OAK PARK, IL —
OSHA Inspection: ALL STAR ROOFING, INC.
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of ALL STAR ROOFING, INC. in 843 N. EAST AVE., OAK PARK, IL 60302 (NAICS 238160). OSHA activity number 342170941.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- ALL STAR ROOFING, INC.
- Site address
- 843 N. EAST AVE.
- City
- OAK PARK
- State
- IL
- ZIP
- 60302
- Mailing
- 3106 OAK PARK AVE., BERWYN, IL 60402
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238160
- Employees
- 6
- Ownership type
- A
Citations
14 citations on file for this inspection.
1903.19 C01
- Issued
- May 22, 2017
- Abate by
- Jun 23, 2017
- Penalty
- Initial $305 · Current $200 Reduced
General-duty citation text
29 CFR 1903.19(c)(1): The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated: All Star Roofing, Inc., failed to certify to OSHA within 10 calendar days after the abatement date that each of the following cited violations had been corrected: Citation Number Item Number Abatement Date 01 01 04/03/2017 01 02 04/03/2017 01 03 04/03/2017 01 04 04/03/2017 01 05a 04/28/2017 01 05b 04/282017 01 06a 04/03/2017 01 06b 04/03/2017 01 07 04/03/2017 02 01 04/03/2017 02 02 04/03/2017 03 01 04/03/2017 03 02 04/03/2017 In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
- — I (O) $200
- — Z (O) $305
1926.100 A
- Issued
- Mar 28, 2017
- Abate by
- Apr 3, 2017
- Penalty
- Initial $2,390 · Current $2,390
General-duty citation text
29 CFR 1926.100(a): Employees were not protected by protective helmets while working in areas where there was a possible danger of head injury from impact, or from falling or flying objects, or from electrical shock and burns: a) On March 10, 2017, employees were not wearing protective helmets where there was a possible danger of head injury. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (S) $2390
1926.451 B05 II
- Issued
- Mar 28, 2017
- Abate by
- Apr 3, 2017
- Penalty
- Initial $2,988 · Current $2,988
General-duty citation text
29 CFR 1926.451(b)(5)(ii): The end of a platform greater than 10 feet in length extended over its support more than 18 inches and the platform was not designed and installed so that the cantilevered portion of the platform is able to support employees without tipping, or has guardrails which block employee access to the cantilevered end: a) On March 10, 2017, employees were working from a ladder jack scaffold platform which was extended approximately four feet over the end supports. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (S) $2988
1926.451 F06
- Issued
- Mar 28, 2017
- Abate by
- Apr 3, 2017
- Penalty
- Initial $4,183 · Current $4,183
General-duty citation text
29 CFR 1926.451(f)(6): Scaffolds were erected, used, dismantled, altered, or moved such that they, or any conductive material handled on them, could have come closer than the minimum distances established for specific voltages as set forth in the table in subparagraph (f)(6). a) On or about March 10, 2017, employer permitted employees to erect and use a ladder jack scaffold platform in close proximity to energized power lines having a voltage of 120/240 volts. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
- — Z (S) $4183
1926.451 G01 I
- Issued
- Mar 28, 2017
- Abate by
- Apr 3, 2017
- Penalty
- Initial $4,183 · Current $4,183
General-duty citation text
29 CFR 1926.451(g)(1)(i): Each employee on a boatswains' chair, catenary scaffold, float scaffold, needle beam scaffold, or ladder jack scaffold was not protected by a personal fall arrest system: a) On March 10, 2017, employees were exposed to the hazard of falling while working from a ladder jack scaffold platform elevated approximately 19 feet above the ground. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
- — Z (S) $4183
1926.454 A
- Issued
- Mar 28, 2017
- Abate by
- Apr 28, 2017
- Penalty
- Initial $2,988 · Current $2,988
General-duty citation text
29 CFR 1926.454(a): The employer did not have each employee who performed work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards: a) On or about March 10, 2017, employer did not provide training to each employee in order to recognize hazards associated with working from ladder jack scaffolding and to understand procedures to control or minimize those hazards. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (S) $2988
1926.503 A01
- Issued
- Mar 28, 2017
- Abate by
- Apr 28, 2017
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.503(a)(1): The employer did not provide a training program for each employee who might be exposed to fall hazards: a) On or about March 10, 2017, employer did not provide training to each employee in order to recognize hazards associated with working at an elevation and to understand procedures to control or minimize those hazards. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (S) $0
