OSHA Inspection: A & S CONSTRUCTION, INC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of A & S CONSTRUCTION, INC in 3716 PAULDING AVE, BRONX, NY 10467 (NAICS 238130). OSHA activity number 338751837.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch A & S Construction, INC — free Get an email when a new federal OSHA severe-injury report for A & S Construction, INC is published. One employer, no account, unsubscribe in one click.
Site address
3716 PAULDING AVE
City
BRONX
State
NY
ZIP
10467
Mailing
126-05 97TH AVE, RICHMOND HILL, NY 11418
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238130
Employees
5
Ownership type
A

7 citations on file for this inspection.

1926.25 A

Serious Gravity 1 1 instance 5 exposed
Issued
Feb 25, 2013
Penalty
Initial $1,200 · Current $720 Reduced
29 CFR 1926.25(a): During the course of construction, alteration, or repairs, form and scrap lumber with protruding nails, and all other debris, shall be kept cleared from work areas, passageways, and stairs, in and around buildings or other structures:    On or about 2/7/2013, Paulding Ave.    a) The employees were working in the side yard and there was debris obstructing their passageway.
Recent events (3)
  • — C (S) $1200
  • — F (S) $720
  • — Z (S) $1200

1926.403 D01

Serious Gravity 1 2 instances 2 exposed
Issued
Feb 25, 2013
Penalty
Initial $1,200 · Current $720 Reduced
29 CFR 1926.403(d)(1): Mounting. Electric equipment shall be firmly secured to the surface on which it is mounted. Wooden plugs driven into holes in masonry, concrete, plaster, or similar materials shall not be used:    On or about 2/7/2013, Paulding Ave.    a) The employees used the outlet to energize their tools. It was not secured in place.
Recent events (3)
  • — C (S) $1200
  • — F (S) $720
  • — Z (S) $1200

1926.405 B02

Serious Gravity 1 2 instances 2 exposed
Issued
Feb 25, 2013
Penalty
Initial $0 · Current $0
29 CFR 1926.405(b)(2): Covers and canopies. All pull boxes, junction boxes, and fittings shall be provided with covers. If metal covers are used, they shall be grounded. In energized installations each outlet box shall have a cover, faceplate, or fixture canopy. Covers of outlet boxes having holes through which flexible cord pendants pass shall be provided with bushings designed for the purpose or shall have smooth, well-rounded surfaces on which the cords may bear:    On or about 2/7/2013, 1st and 2nd Floors    a) The 110 electrical panels were live and not covered.
Recent events (3)
  • — C (S) $0
  • — F (S) $0
  • — Z (S) $0

1926.404 B01 I

Serious Gravity 1 2 instances 2 exposed
Issued
Feb 25, 2013
Penalty
Initial $1,200 · Current $720 Reduced
29 CFR 1926.404(b)(1)(i): General. The employer shall use either ground fault circuit interrupters as specified in paragraph (b)(1)(ii) of this section or an assured equipment grounding conductor program as specified in paragraph (b)(1)(iii) of this section to protect employees on construction sites. These requirements are in addition to any other requirements for equipment grounding conductors:    On or about 2/7/2013, 2nd Floor and Side Yard    a) The employees were using extension cords to energize their tools. They did not have a ground fault circuit interupters.
Recent events (3)
  • — C (S) $1200
  • — F (S) $720
  • — Z (S) $1200

1926.404 F06

Serious Gravity 1 1 instance 1 exposed
Issued
Feb 25, 2013
Penalty
Initial $1,200 · Current $720 Reduced
29 CFR 1926.404(f)(6): Grounding path. The path to ground from circuits, equipment, and enclosures shall be permanent and continuous:    On or about 2/7/2013, 2nd Floor    a) The employee was using an extension cord to energize his Dewalt screwgun. The extension cord had the ground pin broken off.
Recent events (3)
  • — C (S) $1200
  • — F (S) $720
  • — Z (S) $1200

1926.416 E01

Serious Gravity 1 1 instance 1 exposed
Issued
Feb 25, 2013
Penalty
Initial $0 · Current $0
29 CFR 1926.416(e)(1): Worn or frayed electric cords or cables shall not be used.      On or about 2/7/2013, 2nd Floor    a) The employee was using the extension cord to energize his power tool. The extension cord was frayed and had exposed wires.
Recent events (3)
  • — C (S) $0
  • — F (S) $0
  • — Z (S) $0

1926.501 B01

Serious Gravity 5 1 instance 2 exposed
Issued
Feb 25, 2013
Penalty
Initial $2,000 · Current $1,200 Reduced
29 CFR 1926.501(b)(1): "Unprotected sides and edges." Each employee on a walking/working surface (horizontal and vertical surface) with an unprotected side or edge which is 6 feet (1.8 m) or more above a lower level shall be protected from falling by the use of guardrail systems, safety net systems, or personal fall arrest systems:    On or about 2/7/2013, 2nd Floor      a) The employees used a stairs with an unprotected side to gain access to and from the 2nd floor.
Recent events (3)
  • — C (S) $2000
  • — F (S) $1200
  • — Z (S) $2000

View A & S Construction, INC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 338751837.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.