Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: LAROSE INDUSTRIES, LLC

Complaint inspection · Safety discipline

On , OSHA opened a complaint safety inspection of LAROSE INDUSTRIES, LLC in 250 EAST INDUSTRIAL PKWY, FAYETTE, OH 43521 (NAICS 326199). OSHA activity number 343199576.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Larose Industries, LLC — free Get an email when a new federal OSHA severe-injury report for Larose Industries, LLC is published. One employer, no account, unsubscribe in one click.
Site address
250 EAST INDUSTRIAL PKWY
City
FAYETTE
State
OH
ZIP
43521
Mailing
250 EAST INDUSTRIAL PKWY, FAYETTE, OH 43521
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
326199
Employees
58
Ownership type
A

10 citations on file for this inspection.

1910.147 C06 I

Serious Gravity 5 1 instance 3 exposed
Issued
Sep 24, 2018
Abate by
Oct 11, 2018
Penalty
Initial $10,163 · Current $10,163
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed:   a.)    On or about May 31, 2018, the employer did not ensure periodic inspections were completed for employees who performed lock out tag out activities. Employees were exposed to crush-by hazards while performing cleaning activities on equipment, such as but not limited to the P8 Paint Strip machine.
Recent events (1)
  • — Z (S) $10163

1910.212 A03 II

Serious Gravity 5 1 instance 58 exposed
Issued
Sep 24, 2018
Abate by
Oct 18, 2018
Penalty
Initial $10,163 · Current $10,163
29 CFR 1910.212(a)(3)(ii): Point(s) of operation of machinery were not guarded to prevent employee(s) from having any part of their body in the danger zone(s) during operating cycle(s):   a.)    On May 31, 2018, the employer did not ensure employees were protected from pinch points while operating the P8 Paint Strip machine. Employees are required to operate the machine and are exposed to crush hazards in that the smasher bar is not guarded.
Recent events (1)
  • — Z (S) $10163

1910.303 B07 I

Serious Gravity 1 1 instance 3 exposed
Issued
Sep 24, 2018
Abate by
Oct 3, 2018
Penalty
Initial $6,097 · Current $6,097
29 CFR 1910.303(b)(7)(i): Unused openings in boxes, raceways, auxiliary gutters, cabinets, equipment cases, or housings were not effectively closed to afford protection substantially equivalent to the wall of the equipment:   a. On or about May 31, 2018, the employer did not assure that an unused opening located on the electrical outlet for the P3 paint line labeler was effectively closed.  The outlet box, located under the P3 paint line conveyor, exposed employees to a 110 volt electrical hazard.
Recent events (1)
  • — Z (S) $6097

1910.332 B01

Serious Gravity 1 1 instance 1 exposed
Issued
Sep 24, 2018
Abate by
Oct 18, 2018
Penalty
Initial $6,097 · Current $6,097
29 CFR 1910.332(b)(1): Employees were not trained in and familiar with the safety-related work practices required by 1910.331 through 1910.335 that pertained to their respective job assignments:  a.)    On or about May 31, 2018, the employer did not ensure employees were familiar with electrical safety related work practices before changing a fuse on the 110V P3 Paint Line conveyor. Employees were required to perform electrical work near 110V and did not recognize hazards associated with Electrical Safety Related Work Practices.
Recent events (1)
  • — Z (S) $6097

1910.333 A

Serious Gravity 1 1 instance 1 exposed
Issued
Sep 24, 2018
Abate by
Oct 18, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.333(a): Safety-related work practices were not employed to prevent electric shock or other injuries resulting from either direct or indirect electrical contacts, when work was performed near or on equipment or circuits which were or could be energized:   a.)    On or about May 31, 2018, the employer did not ensure employees utilized electrical safety related work practices while changing a fuse on the 110V P3 Paint Line conveyor and were exposed to electric shock and arc flash hazards.
Recent events (1)
  • — Z (S) $0