1926.502 D01
- Issued
- Mar 28, 2017
- Abate by
- Apr 3, 2017
- Penalty
- Initial $2,988 · Current $2,988
General-duty citation text
29 CFR 1926.502(d)(1): Personal fall arrest system connectors were not drop forged, pressed or formed steel, or made of equivalent materials: a) On March 10, 2017, employees were exposed to fall hazards while using personal fall arrest system components containing connectors that were not drop forged, pressed or formed steel. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (S) $2988
1926.502 D15
- Issued
- Mar 28, 2017
- Abate by
- Apr 3, 2017
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.502(d)(15): Anchorage used for attachment for personal fall arrest equipment was not capable of supporting at least 5,000 pounds (22.2 kN) per employee attached nor was it designed, installed and used as follows: As part of a complete personal fall arrest system which maintains a safety factor of at least two; and under the supervision of a qualified person: a) On March 10, 2017, the employer did not ensure that the anchorage used by employees as an attachment point for personal fall arrest system was capable of supporting at least 5,000 pound per employee attached to it. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (S) $0
1926.1053 B22
- Issued
- Mar 28, 2017
- Abate by
- Apr 3, 2017
- Penalty
- Initial $2,390 · Current $2,390
General-duty citation text
29 CFR 1926.1053(b)(22): Employees using ladders were carrying objects or loads that could cause the employee to lose balance and fall: a) On March 10, 2017, employees were exposed to fall hazards while carrying building material up the ladder. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (S) $2390
1926.102 A01
- Issued
- Mar 28, 2017
- Abate by
- Apr 3, 2017
- Penalty
- Initial $4,780 · Current $4,780
General-duty citation text
29 CFR 1926.102(a)(1): Employees were not provided with eye and face protection equipment when machines or operations present potential eye or face injury from physical, chemical, or radiation agents: a) On March 10, 2017, employees were exposed to eye injury while operating a power tools without eye protection during carpentry work. All Star Roofing, Inc., was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1926.102(a)(1), which was contained in OSHA inspection number 804101, citation number 1, item number 1 and was affirmed as a final order on January 31, 2013, with respect to a workplace located at 1357 West Taylor St., Chicago, IL 60607. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (R) $4780
1926.501 B13
- Issued
- Mar 28, 2017
- Abate by
- Apr 3, 2017
- Penalty
- Initial $14,939 · Current $14,939
General-duty citation text
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b): a) On March 10, 2017, employees engaged in carpentry work were not protected from fall hazards while working at an elevation of approximately 12 feet above the ground. All Star Roofing, Inc., was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1926.501(b)(1), which was contained in OSHA inspection number 804101, citation number 2, item number 1 and was affirmed as a final order on January 31, 2013, with respect to a workplace located at 1357 West Taylor St., Chicago, IL 60607. All Star Roofing, Inc., was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1926.501(b)(10), which was contained in OSHA inspection number 625258, citation number 1, item number 1 and was affirmed as a final order on October 23, 2012, with respect to a workplace located at 4311 S. Harlem Ave., Stickney, IL 60402. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
- — Z (R) $14939
1926.403 B02
- Issued
- Mar 28, 2017
- Abate by
- Apr 3, 2017
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.403(b)(2): Listed, labeled, or certified equipment was not installed and used in accordance with instructions included in the listing, labeling, or certification: a) On March 10, 2017, employees engaged in carpentry work were using a relocatable power tap in an outdoor setting to power tools onsite. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (O) $0
1926.404 F06
- Issued
- Mar 28, 2017
- Abate by
- Apr 3, 2017
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.404(f)(6): The path to ground from circuits, equipment, or enclosures was not permanent and continuous: a) On March 10, 2017, extension cords, used by employees during carpentry work, did not have permanent and continuous path to ground. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (O) $0
More inspections at ALL Star Roofing, INC.
View ALL Star Roofing, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 238160)
More inspections in IL
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 342170941.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.