Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: CORTEC CORPORATION

Planned inspection · Health discipline

On , OSHA opened a planned health inspection of CORTEC CORPORATION in 1300 SOUTH RIVER ST., SPOONER, WI 54801 (NAICS 561990). OSHA activity number 339246340.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Cortec Corporation — free Get an email when a new federal OSHA severe-injury report for Cortec Corporation is published. One employer, no account, unsubscribe in one click.
Establishment
CORTEC CORPORATION
Site address
1300 SOUTH RIVER ST.
City
SPOONER
State
WI
ZIP
54801
Mailing
1300 SOUTH RIVER ST., SPOONER, WI 54801
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
561990
Employees
7
Ownership type
A

12 citations on file for this inspection.

1910.106 D04 I

Serious Gravity 5 1 instance 7 exposed
Issued
Nov 26, 2013
Abate by
Apr 9, 2014
Penalty
Initial $3,825 · Current $1,915 Reduced
29 CFR 1910.106(d)(4)(i): "Construction." Openings to other rooms or buildings were not provided with noncombustible liquid-tight raised sills or ramps at least 4 inches in height, or the floor in the storage area was not at least 4 inches below the surrounding floor. A permissible alternate to the sill or ramp was not an open-grated trench inside of the room which drains to a safe location:     (a) Hazardous Material Storage and Mixing Room; The inside flammable storage room had openings to other rooms (gap under door 109B to Manufacturing 2) and did not have liquid-tight raised sills or ramps at least 4 inches in height, flooring 4 inches below grade, and/or drainage to a safe location as the drains were intentionally plugged.
Recent events (2)
  • — I (S) $1915
  • — Z (S) $3825

1910.106 D04 IV

Serious Gravity 5 1 instance 7 exposed
Issued
Nov 26, 2013
Abate by
Mar 4, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.106(d)(4)(iv): 29 CFR 1910.106(d)(4)(iv): Ventilation. Every inside storage room shall be provided with either a gravity or a mechanical exhaust ventilation system. Such system was not designed to provide for a complete change of air within the room at least six times per hour:   (a) Hazardous Material Storage and Mixing Room; The inside flammable storage room was not provided with a complete change of air at least six times per hour, the calculated change of air was 5.3.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.119 D03 I

Serious Gravity 1 1 instance 7 exposed
Issued
Nov 26, 2013
Abate by
Mar 4, 2014
Penalty
Initial $2,295 · Current $1,147 Reduced
29 CFR 1910.119(d)(3)(i): Process safety information pertaining to the equipment in the process did not include the elements specified in 29 CFR 1910.119(d)(3)(i)(A) through (H):     (a) Tank Farm; The Propellant Gas Piping P& ID did not include the addition of the purge pot which was added in 2012 to the tank farm.     (b) Manufacturing 2 and the Hazardous Material Storage Room; The Plant System P&IDs did not include the flammable liquids drainage system designated for overflow from the mixing and flammable storage room.
Recent events (2)
  • — I (S) $1147
  • — Z (S) $2295

1910.119 F03

Serious Gravity 1 1 instance 7 exposed
Issued
Nov 26, 2013
Abate by
Jan 17, 2014
Penalty
Initial $2,295 · Current $1,147 Reduced
29 CFR 1910.119(f)(3): The employer did not annually certify that operating procedures were current and accurate:     (a) Throughout the facility; Operating procedures were not certified annually to ensure they were current and accurate.
Recent events (2)
  • — I (S) $1147
  • — Z (S) $2295

1910.119 G03

Serious Gravity 1 1 instance 7 exposed
Issued
Nov 26, 2013
Abate by
Jan 17, 2014
Penalty
Initial $2,295 · Current $1,147 Reduced
29 CFR 1910.119(g)(3): 1910.119(g)(3) Training documentation. The employer shall ascertain that each employee involved in operating a process has received and understood the training required by this paragraph. The employer shall prepare a record which contains the identity of the employee, the date of training, and the means used to verify that the employee understood the training:     (a) Throughout the facility; The employer did not determine that the Production/Maintenance Supervisor involved in maintenance and operation of the covered process understood the required training.
Recent events (2)
  • — I (S) $1147
  • — Z (S) $2295

