OSHA Inspection: KISKA CONSTRUCTION, INC.

Complaint inspection · Health discipline

On , OSHA opened a complaint health inspection of KISKA CONSTRUCTION, INC. in NEWBURGH-BEACON BRIDGE, NEWBURGH, NY 12550 (NAICS 237310). OSHA activity number 339772766.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Kiska Construction, INC. — free Get an email when a new federal OSHA severe-injury report for Kiska Construction, INC. is published. One employer, no account, unsubscribe in one click.
Site address
NEWBURGH-BEACON BRIDGE
City
NEWBURGH
State
NY
ZIP
12550
Mailing
1034 44TH DR 2ND FLOOR, LONG ISLAND CITY, NY 11101
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
237310
Employees
40
Ownership type
A

8 citations on file for this inspection.

1926.55 A

Serious Gravity 10 1 instance 6 exposed
Issued
Oct 28, 2014
Abate by
Oct 3, 2015
Penalty
Initial $4,900 · Current $2,500 Reduced
29 CFR 1926.55(a): Employer did not avoid exposure of employees to inhalation, ingestion, skin absorption, or contact with any material or substance at a concentration above those specified in the "Threshold Limit Values of Airborne Contaminants for 1970" of the American Conference of Governmental Industrial Hygienists:     a). On or about 5/14/14, on the Beacon Bridge, for employees conducting a form of MIG welding with a flux cord were exposed to Zinc Oxide Fume at  a time weighted average of 39.61 mg/m3 which is 7.9 times the permissible exposure limit of 5 mg/m3. The time weighted average was calculated based on a sampling period of 144 minutes. Zero exposure was assumed for the unsampled time period.    b). On or about 5/14/14, on the Beacon Bridge, for employees conducting a form of MIG welding with a flux cord were exposed to Zinc Oxide Fume at a time weighted average of 8.139 mg/m3 which is 1.6 times the permissible exposure limit of 5 mg/m3. The time weighted average was calculated based on a sampling period of 370 minutes. Zero exposure was assumed for the unsampled time period.
Recent events (3)
  • — J (S) $2500
  • — C (S) $4900
  • — Z (S) $4900

1926.55 B

Serious Gravity 10 1 instance 6 exposed
Issued
Oct 28, 2014
Abate by
Oct 3, 2015
Penalty
Initial $0 · Current $0
29 CFR 1926.55(b): Feasible administrative or engineering controls were not implemented to reduce employee exposure(s):    a). On or about 5/14/14, on the Beacon Bridge, for employees conducting a form of MIG welding with a flux cord were exposed to Zinc Oxide Fume at  a time weighted average of 39.61 mg/m3 which is 7.9 times the permissible exposure limit of 5 mg/m3. The time weighted average was calculated based on a sampling period of 144 minutes. Zero exposure was assumed for the unsampled time period.    b). On or about 5/14/14, on the Beacon Bridge, for employees conducting a form of MIG welding with a flux cord were exposed to Zinc Oxide Fume at a time weighted average of 8.139 mg/m3 which is 1.6 times the permissible exposure limit of 5 mg/m3. The time weighted average was calculated based on a sampling period of 370 minutes. Zero exposure was assumed for the unsampled time period.
Recent events (3)
  • — J (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.134 C01

Serious Gravity 10 1 instance 6 exposed
Issued
Oct 28, 2014
Abate by
Oct 3, 2015
Penalty
Initial $4,900 · Current $2,500 Reduced
29 CFR 1910.134(c)(1): In any workplace where respirators are necessary to protect the health of the employee or whenever respirators are required by the employer, the employer did not establish and implement a written respiratory protection program with worksite-specific procedures:    a). On or about 5/14/14, on the Beacon Bridge, for welders required to don a 3M 1/2 mask respirator while conducting a form of MIG welding with a flux cord.  Employees were exposed to Zinc Oxide Fume at  a time weighted average of 39.61 mg/m3 which is 7.9 times the permissible exposure limit of 5 mg/m3. The employer did not implement a respiratory protection program to include a written program, fit test, medical evaluations, and training.
Recent events (3)
  • — J (S) $2500
  • — C (S) $4900
  • — Z (S) $4900

1910.134 E01

Deleted Serious Gravity 10 1 instance 6 exposed
Issued
Oct 28, 2014
Abate by
Nov 20, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.134(e)(1): The employer did not provide a medical evaluation to determine the employee's ability to use a respirator, before the employee is fit tested or required to use the respirator in the workplace:  a). On or about 5/14/14, on the Beacon Bridge, for welders required to don a 3M 1/2 mask respirator while conducting a form of MIG welding with a flux cord.  Employees were exposed to Zinc Oxide Fume at  a time weighted average of 39.61 mg/m3 which is 7.9 times the permissible exposure limit of 5 mg/m3. The employer did not implement a respiratory protection program to include medical evaluations.
Recent events (3)
  • — J (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.134 F01

