On , OSHA opened a planned safety inspection of DA EUN PACIFIC in LOT # 5166-6-R3 BLDG. 1A, TAMUNING, GU 96913 (NAICS 332999). OSHA activity number 339016222.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- DA EUN PACIFIC
- Site address
- LOT # 5166-6-R3 BLDG. 1A
- City
- TAMUNING
- State
- GU
- ZIP
- 96913
- Mailing
- 1270 N. MARINE DRIVE STE. 101 PMB 439, TAMUNING, GU 96913
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 332999
- Employees
- 5
- Ownership type
- A
Citations
3 citations on file for this inspection.
1910.23 C01
- Issued
- May 30, 2013
- Abate by
- May 30, 2013
- Penalty
- Initial $1,301 · Current $1,301
General-duty citation text
29 CFR 1910.23(c)(1): Open-sided floors and/or platforms four feet or more above adjacent floor or ground level were not guarded with standard railings (or equivalent) and toeboards: a) Shop, platform above offices - On or about 4/22/13, and at times prior thereto, the open edge of a storage platform was missing a railing thereby exposing employees to a fall hazard of 8 feet, 6 inches.
Recent events (1)
- — Z (S) $1301
1910.215 A04
- Issued
- May 30, 2013
- Abate by
- May 30, 2013
- Penalty
- Initial $1,224 · Current $1,224
General-duty citation text
29 CFR 1910.215(a)(4): Work rest(s) on grinding machinery were not adjusted closely to the wheel with a maximum opening of one eighth inch: a) Shop - On or about 4/22/13 and at times prior thereto, a Ryobi double wheeled bench grinder had a measured 1/2" gap between the workrest and the abrasive wheels on both sides.
Recent events (1)
- — Z (S) $1224
1910.303 G01
- Issued
- May 30, 2013
- Abate by
- May 30, 2013
- Penalty
- Initial $780 · Current $780
General-duty citation text
29 CFR 1910.303(g)(1): Sufficient access and working space was not provided and maintained about all electric equipment (operating at 600 volts, nominal, or less to ground) to permit ready and safe operation and maintenance of such equipment: a) Shop, bay door near Harmon Industrial Park - On or about 4/22/13 and at times prior thereto, an electrical panel board was blocked by duct work and insulation and did not permit a 3-foot minimum clearance.
Recent events (1)
- — Z (S) $780
More inspections at DA EUN Pacific
View DA EUN Pacific's full OSHA safety record →
More inspections in this industry (NAICS 332999)
More inspections in GU
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339016222.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.