OSHA Inspection: PCC PRINT SHOP, INC.

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of PCC PRINT SHOP, INC. in 118 ST. JOHNS ST., PENSACOLA, FL 32503 (NAICS 323117). OSHA activity number 341182202.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch PCC Print Shop, INC. — free Get an email when a new federal OSHA severe-injury report for PCC Print Shop, INC. is published. One employer, no account, unsubscribe in one click.
Site address
118 ST. JOHNS ST.
City
PENSACOLA
State
FL
ZIP
32503
Mailing
118 ST. JOHNS ST., PENSACOLA, FL 32503
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
323117
Employees
43
Ownership type
A

3 citations on file for this inspection.

1910.147 C04 I

Serious Gravity 10 1 instance 25 exposed
Issued
Apr 22, 2016
Penalty
Initial $4,900 · Current $4,900
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section:  a.  On or about January 15, 2016, at PCC Print Shop, Inc., the employer did not develop and utilize procedures for the control of potentially hazardous energy for their employees while they were required to clean, perform preventive maintenance, and make general repairs to Heidelberg Web System, Model Sunday 2000 Serial: 0R7000-2.    b.  On or about January 15, 2016, at PCC Print Shop, Inc., the employer did not develop and utilize procedures for the control of potentially hazardous energy for their employees while they were required to clean, perform preventive maintenance, and make general repairs to 8 Color sheet Fed Printing Press, Model #SM102 8P5, Serial #546-605.    c.  On or about January 15, 2016, at PCC Print Shop, Inc., the employer did not develop and utilize procedures for the control of potentially hazardous energy for their employees while they were required to clean, perform preventive maintenance, and make general repairs to 8 color Roll Press, Model #SM102 8P5-5, Serial #545-167.  d.  On or about January 15, 2016, at PCC Print Shop, Inc., the employer did not develop and utilize procedures for the control of potentially hazardous energy for their employees while they were required to clean, perform preventive maintenance, and make general repairs to Fimag Web Press, Model P2100A, Serial # 678.
Recent events (2)
  • — I (S) $4900
  • — Z (S) $4900

1910.147 C06 I

Serious Gravity 5 1 instance 11 exposed
Issued
Apr 22, 2016
Penalty
Initial $3,500 · Current $0 Reduced
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed:    a.  On or about January 15, 2016 at PCC Print Shop, Inc., the employer did not conduct periodic inspections at least annually on lockout/tagout (LOTO) procedures and requirements.  Employees were not locking out machines and did not have record of periodic inspections for the machines they operated.  Employees are exposed to crushing and amputations.
Recent events (2)
  • — I (S) $0
  • — Z (S) $3500

1910.147 C07 I

Serious Gravity 5 1 instance 25 exposed
Issued
Apr 22, 2016
Abate by
May 18, 2016
Penalty
Initial $3,500 · Current $2,500 Reduced
29 CFR 1910.147(c)(7)(i): The employer did not provide training to ensure that the purpose and function of the energy control program are understood by employees and that the knowledge and skills required for the safe application, usage, and removal of the energy controls are acquired by employees:    a. On or about January 15, 2016, at PCC Print Shop Inc. the employer did not provide training to employees servicing machines about the hazards and procedures to minimize those hazards.  Employees were exposed to crushing and amputations hazards.
Recent events (2)
  • — I (S) $2500
  • — Z (S) $3500

View PCC Print Shop, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 341182202.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.