OSHA Inspection: ITW POLYMER SEALANTS NORTH AMERICA, INC.

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of ITW POLYMER SEALANTS NORTH AMERICA, INC. in 56 AIR STATION INDUSTRIAL PARK, ROCKLAND, MA 02370 (NAICS 325520). OSHA activity number 343257077.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch ITW Polymer Sealants North America, INC. — free Get an email when a new federal OSHA severe-injury report for ITW Polymer Sealants North America, INC. is published. One employer, no account, unsubscribe in one click.
Site address
56 AIR STATION INDUSTRIAL PARK
City
ROCKLAND
State
MA
ZIP
02370
Mailing
56 AIR STATION INDUSTRIAL PARK, ROCKLAND, MA 02370
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
325520
Employees
13
Ownership type
A

13 citations on file for this inspection.

1910.28 B01 I

Serious Gravity 10 3 instances 2 exposed
Issued
Dec 10, 2018
Abate by
Dec 18, 2018
Penalty
Initial $12,934 · Current $5,750 Reduced
29 CFR 1910.28(b)(1)(i): The employer did not ensure that each employee on a walking-working surface with an unprotected side or edge that was 4 feet (1.2 m) or more above a lower level was protected from falling by one or more of the following:  Guardrail systems, safety net systems, or personal fall arrest systems:    Location:  Tank Farm catwalk, Reactor Room mezzanine, Gas House roof    Employees are inadequately protected against falls of up to approximately 10 feet 3 inches.    Instance A:  Catwalks used by employees to measure solvent levels in tanks lack mid-rails in some sections thereby exposing employees to fall hazards of approximately 9 feet 3 inches.    Instance B:   Employees going onto the Gas House roof to open valves and perform maintenance tasks are unprotected against falls of approximately 8 feet 6 inches.    Instance C: Employees unloading bags of dry ingredients are unprotected against a fall hazard of approximately 10 feet 3 inches.
Recent events (3)
  • — F (S) $5750
  • — C (S) $12934
  • — Z (S) $12934

1910.119 D03 I

Serious Gravity 5 3 instances 15 exposed
Issued
Dec 10, 2018
Abate by
Dec 31, 2019
Penalty
Initial $10,163 · Current $4,700 Reduced
29 CFR 1910.119(d)(3)(i): Process safety information pertaining to the equipment in the process did not include the elements specified in 29 CFR 1910.119(d)(3)(i)(A) through (H):    Location:  Tank Farm, Reactor Room, Churn Room, Clay Mix Room    Instance A:  The Reactor lacked a name plate which indicated its maximum allowable working pressure and temperature, date of installation and other required information.    Instance B:  The company did not have design and design basis information for hydrostatic relief valves for the A70 and DME propellant piping.    Instance C:  The company did not have ventilation design information for the Churn Room and its ventilation design information for the Clay Mix Room is inadequate.
Recent events (3)
  • — F (S) $4700
  • — C (S) $10163
  • — Z (S) $10163

1910.119 E03

Serious Gravity 5 4 instances 15 exposed
Issued
Dec 10, 2018
Abate by
Jan 31, 2019
Penalty
Initial $10,163 · Current $4,700 Reduced
29 CFR 1910.119(e)(3): The process hazard analysis did not address the elements of (i) through (vii) of this paragraph:    Location:  Tank Farm, Gas House, Reactor Room, Churn Room, Clay Mix Room    The "What-If " process hazard analysis did not identify all the engineering and administrative controls needed to manage the consequences of failure of equipment, safe work practices, etc.    Instance A:  The What-If analysis does not indicate how safety will be maintained in the event of a power outage.    Instance B:  The What-If analysis does not indicate how hazards associated with the rupture of propellant piping will be addressed.    Instance C: The What-If analysis does not address the failure of propellant tanks due to mechanical damage such as their being struck by nearby collapsing vertical tanks.    Instance D:  The What-If analysis does not identify a closed input valve which causes a delivery hose to burst or blow off the valve as a potential hazard.    Instance E:  The What-If analysis does not indicate how the hazards associated with blocked or otherwise malfunctioning ventilation will be addressed.
Recent events (3)
  • — F (S) $4700
  • — C (S) $10163
  • — Z (S) $10163

1910.119 F01

Deleted Serious Gravity 5 1 instance 5 exposed
Issued
Dec 10, 2018
Abate by
Jan 31, 2019
Penalty
Initial $10,163 · Current $0 Reduced
29 CFR 1910.119(f)(1): The employer did not develop and implement written operating procedures that provided clear instructions for safely conducting activities involved in each covered process consistent with the process safety information and addressing at least steps for each operating phase, safe operating limits, safety and health considerations, and safety systems and their functions as outlined by this paragraph:  Facility:  Tank Farm, Gas House  The company has not developed and implemented written operating procedures for the Tank Farm, Gas House or Reactor Room.  Instance A:  The company has three different operating procedures for unloading the Tank Farm.  The Aeropres procedure that it identified as the procedure governing the unloading of propellants calls for taking a sample and having it analyzed before unloading.  This is not done.    Instance B:  Tank Farm employees do not inspect Tank Farm hoses.  Instance C:  A Gas House employee was unfamiliar with a document that contained Gas House operating procedures.  Instance D:  Gas House operating procedures in a Gunderson Systems 2003 document are not up-to-date.
Recent events (3)
  • — F (S) $0
  • — C (S) $10163
  • — Z (S) $10163