1910.333 B02 I

Serious Gravity 1 1 instance 1 exposed
Issued
Sep 24, 2018
Abate by
Oct 18, 2018
Penalty
Initial $6,097 · Current $6,097
29 CFR 1910.333(b)(2)(i): The employer did not maintain a written copy of the procedures outlined in paragraph (b)(2) of 29 CFR 1910.333 and did not make it available for inspection by the Assistant Secretary of Labor and his or her authorized representatives:   a.)    On or about May 31, 2018, the employer did not ensure procedures for deenergizing electrical circuits were in place prior to employees changing a fuse on the 110V P3 Paint Line conveyor and were exposed to electric shock and arc flash hazards.
Recent events (1)
  • — Z (S) $6097

1910.333 B02 III A

Serious Gravity 1 1 instance 1 exposed
Issued
Sep 24, 2018
Abate by
Oct 11, 2018
Penalty
Initial $6,097 · Current $6,097
29 CFR 1910.333(b)(2)(iii)(A): A lock and a tag were not placed on each disconnecting means used to deenergize circuits and equipment on which work was to be performed:   a.)    On or about May 31, 2018, the employer did not ensure a lock was placed on the breaker panel while replacing a 15amp fuse on the P3 paint line conveyor exposing them to electrical hazards from unexpected start up of the equipment.
Recent events (1)
  • — Z (S) $6097

1910.335 A01 I

Serious Gravity 1 1 instance 1 exposed
Issued
Sep 24, 2018
Abate by
Oct 18, 2018
Penalty
Initial $6,097 · Current $6,097
29 CFR 1910.335(a)(1)(i): Employees working in areas where there were potential electrical hazards were not provided with electrical protective equipment that was appropriate for the specific parts of the body that needed to be protected and for the work being performed:   a.)    On or about May 31, 2018, the employer did not ensure maintenance employees were protected while pulling a 15 amp 32V fuse on the P3 paint line conveyor. Employees were required to replace the fuse and did not wear the required hand and body protection while verifying zero energy, exposing them to electrical shock and arc flash hazards.
Recent events (1)
  • — Z (S) $6097

1910.147 C07 I

Repeat Gravity 5 1 instance 5 exposed
Issued
Sep 24, 2018
Abate by
Oct 18, 2018
Penalty
Initial $50,815 · Current $50,815
29 CFR 1910.147(c)(7)(i): The employer did not provide adequate training to ensure that the purpose and function of the energy control program was understood by employees:   a.)    On or about May 31, 2018, the employer did not ensure that employees were adequately trained in the lockout procedures for the paint machines, including but not limited to the P8 strip machine.  Employees did not lock out and tag out the electrical disconnect while cleaning the paint from the holes and cup holders and are exposed to crush hazards from the smasher bar.  Larose Industries, LLC dba Cra-Z-Art was previously cited for a violation of this occupational safety and health standard  1910.147(c)(7)(i) which was contained in OSHA inspection number 1210228 , citation number 1, item number 2, and was affirmed as a final order on April 28, 2017, with respect to a workplace located at 250 E. Industrial Pkwy Fayette, OH 43521.
Recent events (1)
  • — Z (R) $50815

1910.147 D03

Repeat Gravity 5 1 instance 5 exposed
Issued
Sep 24, 2018
Abate by
Oct 18, 2018
Penalty
Initial $50,815 · Current $50,815
29 CFR 1910.147(d)(3): All energy isolating devices that were needed to control the energy to the machine or equipment were not physically located and operated in such a manner as to isolate the machine or equipment from the energy source(s):   a.)    On or about May 31, 2018, the employer did not ensure the P8 strip machine in the Paint Department was properly de-energized by using the established procedures. Employees were exposed to crush hazards from the smasher while wiping out the cup holders and holes with rags and pinch points from the chain and sprockets while changing out the wash bucket while relying on the e-stop for energy control.  Larose Industries, LLC dba Cra-Z-Art was previously cited for a violation of an equivalent occupational safety and health standard, 1910.147(d), which was contained in OSHA inspection number 1210228, citation number 1, item number 1b and was affirmed as a final order on April 28, 2017 with respect to a workplace located at 250 East Industrial Pkwy Fayette, OH 43521.
Recent events (1)
  • — Z (R) $50815

View Larose Industries, LLC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 343199576.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.