OSHA Inspection: RVM CONSTRUCTION, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of RVM CONSTRUCTION, INC. in 200 WEST MAIN STREET, NEW ALBANY, OH 43054 (NAICS 238140). OSHA activity number 342615762.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch RVM Construction, INC. — free Get an email when a new federal OSHA severe-injury report for RVM Construction, INC. is published. One employer, no account, unsubscribe in one click.
Site address
200 WEST MAIN STREET
City
NEW ALBANY
State
OH
ZIP
43054
Mailing
284 CEDAR HILL ROAD SUITE 200, LANCASTER, OH 43130
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
12
Ownership type
A

3 citations on file for this inspection.

1926.451 E09 III

Serious Gravity 10 1 instance 2 exposed
Issued
Oct 18, 2017
Abate by
Oct 30, 2017
Penalty
Initial $9,760 · Current $7,808 Reduced
29 CFR 1926.451(e)(9)(iii): When erecting or dismantling tubular welded frame scaffolds, (end) frames, with horizontal members that are parallel, level and are not more than 22 inches apart vertically may be used as climbing devices for access, provided they are erected in a manner that creates a usable ladder and provides good hand hold and foot space.  a. On or about September 6, 2017, located at the site in New Albany, Ohio, employees were dismantling a fabricated frame scaffold while on the fifth buck and used the frame of the scaffolding to ascend and descend the scaffolding exposing the employees to a maximum fall hazard of approximately 32 feet.
Recent events (2)
  • — I (S) $7808
  • — Z (S) $9760

1926.451 E09 IV

Serious Gravity 5 1 instance 2 exposed
Issued
Oct 18, 2017
Abate by
Oct 30, 2017
Penalty
Initial $0 · Current $0
29 CFR 1926.451(e)(9)(iv): Cross braces on tubular welded frame scaffolds shall not be used as a means of access or egress.  a. On or about September 6, 2017, located at the site in New Albany, Ohio, employees were dismantling a fabricated frame scaffold while on the fifth buck and used the crossbracing to climb down to the fourth buck, thereby exposing the employees to a fall hazard of approximately 6 feet, 7 inches.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.451 G02

Serious Gravity 10 2 instances 4 exposed
Issued
Oct 18, 2017
Abate by
Nov 7, 2017
Penalty
Initial $9,760 · Current $0 Reduced
29 CFR 1926.451(g)(2): Effective September 2, 1997, the employer shall have a competent person determine the feasibility and safety of providing fall protection for employees erecting or dismantling supported scaffolds. Employers are required to provide fall protection for employees erecting or dismantling supported scaffolds where the installation and use of such protection is feasible and does not create a greater hazard.    a. On or about September 6, 2017, located in New Albany, Ohio, employees were dismantling fabricated frame scaffolding on the top of the fourth buck. Employees were required to access a ladder on the top of the 3rd buck while there were no guardrails between frames on the eastern side to protect the employees from a fall, thereby exposing the employees to a fall hazard of approximately 25 feet.     b. On or about September 6, 2017, located in New Albany, Ohio, employees were dismantling fabricated frame scaffolding on the top of the fourth buck. Employees were required to access a ladder on the top of the 3rd buck while there were no midrails across three openings between frames to protect the employees from a fall, thereby exposing the employees to a fall hazard of approximately 25 feet.
Recent events (2)
  • — I (S) $0
  • — Z (S) $9760

View RVM Construction, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 342615762.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.