1910.119 F04

Serious Gravity 5 1 instance 2 exposed
Issued
Dec 10, 2018
Abate by
Dec 24, 2018
Penalty
Initial $10,163 · Current $4,700 Reduced
29 CFR 1910.119(f)(4): The employer did not develop and implement safe work practices to provide for the control of hazards during operations such as lockout/tagout; confined space entry; opening process equipment or piping; and control over entrance into a facility by maintenance, contractor, laboratory, or other support personnel:    Location:  Tank Farm, Gas House, Reactor Room    Equipment such as valves are not being locked out prior to maintenance work being performed on them.
Recent events (3)
  • — F (S) $4700
  • — C (S) $10163
  • — Z (S) $10163

1910.147 C04 I

Deleted Serious Gravity 5 1 instance 4 exposed
Issued
Dec 10, 2018
Abate by
Dec 24, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section:  Location:  Prosys Room, palletizer and shrink wrap machines  Lock out / tag out procedures for the shrink wrap machine are inadequate.  An employee was injured while performing maintenance work on the palletizer.  Instance A:  The procedure does not include procedures for 'troubleshooting" the machine when pneumatic power to the 'arms' must remain 'on'.  Instance B: When pneumatic power can be de-energized, the procedure does not call for locking out the valve.  Instance C:  The procedure does not call for verifying that electric power to the machine is 'off'.  Instance D:  The procedures do not adequately address de-energization of the shrink wrap machine.
Recent events (3)
  • — F (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.147 F01 II

Serious Gravity 5 1 instance 2 exposed
Issued
Dec 10, 2018
Abate by
Dec 18, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.147(f)(1)(ii): Employees were not removed from the machine or equipment area in accordance with paragraph (e)(2) of this section during testing or positioning of machines, equipment or components thereof.  Location:  Prosys Room  An employee was not removed from the machine area during the troubleshooting of the shrink wrap machine arm.  He was seriously injured when the machine arm activated and struck him in the head.
Recent events (3)
  • — F (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.119 G01 I

Serious Gravity 5 1 instance 3 exposed
Issued
Dec 10, 2018
Abate by
Jan 31, 2019
Penalty
Initial $10,163 · Current $4,700 Reduced
29 CFR 1910.119(g)(1)(i): The employer did not train each employee before being involved in operating a newly assigned process in the operating procedures as specified in paragraph (f) of this section.    Facility:  Tank Farm, Gas House, Reactor Room, Churn Room, Clay Mix Room    Employees have not been adequately trained on the process operating procedures for PSM covered processes.
Recent events (3)
  • — F (S) $4700
  • — C (S) $10163
  • — Z (S) $10163

1910.119 G02

Serious Gravity 5 1 instance 4 exposed
Issued
Dec 10, 2018
Abate by
Jan 31, 2019
Penalty
Initial $0 · Current $0
29 CFR 1910.119(g)(2): Refresher training was not provided at least every three years to each employee involved in operating a process to assure that the employee understands and adheres to the current operating procedures of the process:    Location:  Tank Farm, Gas House, Reactor Room    Employees have not received refresher training of an overview of the process operating procedures for PSM covered processes.
Recent events (3)
  • — F (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.119 G03

Serious Gravity 5 1 instance 3 exposed
Issued
Dec 10, 2018
Abate by
Jan 31, 2019
Penalty
Initial $0 · Current $0
29 CFR 1910.119(g)(3):   Training documentation. The employer do not ascertain that each employee involved in operating a process had received and understood the training required by this paragraph. The employer did not prepare a record which contains the identity of the employee, the date of training, and the means used to verify that the employee understood the training.    Location:    Tank Farm, Gas House, Reactor Room, Churn Room, Clay Mix Room.    The company has not prepared sufficient written records documenting that its employees have received training on operating procedures for PSM covered processes.
Recent events (3)
  • — F (S) $0
  • — C (S) $0
  • — Z (S) $0

1910.119 J04 III

Serious Gravity 10 1 instance 15 exposed
Issued
Dec 10, 2018
Abate by
Jun 30, 2020
Penalty
Initial $12,934 · Current $5,750 Reduced
29 CFR 1910.119(j)(4)(iii): The frequency of inspections and tests of process equipment to maintain its mechanical integrity, was not consistent with applicable manufacturer's recommendations and good engineering practices, or more frequently determined to be necessary by prior operating experience.        Location:  Tank Farm, Gas House, Reactor Room    The company has not performed inspections and tests of process equipment consistent with applicable manufacturers' recommendations and good engineering practices.
Recent events (3)
  • — F (S) $5750
  • — C (S) $12934
  • — Z (S) $12934

1910.119 J05

Serious Gravity 5 1 instance 15 exposed
Issued
Dec 10, 2018
Penalty
Initial $10,163 · Current $4,700 Reduced
29 CFR 1910.119(j)(5): The employer did not correct deficiencies in equipment that were outside acceptable limits (defined by the process safety information in paragraph (d) of this section) before further use or in a safe and timely manner when necessary means were taken to assure safe operation:    Location:  Tank Farm    For several years, vertical solvent tanks were inadequately protected against wind and seismic loads.  Had they collapsed, they could have severely damaged nearby propellant tanks and piping and produced a catastrophic release of propellant.
Recent events (3)
  • — F (S) $4700
  • — C (S) $10163
  • — Z (S) $10163

1910.147 C07 I B

Deleted Serious Gravity 5 2 instances 4 exposed
Issued
Dec 10, 2018
Abate by
Jan 9, 2019
Penalty
Initial $10,163 · Current $0 Reduced
29 CFR 1910.147(c)(7)(i)(B): Affected employees were not instructed in the purpose and use of the energy control procedure.  Location:  Prosys Room, Tank Farm  Affected employees did not receive lock out / tag out training.    Instance A:   Employees working in the Tank Farm who assist with maintenance work.  Instance B:   Employees operating the Prosys Room palletizer and shrink wrap machine.
Recent events (3)
  • — F (S) $0
  • — C (S) $10163
  • — Z (S) $10163

View ITW Polymer Sealants North America, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 343257077.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.