1910.119 H02 II

Serious Gravity 1 1 instance 10 exposed
Issued
Nov 26, 2013
Abate by
Jan 17, 2014
Penalty
Initial $2,295 · Current $1,147 Reduced
29 CFR 1910.119(h)(2)(ii): 29 CFR 1910.119(h)(2)(ii):  The employer did not inform contract employees of potential fire, explosion or toxic release hazards related to working on or near a covered process:      (a) Throughout the facility; The employer did not inform contract employers such as, but not limited to, Fenwal, Energys USA, Inc., Summit Fire Protection, etc. on the potential fire, explosion, or toxic release hazards related to the covered process.
Recent events (2)
  • — I (S) $1147
  • — Z (S) $2295

1910.119 H02 III

Serious Gravity 1 1 instance 10 exposed
Issued
Nov 26, 2013
Abate by
Jan 17, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.119(h)(2)(iii): The employer did not explain the applicable provisions of the emergency action plan to contract employees who work on or adjacent to a covered process:     (a) Throughout the facility;  The employer did not explain the applicable provisions of the emergency action plan to contract employers such as, but not limited to, Fenwal, Energys USA, Inc., Summit Fire Protection, etc.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.119 H02 V

Serious Gravity 1 1 instance 7 exposed
Issued
Nov 26, 2013
Abate by
Feb 10, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.119(h)(2)(v): The employer did not periodically evaluate the performance of contract employers to ensure they were fulfilling their obligations as specified in 29 CFR 1910.119(h)(3):   (a) Throughout the facility; The employer did not periodically evaluate the performance of contract employers in fulfilling their obligations including, but not limited, to Fenwal, Energys USA, Summit Fire Protection, NEI Northern Electricians, KNG Mechanical, etc.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.119 H02 VI

Serious Gravity 1 1 instance 10 exposed
Issued
Nov 26, 2013
Abate by
Dec 5, 2013
Penalty
Initial $0 · Current $0
29 CFR 1910.119(h)(2)(vi): The employer did not maintain a contract employee injury and illness log related to the contractor's work in process areas:   (a) Throughout the facility; The employer did not maintain a separate contractor employee injury and illness log related to contract work in process areas.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.119 J04 I

Serious Gravity 5 1 instance 7 exposed
Issued
Nov 26, 2013
Abate by
Mar 4, 2014
Penalty
Initial $3,060 · Current $1,530 Reduced
29 CFR 1910.119(j)(4)(i): The employer did not perform inspection and tests on process equipment:      (a) Gas House, EX Fill Room, Conveyor System; The employer did not perform the yearly calibration tests on the Drager-IR EX sensors as required by the manufacturer and their Mechanical Integrity Inspection and Maintenance Schedule. There were several sensors within the gas house, the EX Fill Room, and the gas house conveyor system.
Recent events (2)
  • — I (S) $1530
  • — Z (S) $3060

1910.119 J02

Serious Gravity 5 1 instance 7 exposed
Issued
Nov 26, 2013
Abate by
Jan 17, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.119(j)(2): The employer did not establish written procedures to maintain the on-going integrity of process equipment:    (a) Gas House, EX Fill Room, Conveyor System; The employer did not establish written procedures to ensure the Drager- IR EX sensors were tested and maintained in accordance with manufacturer's recommendations.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.119 O04

Serious Gravity 5 1 instance 7 exposed
Issued
Nov 26, 2013
Abate by
Jan 17, 2014
Penalty
Initial $3,060 · Current $1,530 Reduced
29 CFR 1910.119(o)(4): The employer did not promptly determine and document an appropriate response to each of the findings of the compliance audit, and document that deficiencies have been corrected:     (a) Throughout the facility; The employer failed to develop a system to track any identified deficiencies noted during the process safety compliance audit. There were 16 items identified in the 2013 audit with no method to track those items to completion.
Recent events (2)
  • — I (S) $1530
  • — Z (S) $3060

View Cortec Corporation's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339246340.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.