Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: ANA LLC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of ANA LLC in 1353 MERIDIAN PL, WASHINGTON, DC 20010 (NAICS 238130). OSHA activity number 340476167.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch ANA LLC — free Get an email when a new federal OSHA severe-injury report for ANA LLC is published. One employer, no account, unsubscribe in one click.
Establishment
ANA LLC
Site address
1353 MERIDIAN PL
City
WASHINGTON
State
DC
ZIP
20010
Mailing
4601 KEMPER STREET, ROCKVILLE, MD 20853
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238130
Employees
8
Ownership type
A

4 citations on file for this inspection.

1926.25 A

Other-than-serious 1 instance 6 exposed
Issued
Apr 13, 2015
Abate by
Apr 17, 2015
Penalty
Initial $1,200 · Current $0 Reduced
29 CFR 1926.25(a): During the course of construction, alteration, or repairs,  debris was not kept cleared from work areas, passageways, and stairs, in and around buildings or other structures:    a) Rear Ground, Back Yard of Structure -  Workers were forced to walk over scrap lumber, bricks, material, trash and other debris in order to access the work area, on or about 3/19/2015.    Abatement certification is required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (O) $0
  • — Z (S) $1200

1926.501 B13

Serious Gravity 10 1 instance 4 exposed
Issued
Apr 13, 2015
Abate by
Apr 17, 2015
Penalty
Initial $2,800 · Current $1,400 Reduced
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b):    a) Roof Top Front, Rear and Sides of Structure - Four workers  laying sheets of plywood  were not  protected from falling approximately 15' off the sides to the neighboring roof or 35' off the rear and front of the structure to the ground below, on or about 3/19/205.     Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
  • — I (S) $1400
  • — Z (S) $2800

1926.1053 B04

Other-than-serious 1 instance 6 exposed
Issued
Apr 13, 2015
Abate by
Apr 17, 2015
Penalty
Initial $1,200 · Current $0 Reduced
29 CFR 1926.1053(b)(4): Ladder(s) were used for purposes other than the purpose for which they were designed:    a) Rear, Left Side  - A 6' fiberglass step ladder was in the folded, closed position, leaned against the structure and used as a non-self supported, extension, ladder to gain access to the first level on or about 3/19/2015.    Abatement certification is required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (O) $0
  • — Z (S) $1200

1926.1053 B01

Serious Gravity 5 1 instance 6 exposed
Issued
Apr 13, 2015
Abate by
Apr 17, 2015
Penalty
Initial $2,000 · Current $1,000 Reduced
29 CFR 1926.1053(b)(1): Where (a) portable ladder(s) was/were used for access to an upper level landing surface and the ladder's length did not allow the ladder side rails to extend at least 3 feet (0.9 m) above the upper landing surface being accessed, the ladder was not secured at its top to a rigid support that will not deflect, and/or a grasping device was not provided to assist employees in mounting and dismounting the ladder.      a) Rear Center, Ground Level to 2nd Floor - Ladder used to gain access to the second level from outside, extended approximately 24" past access landing on or about 3/19/2015.     Abatement certification is required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $1000
  • — Z (S) $2000

View ANA LLC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 340476167.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.