ARLEY, AL —
OSHA Inspection: ADDISON STEEL TRUSS, INC.
Complaint inspection · Safety discipline
At a glance
On , OSHA opened a complaint safety inspection of ADDISON STEEL TRUSS, INC. in 33884 HIGHWAY 278, ARLEY, AL 35540 (NAICS 321214). OSHA activity number 340963826.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- ADDISON STEEL TRUSS, INC.
- Site address
- 33884 HIGHWAY 278
- City
- ARLEY
- State
- AL
- ZIP
- 35540
- Mailing
- P.O. BOX 225, ADDISON, AL 35540
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 321214
- Employees
- 7
- Ownership type
- A
Citations
6 citations on file for this inspection.
1910.136 A
- Issued
- Nov 12, 2015
- Abate by
- Nov 24, 2015
- Penalty
- Initial $1,600 · Current $960 Reduced
General-duty citation text
29 CFR 1910.136(a): The employer did not ensure that each affected employee used protective footwear when working in areas where there is a danger of foot injuries due to falling or rolling objects, or objects piercing the sole: (a) On or about 10/05/2015 - Welding Area, employees working with welding trusses weighing approximately 200 pounds were not required to wear foot protection.
Recent events (2)
- — I (S) $960
- — Z (S) $1600
1910.132 D01
- Issued
- Nov 12, 2015
- Abate by
- Nov 24, 2015
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.132(d)(1): The employer did not assess the workplace to determine if hazards are present, or are likely to be present, which necessitate the use of personal protective equipment (PPE): (a) On or about 10/05/2015 - Welding Area, the employer did not assess the hazards in the welding area associated with working with welding trusses weighing approximately 200 pounds.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.212 A05
- Issued
- Nov 12, 2015
- Abate by
- Nov 24, 2015
- Penalty
- Initial $1,600 · Current $960 Reduced
General-duty citation text
29 CFR 1910.212(a)(5): Fan blade guards, where the periphery of the blades was less than seven feet above the floor or working level, had openings larger than one-half inch: (a) On or about 10/05/2015 - Welding Area, the box fan located on the floor had 4-inch openings.
Recent events (2)
- — I (S) $960
- — Z (S) $1600
1910.254 D08
- Issued
- Nov 12, 2015
- Abate by
- Nov 24, 2015
- Penalty
- Initial $2,400 · Current $1,440 Reduced
General-duty citation text
29 CFR 1910.254(d)(8): Welding cables with splices within 10 feet (3 m) of the holder were used: (a) On or about 10/05/2015 - Welding Area, Lincoln Welders, Model 525, welding cables were spliced at 2 feet from the holders.
Recent events (2)
- — I (S) $1440
- — Z (S) $2400
1910.303 G02 I
- Issued
- Nov 12, 2015
- Abate by
- Nov 24, 2015
- Penalty
- Initial $1,600 · Current $960 Reduced
General-duty citation text
29 CFR 1910.303(g)(2)(i): Live parts of electric equipment operating at 50 volts or more were not guarded against accidental contact by approved cabinets of other forms of approved enclosures, or other means listed under this provision: (a) On or about 10/05/2015 - Welding Area, a 270-volt electrical circuit breaker did not have a cover.
Recent events (2)
- — I (S) $960
- — Z (S) $1600
1910.253 B04 III
- Issued
- Nov 12, 2015
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.253(b)(4)(iii): Oxygen cylinders in storage were not separated from fuel-gas cylinders or combustible materials (especially oil or grease), a minimum distance of 20 feet (6.1 m) or by a noncombustible barrier at least 5 feet (1.5 m) high having a fire-resistance rating of at least one-half hour: (a) On or about 10/05/2015 - Welding Area, one oxygen cylinder and one acetylene cylinder were stored together.
Recent events (2)
- — I (O) $0
- — Z (O) $0
More inspections at Addison Steel Truss, INC.
View Addison Steel Truss, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 321214)
More inspections in AL
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 340963826.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.