Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,195,903Inspections Most recent open 2026-08-18 Last loaded 2026-08-21

OSHA Inspection: ARCTIC GLACIER U.S.A., INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of ARCTIC GLACIER U.S.A., INC. in 900 TURK HILL ROAD, FAIRPORT, NY 14450 (NAICS 312113). OSHA activity number 338914666.

What this inspection record means

OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Arctic Glacier U.S.A., INC. for free Get an email when a new federal OSHA severe-injury report for Arctic Glacier U.S.A., INC. is published. One employer, no account, unsubscribe in one click.
Site address
900 TURK HILL ROAD
City
FAIRPORT
State
NY
ZIP
14450
Mailing
900 TURK HILL ROAD, FAIRPORT, NY 14450
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
Non-union (B)
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
312113
Employees
47
Ownership type
Private (A)

13 citations on file for this inspection.

1910.23 D01 IV

Other-than-serious 1 instance 4 exposed
Issued
Aug 20, 2013
Penalty
Initial $3,300 · Current $6,400
29 CFR 1910.23(d)(1)(iv):     Stairways more than 44 inches wide but less than 88 inches wide, did not have one handrail on each enclosed side and one stair railing on each open side.      a) On or about 2/21/13 stairway entrance to Turbo Room 1 & 2; enclosed stairway with a width of 48 inches did not have a handrail on the left side descending.       No Abatement Certification Required
Recent events (3)
  • · J (O) $6400
  • · C (S) $3300
  • · Z (S) $3300

1910.24 E

Other-than-serious 1 instance 4 exposed
Issued
Aug 20, 2013
Abate by
Sep 20, 2013
Penalty
Initial $5,500 · Current $12,800
29 CFR 1910.24(e):     Fixed stairs were not installed at angles to the horizontal between 30 degrees and 50 degrees.      a) On or about 2/21/13 in the Main Plant; the stairs in the north hallway, used to access the second floor and the Turbo area, were at an angle of 55 degrees to the horizontal.      b) On or about 3/21/13 in the Main Plant; the stairs which provide access to the roof from the Turbo 5 area, were at an angle of 60 degrees to the horizontal.      Abatement Certification Required
Recent events (3)
  • · J (O) $12800
  • · C (S) $5500
  • · Z (S) $5500

1910.119 E03 V

Deleted Serious Gravity 5 1 instance 4 exposed
Issued
Aug 20, 2013
Abate by
Sep 20, 2013
Penalty
Initial $5,500 · Current $0 Reduced
29 CFR 1910.119(e)(3)(v): The process hazard analysis did not address facility siting.  a) On or about 2/26/13 in the area between Dock #9 and the ramp to Dock #7; the employer's process hazard analysis, conducted on May 20, 2011, failed to address the hazards of specific ammonia pipes being struck by moving vehicles, such as but not limited to, the four inch ammonia line suction line, along the north side of the Dock #7 ramp.     Abatement Certification Required
Recent events (3)
  • · J (S) $0
  • · C (S) $5500
  • · Z (S) $5500

1910.119 F01 II A

Deleted Serious Gravity 5 1 instance 2 exposed
Issued
Aug 20, 2013
Abate by
Sep 20, 2013
Penalty
Initial $5,500 · Current $0 Reduced
29 CFR 1910.119(f)(1)(ii)(A):   Written operating procedures did not address the consequences of deviations;    a) On or about 2/21/13 throughout the Main Plant; oil draining procedures, such as but not limited to, Intercooler Float Column ( IC1-11), House Oil Pot ( CPL-17), Ice Oil Pot (CPL-12), Gylcol Cooler ( HX1-21, HX1-19), did not include the consequences of trapping ammonia between two closed valves.    Abatement Certification Required
Recent events (3)
  • · J (S) $0
  • · C (S) $5500
  • · Z (S) $5500

1910.147 C05 I

Deleted Serious Gravity 5 1 instance 2 exposed
Issued
Aug 20, 2013
Penalty
Initial $5,500 · Current $0 Reduced
29 CFR 1910.147(c)(5)(i): Locks, tags, chains, wedges, key blocks, adapter pins, self-locking fasteners, or other hardware were not provided by the employer for isolating, securing or blocking of machines or equipment from energy sources:  a) On or about 2/26/13 in the #7 Screw Conveyor area; an employee assisting with the installation of a new horizontal and vertical screw conveyor to feed ice to the Sorting System and Ice Rake, was not provided with hardware, such as but not limited to locks, tags, fasteners, for isolating the hazardous energy sources associated with this service and maintenance work activity.    Abatement Certification Required
Recent events (3)
  • · J (S) $0
  • · C (S) $5500
  • · Z (S) $5500

