Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: JIN CHENG CONSTRUCTION CORPORATION

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of JIN CHENG CONSTRUCTION CORPORATION in NEW 4 BEDROOM, 3 BATHROOM, 2 CAR GARAGE RESIDENCE LALO STREET, BARRIGADA, GU 96921 (NAICS 236117). OSHA activity number 339482671.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch JIN Cheng Construction Corporation — free Get an email when a new federal OSHA severe-injury report for JIN Cheng Construction Corporation is published. One employer, no account, unsubscribe in one click.
Site address
NEW 4 BEDROOM, 3 BATHROOM, 2 CAR GARAGE RESIDENCE LALO STREET
City
BARRIGADA
State
GU
ZIP
96921
Mailing
PO BOX 315353, TAMUNING, GU 96931
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236117
Employees
4
Ownership type
A

6 citations on file for this inspection.

1926.20 B02

Other-than-serious 1 instance 1 exposed
Issued
Jan 29, 2014
Abate by
Feb 6, 2014
Penalty
Initial $1,020 · Current $0 Reduced
29 CFR 1926.20(b)(2): The employer failed to initiate and maintain programs that provided for frequent and regular inspections of the job sites, materials, and equipment were made by competent persons designated by the employer:     At the project on or about November 14, 2013, and at times prior thereto, inspections were not completed to ensure compliance with OSHA regulations or the person that completed the inspections was not competent as there were no fire extinguishers, no toilets, poor housekeeping and no first aid kits onsite.
Recent events (2)
  • — I (O) $0
  • — Z (S) $1020

1926.25 A

Serious Gravity 1 1 instance 1 exposed
Issued
Jan 29, 2014
Abate by
Feb 6, 2014
Penalty
Initial $1,020 · Current $1,020
29 CFR 1926.25(a): During the course of construction, alteration, or repairs, form and scrap lumber with protruding nails, and all other debris, were not kept cleared from work areas, passageways, and stairs, in and around buildings or other structures:   In the garage and front bedroom on or about November 14, 2013, conduit, scrap drywall, lumber, empty paper bags, rolled up extension cords and tarps were not kept clear of doorways and passageways.
Recent events (2)
  • — I (S) $1020
  • — Z (S) $1020

1926.50 C

Serious Gravity 1 1 instance 1 exposed
Issued
Jan 29, 2014
Abate by
Feb 6, 2014
Penalty
Initial $1,020 · Current $1,020
29 CFR 1926.50(c): In the absence of an infirmary, clinic, hospital, or physician, that was reasonably accessible in terms of time and distance to the worksite, which was available for the treatment of injured employees, a person who has a valid certificate in first-aid training from the U.S. Bureau of Mines, the American Red Cross, or equivalent training that can be verified by documentary evidence, was not be available at the worksite to render first aid:      At the project on or about November 14, 2013, and at times prior thereto, no one had first aid training and the nearest medical facility was more than four minutes away.  Employees used power saws at the project.
Recent events (2)
  • — I (S) $1020
  • — Z (S) $1020

1926.50 D01

Serious Gravity 1 1 instance 1 exposed
Issued
Jan 29, 2014
Abate by
Feb 6, 2014
Penalty
Initial $1,020 · Current $0 Reduced
29 CFR 1926.50(d)(1): First aid supplies were not easily accessible when required:    At the project on or about November 14, 2013, and at times prior thereto, there were no first aid supplies onsite and the nearest medical facility was more than four minutes away.  Employees used power saws at the project.
Recent events (2)
  • — I (S) $0
  • — Z (S) $1020

1926.51 C01

Other-than-serious 1 instance 1 exposed
Issued
Jan 29, 2014
Abate by
Feb 6, 2014
Penalty
Initial $1,020 · Current $0 Reduced
29 CFR 1926.51(c)(1): Toilets were not provided for employees:     At the project on or about November 14, 2013, and at times prior thereto, there were no toilets onsite.  Employees did not travel from site to site during the day.  They stayed onsite for the duration of the work shift.  Employees said they were not allowed to use the toilet at the house next door.
Recent events (2)
  • — I (O) $0
  • — Z (S) $1020

1926.150 C01 I

Serious Gravity 1 1 instance 1 exposed
Issued
Jan 29, 2014
Abate by
Feb 6, 2014
Penalty
Initial $1,020 · Current $1,020
29 CFR 1926.150(c)(1)(i): A fire extinguisher, rated not less than 2A, was not provided for each 3,000 square feet of the protected building area, or major fraction thereof:   At the project on or about November 14, 2013, and at times prior thereto, there was no fire extinguishers onsite.  The structure under construction contained about 2538 feet.  Onsite, there were pieces of lumber, empty paper bags that had contained cement, and cloth tarps.  Potential ignition sources included power saws, electrical equipment, smoking, and vehicles.  There were no alternate means to fight fires onsite, such as, 55 gallon drums with water and pails or hoses connected to water sources.
Recent events (2)
  • — I (S) $1020
  • — Z (S) $1020

View JIN Cheng Construction Corporation's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339482671.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.