SAVANNAH, GA —
OSHA Inspection: ALFREDO LARES OCHOA
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of ALFREDO LARES OCHOA in 318 MALL BLVD BLD B, SAVANNAH, GA 31406 (NAICS 238140). OSHA activity number 340834563.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- ALFREDO LARES OCHOA
- Site address
- 318 MALL BLVD BLD B
- City
- SAVANNAH
- State
- GA
- ZIP
- 31406
- Mailing
- 800 QUACCO RD LOT 214, SAVANNAH, GA 31419
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 6
- Ownership type
- A
Citations
6 citations on file for this inspection.
5(a)(1)
- Issued
- Dec 28, 2015
- Penalty
- Initial $2,000 · Current $1,400 Reduced
General-duty citation text
OSH ACT of 1970 Section (5)(a)(1): Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employee(s) in that employee(s) were exposed to the hazard of ejection and crush-by. a) Throughout jobsite-On or about July 27, 2015, an employee was operating a GENIE GTH-844 forklift without the use of seatbelts, exposing the employee to ejection, and others to struck-by and crushing hazards.
Recent events (2)
- — I (S) $1400
- — Z (S) $2000
1926.100 A
- Issued
- Dec 28, 2015
- Penalty
- Initial $1,600 · Current $1,120 Reduced
General-duty citation text
29 CFR 1926.100(a): Employees working in areas where there was a possible danger of head injury from impact, or falling or flying objects, or from electrical shock and burns, were not protected by protective helmets: a) Scaffold Area July 27, 2015, employees were working from scaffolding installing brick and performing other overhead work while other employees were allowed to work below and nearby without head protection, exposing employees to struck-by hazards.
Recent events (2)
- — I (S) $1120
- — Z (S) $1600
1910.178 M05 I
- Issued
- Dec 28, 2015
- Penalty
- Initial $1,700 · Current $1,190 Reduced
General-duty citation text
29 CFR 1910.178(m)(5)(i): When a powered industrial truck is left unattended, load engaging means were not fully lowered, controls were not netralized, power was not shut off, and brakes set. a) Jobsite-On or about July 27, 2015, the operator of a GENIE-844 forklift (PIT) left the forklift unattended, was more than 25 feet away, left the load engaging means in an elevated position, and the engine was not shut off, exposing employees to inadvertent movement of the forklift.
Recent events (2)
- — I (S) $1190
- — Z (S) $1700
1926.451 E01
- Issued
- Dec 28, 2015
- Penalty
- Initial $2,000 · Current $1,400 Reduced
General-duty citation text
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Crossbraces were used as a means of access. a) Jobsite-On or about July 27, 2015, employees were allowed to use cross bracing and scaffold up-rights to ascend and descend the scaffold system, exposing employees to fall hazards up to 19 feet.
Recent events (2)
- — I (S) $1400
- — Z (S) $2000
1926.451 G01 V
- Issued
- Dec 28, 2015
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.451(g)(1)(v): Each employee on a walkway located within a scaffold was not protected by a guardrail system (with a minimum 200 pound toprail capacity) installed within 9.5 inches (24.1 cm) of and along at least one side of the walkway. a) Jobsite-On or about July 27, 2015, employees using scaffold walkways to transition between tubular welded frame scaffold systems were not provided with an adequate guardrail in that a large gap was left open at the corner, exposing employees to fall hazards up to about 19 feet.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1926.451 G04 I
- Issued
- Dec 28, 2015
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.451(g)(4)(i): Guardrail systems were not installed along all open sides and ends of platforms before being released for use by employees other than erection/dismantling crews: a) Jobsite-On or about, and at times prior to July 27, 2015, the employer allowed employees to work from the 3rd tier tubular welded frame scaffolding with exposed open sides and ends. The employer failed to ensure fall protection was provided such as, but not limited to guardrails, exposing employees to fall hazards up to 19 feet.
Recent events (2)
- — I (S) $0
- — Z (S) $0
More inspections at Alfredo Lares Ochoa
View Alfredo Lares Ochoa's full OSHA safety record →
More inspections in this industry (NAICS 238140)
More inspections in GA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 340834563.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.