Deleted Serious Gravity 10 1 instance 6 exposed
Issued
Oct 28, 2014
Abate by
Nov 20, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.134(f)(1): The employer did not ensure that employees using a tight-fitting facepiece respirator pass an appropriate qualitative fit test (QLFT) or quantitative fit test (QNFT) as stated in this paragraph:  a). On or about 5/14/14, on the Beacon Bridge, for welders required to don a 3M 1/2 mask respirator while conducting a form of MIG welding with a flux cord.  Employees were exposed to Zinc Oxide Fume at  a time weighted average of 39.61 mg/m3 which is 7.9 times the permissible exposure limit of 5 mg/m3. The employer did not implement a respiratory protection program to include fit tests.
Recent events (3)
  • — J (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.134 K01

Deleted Serious Gravity 10 1 instance 6 exposed
Issued
Oct 28, 2014
Abate by
Nov 20, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.134(k)(1): 29 CFR 1910.134(k)(1): The employer did not provide effective training that covered the required elements in 1910.134(k)(1)(i) through 1910.134(k)(1)(vii):  a). On or about 5/14/14, on the Beacon Bridge, for welders required to don a 3M 1/2 mask respirator while conducting a form of MIG welding with a flux cord.  Employees were exposed to Zinc Oxide Fume at  a time weighted average of 39.61 mg/m3 which is 7.9 times the permissible exposure limit of 5 mg/m3. The employer did not implement a respiratory protection program to include training.
Recent events (3)
  • — J (S) $0
  • — C (S) $0
  • — Z (S) $0

1926.353 A02

Deleted Serious Gravity 10 1 instance 6 exposed
Issued
Oct 28, 2014
Abate by
Nov 25, 2014
Penalty
Initial $4,900 · Current $0 Reduced
29 CFR 1926.353(a)(2): General mechanical ventilation was not of sufficient capacity and was not so arranged as to produce the number of air changes necessary to maintain welding fumes and smoke within safe limits, as defined in Subpart D of this part:  a). On or about 5/14/14, on the Beacon Bridge, for employees conducting a form of MIG welding with a flux cord. The welding wire contained substances including, but not limited to, Barium and Manganese. The employer conducted sampling prior to the inspection with results that indicated that employees were over exposed to Barium (exposure ranged from 1.2 mg/m3-4.5 mg/m3) and Zinc Oxide (5.6 mg/m3-82 mg/m3). The CSHO conducted sampling while the employer had implemented industrial fans as a means of ventilation. Sampling results indicated that employees were over exposed to Zinc Oxide Fume at 39.61 mg/m3 at an 8 hour Time Weighted Average and 8.139 mg/m3 at an 8 hour Time Weighted Average. Zinc Oxide Fume has a Permissible Exposure Limit of 5mg/m3 at an 8 hour Time Weighted Average. The employer did not provide adequate means of ventilation.
Recent events (3)
  • — J (S) $0
  • — C (S) $4900
  • — Z (S) $4900

1910.1200 H01

Other-than-serious 1 instance 6 exposed
Issued
Oct 28, 2014
Abate by
Oct 3, 2015
Penalty
Initial $4,900 · Current $5,000
29 CFR 1910.1200(h)(1): 29 CFR 1919.1200(h)(1):  Employees were not provided information and training as specified in 29 CFR 1910.1200(h)(2) and (3) on hazardous chemicals in their work area at the time of their initial assignment and whenever a new hazard was introduced into their work area:    a). On or about 5/14/14, on the Beacon Bridge, for employees conducting a form of MIG welding with a flux cord. The welding wire contained substances including, but not limited to, Barium and Manganese. The employer conducted sampling prior to the inspection with results that indicated that employees were over exposed to Barium (exposure ranged from 1.2 mg/m3-4.5 mg/m3) and Zinc Oxide (5.6 mg/m3-82 mg/m3). The CSHO conducted sampling with results that indicated that employees were over exposed to Zinc Oxide Fume at 39.61 mg/m3 at an 8 hour Time Weighted Average and 8.139 mg/m3 at an 8 hour Time Weighted Average. Zinc Oxide Fume has a Permissible Exposure Limit of 5mg/m3 at an 8 hour Time Weighted Average. The employer did not provide training on Barium, Manganese, and Zinc Oxide.
Recent events (3)
  • — J (O) $5000
  • — C (S) $4900
  • — Z (S) $4900

View Kiska Construction, INC.'s full OSHA safety record →