1910.147 D04 I

Deleted Serious Gravity 5 1 instance 2 exposed
Issued
Aug 20, 2013
Penalty
Initial $5,500 · Current $0 Reduced
29 CFR 1910.147(d)(4)(i): Lockout or tagout devices were not affixed to each energy isolating device by authorized employees:   a) On or about 2/26/13 in the #7 Screw Conveyor area; employer does not protect employees from hazardous energy sources when they are involved in service and maintenance activites.  A recent example is when three employees were installing a new horizontal and vertical screw conveyor to feed ice to the Sorting system and Ice Rake and only two locks were attached to each of the two energy sources.    Abatement Certification Required
Recent events (3)
  • · J (S) $0
  • · C (S) $5500
  • · Z (S) $5500

1910.303 G01 II

Serious Gravity 1 1 instance 2 exposed
Issued
Aug 20, 2013
Penalty
Initial $3,300 · Current $7,000
29 CFR 1910.303(g)(1)(ii): The required working space about electric equipment rated 600 volts, nominal, or less to ground, was used for storage:    a) On or about 2/21/13 in the Wash House; empty 5 gallon and one gallon plastic pails, stacks of plastic packing materials and plastic crates were found stacked in front of electrical panels C-11 and C- 24 and two local disconnects, 480 and 208 volts AC, impeding access.        No Abatement Certification Required
Recent events (3)
  • · J (S) $7000
  • · C (S) $3300
  • · Z (S) $3300

1910.305 A02 I

Serious Gravity 5 1 instance 3 exposed
Issued
Aug 20, 2013
Penalty
Initial $4,400 · Current $12,800
29 CFR 1910.305(a)(2)(i): Temporary electrical power and lighting installations rated 600 volts, nominal, or less were used for purposes other than those permitted in subparagraphs (A), (B) and (C) of this paragraph:    a) On or about 2/21/13 in the Block Press machine;  a relocatable power tap was attached to the side of the (ice) Block Press machine with plastic ties, plugged into an extension cord and being used to supply power to the hopper shakers on the fill chute of this machine exposing employees to contact with electric current and fire.      No Abatement Certification Required
Recent events (3)
  • · J (S) $12800
  • · C (S) $4400
  • · Z (S) $4400

1910.305 G01 IV A

Deleted Serious Gravity 5 2 instances 3 exposed
Issued
Aug 20, 2013
Penalty
Initial $4,400 · Current $0 Reduced
29 CFR 1910.305(g)(1)(iv)(A):   Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure:  a) On or about 2/21/13 in the Packaging area on 525 Bagger; an extension cord was being used to supply power to a portable hot air gun which was being used to warm safety switches on the bagging machine exposing employees to contact with electric current.    No Abatement Certification Required
Recent events (3)
  • · J (S) $0
  • · C (S) $4400
  • · Z (S) $4400

1910.119 J02

Deleted Repeat Gravity 10 1 instance 12 exposed
Issued
Aug 20, 2013
Abate by
Sep 20, 2013
Penalty
Initial $38,500 · Current $0 Reduced
29 CFR 1910.119(j)(2): The employer did not establish written procedures to maintain the on-going integrity of process equipment:  a) On or about 2/26/13 throughout the ammonia refrigeration facility; employer did not have a written procedure that described the inspection and testing of the ammonia refrigeration piping systems  ( insulated and uninsulated piping ) in the Main building and Building #11.    b) On or about 2/26/13 throughout the ammonia refrigeration facility; employer did not have a written procedure which described the inspection and testing of the ammonia refrigeration pressure vessels and tanks ( insulated and uninsulated ) in the Main building and Building #11.    c) On or about 2/26/13 throughout the ammonia refrigeration facility; employer did not have a written procedure which described the inspection and testing of the ammonia refrigeration safety relief devices in the Main Building and Building #11.    d) On or about 2/26/13 throughout the ammonia refrigeration facility; employer did not have a written procedure which described the testing of the ammonia compressors in the Main Building.    e) On or about 2/26/13 throughout the ammonia refrigeration facility; employer did not have a written procedure which described the inspection and testing of the ammonia pumps in the Main Building.    Abatement Documentation Required  Arctic Glacier was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1910.119 (j) (2), which was contained in OSHA inspection number 314235276, Citation Number 1, Item Number 4A and was affirmed as a final order on 12/08/12, with respect to a workplace located at 410 Bethel Avenue, Aston, Pa. 19014.
Recent events (3)
  • · J (R) $0
  • · C (R) $38500
  • · Z (R) $38500

