PALATINE, IL —
OSHA Inspection: RAUL'S REMODELING INC.
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of RAUL'S REMODELING INC. in 1829-1837 GOODWIN DRIVE, PALATINE, IL 60067 (NAICS 238160). OSHA activity number 342512365.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- RAUL'S REMODELING INC.
- Site address
- 1829-1837 GOODWIN DRIVE
- City
- PALATINE
- State
- IL
- ZIP
- 60067
- Mailing
- 451 PEBBLE COURT, SCHAUMBURG, IL 60193
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238160
- Employees
- 7
- Ownership type
- A
Citations
5 citations on file for this inspection.
1903.19 C01
- Issued
- Oct 18, 2017
- Abate by
- Nov 21, 2017
- Penalty
- Initial $305 · Current $305
General-duty citation text
29 CFR 1903.19(c)(1): The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated: Raul's Remodeling Inc., failed to certify to OSHA within 10 calendar days after the abatement date that each of the following cited violations had been corrected: Citation Number Item Number Abatement Date 01 01 08/17/2017 01 02 08/17/2017 01 03 08/17/2017 02 01 09/07/2017 In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF THE CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (O) $305
1926.100 A
- Issued
- Aug 11, 2017
- Abate by
- Aug 17, 2017
- Penalty
- Initial $2,173 · Current $2,173
General-duty citation text
29 CFR 1926.100(a): Employees were not protected by protective helmets while working in areas where there was a possible danger of head injury from impact, or from falling or flying objects, or from electrical shock and burns: a) On or about August 1, 2017, employees were exposed to head injury while working without protective helmets in areas below roofing work activities. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (S) $2173
1926.252 A
- Issued
- Aug 11, 2017
- Abate by
- Aug 17, 2017
- Penalty
- Initial $2,173 · Current $2,173
General-duty citation text
29 CFR 1926.252(a): An enclosed chute of wood, or equivalent material, was not used where materials were dropped more than 20 feet to points lying outside the exterior walls of the building(s): a) On or about August 1, 2017, employees were exposed to the hazard of being struck by material and debris that was being thrown from the roof deck at an elevation of approximately 3 stories (30 feet). In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (S) $2173
1926.501 B13
- Issued
- Aug 11, 2017
- Abate by
- Aug 17, 2017
- Penalty
- Initial $3,803 · Current $3,803
General-duty citation text
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501(b): a) On or about August 1, 2017, employees were exposed to the hazard of falling while performing roofing work without fall protection from a pitched roof surface of a three story building. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
- — Z (S) $3803
1926.503 B01
- Issued
- Aug 11, 2017
- Abate by
- Sep 7, 2017
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.503(b)(1): The employer did not verify fall protection training by preparing a written certification record: a) On or about August 1, 2017, the employer did not prepare written certification records related to employee fall protection training. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- — Z (O) $0
More inspections at Raul'S Remodeling INC.
View Raul'S Remodeling INC.'s full OSHA safety record →
More inspections in this industry (NAICS 238160)
More inspections in IL
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 342512365.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.