Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: GCL, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of GCL, INC. in 685 GLENWOOD WAY, BUTLER, PA 16001 (NAICS 332312). OSHA activity number 341268647.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch GCL, INC. — free Get an email when a new federal OSHA severe-injury report for GCL, INC. is published. One employer, no account, unsubscribe in one click.
Establishment
GCL, INC.
Site address
685 GLENWOOD WAY
City
BUTLER
State
PA
ZIP
16001
Mailing
685 GLENWOOD WAY, BUTLER, PA 16001
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
332312
Employees
20
Ownership type
A

4 citations on file for this inspection.

1910.212 A03

Serious Gravity 5 2 instances 2 exposed
Issued
Apr 21, 2016
Abate by
Jun 8, 2016
Penalty
Initial $1,700 · Current $1,275 Reduced
29 CFR 1910.212(a)(3): Point of operation guard(s) were not provided:  (a) Facility, Plant Number 1, Seam Press: On or before February 22, 2016, the point of operation on the press was unguarded.     (b) Facility, Plant Number 2, Hill Acme Kling Punch Press: On or before March 17, 2016, the point of operation on the press was unguarded.
Recent events (2)
  • — I (S) $1275
  • — Z (S) $1700

1910.217 C02 I A

Serious Gravity 5 2 instances 3 exposed
Issued
Apr 21, 2016
Abate by
Jun 8, 2016
Penalty
Initial $1,700 · Current $1,275 Reduced
29 CFR 1910.217(c)(2)(i)(a): Point of operation guard(s) on mechanical power press(es) did not prevent entry of hands or fingers into the point of operation by reaching through, over, under or around the guard:  (a) Facility, Plant Number 1, Chicago Dreis & Krump Brake Press: On or before February 22, 2016, the point of operation on the press die was unguarded on both sides of the press.     (b) Facility, Plant Number 2, 600 H Cincinnati Mechanical Brake Press: On or before March 17, 2016, the point of operation on the press was unguarded in the rear of the die.
Recent events (2)
  • — I (S) $1275
  • — Z (S) $1700

1910.147 C04 I

Other-than-serious 1 instance 1 exposed
Issued
Apr 21, 2016
Abate by
Jun 8, 2016
Penalty
Initial $0 · Current $0
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section:   (a) Facility, Plant Number 1, 110 Ton Thomas Mechanical Press: On or before February 22, 2016, the employer did not create an equipment specific hazardous energy isolation procedure prior to performing a die change.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

1910.217 E01 I

Other-than-serious 4 instances 3 exposed
Issued
Apr 21, 2016
Abate by
Jun 8, 2016
Penalty
Initial $0 · Current $0
29 CFR 1910.217(e)(1)(i): A program of periodic and regular inspections of mechanical power press(es) was not established and followed to insure that all parts, auxiliary equipment and safeguards were in a safe operating condition and adjustment:  (a) Facility, Plant Number 1, 110 Ton Thomas Mechanical Press: On or before February 22, 2016, the employer did not conduct a documented inspection of the press.   (b) Facility, Plant Number 1, Chicago Dries and Krump Mechanical Brake Press: On or before February 22, 2016, the employer did not conduct a documented inspection of the press.  (c) Facility, Plant Number 2, 600 H Cincinnati Brake Press: On or before March 17, 2016, the employer did not conduct a documented inspection of the press.  (d) Facility, Plant Number 2, Long and Alstatter Shear: On or before March 17, 2016, the employer did not conduct a documented inspection of the shear.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

View GCL, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 341268647.