1910.119 J04 III

Deleted Repeat Gravity 10 2 instances 12 exposed
Issued
Aug 20, 2013
Abate by
Sep 20, 2013
Penalty
Initial $38,500 · Current $0 Reduced
29 CFR 1910.119(j)(4)(iii): The frequency of inspections and tests of process equipment to maintain its mechanical integrity, was not consistent with applicable manufacturer's recommendations and good engineering practices, or more frequently determined to be necessary by prior operating experience:   a) On or about 2/26/13 throughout the ammonia refrigeration facility; employer last conducted non destructive testing of the ammonia refrigeration pressure vessels and tanks ( insulated and un-insulated ), such as but not limited to, House Accumulator HAC 1, Receiver R-1, Master Oil Seperator MOS-2, Intercooler IC-1, in the Main building on or about May 2005.  Section 6.4.4 of the International Institute of Ammonia Refrigeration (IIAR) Bulletin 110, 3/93 requires testing at least every five years and the results of vessel testing conducted by a contract testing company in 2005 established next testing to be conducted in five years.    Abatement Documentation  Arctic Glacier was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1910.119 (j)(4)(iii), which was contained in OSHA inspection number 3116154069 Citation Number 1, Item Number 22B and was affirmed as a final order on 09/12/08, with respect to a workplace located at 900 Turk Hill Road, Fairport, New York 14450.
Recent events (3)
  • · J (R) $0
  • · C (R) $38500
  • · Z (R) $38500

1910.119 J04 IV

Serious Gravity 10 1 instance 12 exposed
Issued
Aug 20, 2013
Abate by
Sep 20, 2013
Penalty
Initial $0 · Current $21,000
29 CFR 1910.119(j)(4)(iv): The employer did not document each inspection and test that had been performed on process equipment.  The documentation did not identify the date of the inpsection or test, the name of the person who performed the inspection or test, the serial number or other identifier of the equipment on which the inspection or test was performed, a description of the inspection or test performed, and the results of the inspection or test.    a) On or about 2/24/13 throughout the facility; visual inspections of the Main Plant and Building 11 ammonia piping ( insulated and uninsulated), performed since May 2008, were not documented.      Abatement Documentation Required       Arctic Glacier was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1910.119 (j)(4)(iv), which was contained in OSHA inspection number 312235276, Citation Number 1, Item Number 4b and was affirmed as a final order on 12/08/11, with respect to a workplace located at 410 Bethel Avenue, Aston, PA, 19014.
Recent events (3)
  • · J (S) $21000
  • · C (R) $0
  • · Z (R) $0

1910.147 C07 I A

Deleted Repeat Gravity 5 1 instance 2 exposed
Issued
Aug 20, 2013
Penalty
Initial $27,500 · Current $0 Reduced
29 CFR 1910.147 (c)(7)(i)(A): Authorized employee(s) did not receive training in the methods and means necessary for energy isolation;    a) On or about 2/26/13 in the #7 Screw Conveyor area; employees who performed maintenance tasks only allowable to authorized employees, such as but not limited to, assisting with the installation of a new horizontal and vertical screw conveyor, did not receive the necessary training for the application of Lockout/Tagout ( LOTO ) on the energy isolation devices.            No Abatement Certification Required   Arctic Glacier was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29CFR 1910.147 (c)(7)(i)(A), which was contained in OSHA inspection number 312386097, Citation Number 1, Item Number 3 and was affirmed as a final order on 12/11/08, with respect to a workplace located at  130 E. 42nd Street, Lubbock, Texas 79404.
Recent events (3)
  • · J (R) $0
  • · C (R) $27500
  • · Z (R) $27500

View Arctic Glacier U.S.A., INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). OSHA publishes its own view of this case as inspection number 338914666.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.