activities involved in each covered process consistent with the process safety information and did not address normal operations:     (a) Operating procedures for East Engine Room compressor C-1 did not include detailed procedures for oil draining operations suitable for its drain point.       (b) Operating procedures for East Engine Room compressor C-2 did not include detailed procedures for oil draining operations suitable for its drain point.     (c) Operating procedures for East Engine Room compressor  C-3 did not include detailed procedures for oil draining operations suitable for its drain point.     (d) Operating procedures for East Engine Room compressor C-4 did not include detailed procedures for oil draining operations suitable for its drain point.      (e) Operating procedures for East Engine Room compressor C-5 did not include detailed procedures for oil draining operations suitable for its drain point.     (f) Operating procedures for East Engine Room compressor C-6 did not include detailed procedures for oil draining operations suitable for its drain point.      (g) East Ammonia System: The operating procedure for the East HTR Oil Pot V-4 did not include detailed procedures for oil draining operations suitable for its drain point.
Recent events (3)
  • — F (O) $1000
  • — C (S) $5000
  • — Z (S) $5000

1910.119 G01 I

Serious Gravity 10 1 instance 300 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $7,000 · Current $7,000

Hazardous substances 0170

29 CFR 1910.119(g)(1)(i): The employer did not train each employee before being involved in operating a newly assigned process in the operating procedures as specified in paragraph (f) of this section:     (a) East Ammonia Refrigeration System:  Adequate training was not provided and documented regarding operating procedures for processes and ammonia refrigeration equipment.  Nor was adequate training provided and documented regarding operational phases, operational limits and safety and health considerations.     (b) Adequate training was not provided to workers performing daily rounds, during which observations and readings were taken on various process equipment in the East Ammonia System.  For example, the training provided to these workers did not cover the consequences of deviation from operational limits for the process equipment.
Recent events (3)
  • — F (S) $7000
  • — C (S) $7000
  • — Z (S) $7000

1910.119 G03

Serious Gravity 5 1 instance 500 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.119(g)(3): 29 CFR 1910.119(g)(3):  The employer did not maintain a record of training for employees operating a covered process:    (a) The employer provided operating procedures for ammonia refrigeration equipment, but did not provide any documentation of training for the operators.
Recent events (3)
  • — F (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.119 C01

Serious Gravity 5 1 instance 300 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $5,000 · Current $0 Reduced

Hazardous substances 0170

29 CFR 1910.119(c)(1):     The employer did not develop a written plan of action regarding the implementation of employee participation:    (a) East Ammonia Refrigeration System: A written plan had not been established and implemented for employee participation, including methods the employer used to consult with employees on the conduct and development of process hazard analyses, and including provision of employee access to to process hazard analyses and to all other information required to be developed under this standard.
Recent events (3)
  • — F (S) $0
  • — C (S) $5000
  • — Z (S) $5000

1910.119 J02

Serious Gravity 10 1 instance 300 exposed
Issued
Jul 23, 2013
Abate by
Aug 16, 2013
Penalty
Initial $7,000 · Current $7,000
29 CFR 1910.119(j)(2): The employer did not establish or implement written procedures to maintain the on-going integrity of process equipment.   (a) East Ammonia Refrigeration System: Written procedures to maintain the on-going integrity of process equipment had not been implemented for equipment such as but not limited to pressure vessels, piping systems, pressure relief systems and emergency control systems.
Recent events (3)
  • — F (S) $7000
  • — C (S) $7000
  • — Z (S) $7000

1910.119 L02

Serious Gravity 10 1 instance 300 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $7,000 · Current $5,000 Reduced
29 CFR 1910.119(l)(2): Management of change procedures did not assure that the considerations required by (l)(2)(1) through (l)(2)(v) were addressed prior to any change:    (a) For example, in April 2012, two smaller condensers atop the East Compressor Room were replaced by a large roof-top condenser, but no managment of change was conducted to to evaluate the considerations required by (l)(2)(i) through (1)(2)(v).
Recent events (3)
  • — F (S) $5000
  • — C (S) $7000
  • — Z (S) $7000

1910.151 C

Serious Gravity 5 1 instance 8 exposed
Issued
Jul 23, 2013
Abate by
Jun 2, 2014
Penalty
Initial $5,000 · Current $5,000
29 CFR 1910.151(c):     Where employees were exposed to injurious corrosive materials, suitable facilities for quick drenching or flushing of the eyes and body were not provided within the work area for immediate emergency use: (a) In the area of the West Engine Room workers' eyes and bodies were potentially exposed to anhydrous ammonia, a corrosive chemical.  Yet no suitable emergency eyewash and safety shower were provided in the area of the West Engine Room.  For example, there was no emergency eyewash and safety shower installed just outside the engine room's exit door (in accordance with IIAR Bulletin 109).
Recent events (3)
  • — F (S) $5000
  • — C (S) $5000
  • — Z (S) $5000

1910.305 B02 I

Deleted Serious Gravity 5 1 instance 8 exposed
Issued
Jul 23, 2013
Penalty
Initial $5,000 · Current $0 Reduced
29 CFR 1910.305(b)(2)(i): Pull boxes, junction boxes, and fittings were not provided with covers approved for the purpose:  (a) On or around January 24, 2013, in the East Engine Room, covers for several electrical switches on the Vilter #5 Low Stage Compressor were not in place (covers had previously been removed to enable replacement of these switches, although the maintenance activity was not ongoing).  The circuit breaker controlling power to these switches was in the off position, but no lockout device had been affixed to the circuit breaker by the authorized employee.
Recent events (3)
  • — F (S) $0
  • — C (S) $5000
  • — Z (S) $5000

View Echo Lake Foods INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 338453830.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.