OSHA Inspection: DEFLEX INNOVATIONS INC.

Complaint inspection · Health discipline

On , OSHA opened a complaint health inspection of DEFLEX INNOVATIONS INC. in 22 JERICHO ROAD, BERLIN, NH 03570 (NAICS 336211). OSHA activity number 343319695.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Deflex Innovations INC. — free Get an email when a new federal OSHA severe-injury report for Deflex Innovations INC. is published. One employer, no account, unsubscribe in one click.
Site address
22 JERICHO ROAD
City
BERLIN
State
NH
ZIP
03570
Mailing
107 RUE INDUSTRIELLE NADEAU
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
336211
Employees
4
Ownership type
A

6 citations on file for this inspection.

1910.133 A01

Serious Gravity 5 1 instance 4 exposed
Issued
Nov 6, 2018
Abate by
Nov 27, 2018
Penalty
Initial $2,772 · Current $1,040 Reduced
29 CFR 1910.133(a)(1): The employer did not ensure that each affected employee uses appropriate eye or face protection when exposed to eye or face hazards from flying particles, molten metal, liquid chemicals, acids or caustic liquids, chemical gases or vapors, or potentially injurious light radiation    Location: Site  On or about 7/19/18 Employees pouring corrosive chemicals, such as but not limited to Norox Azox (containing peroxides) from one container to another were not provided adequate eye and face protection as required by the chemical manufacturer.
Recent events (2)
  • — I (S) $1040
  • — Z (S) $2772

1910.134 C

Other-than-serious 1 instance 4 exposed
Issued
Nov 6, 2018
Abate by
Dec 26, 2018
Penalty
Initial $2,217 · Current $0 Reduced
29 CFR 1910.134(c): The employer did not develop and implement a written respiratory protection program with required worksite-specific procedures and elements for required respirator use:    Location: Site    On or about 7/19/18 Employer does not have a respiratory protection program in place and mandates employees use of respirators.
Recent events (2)
  • — I (O) $0
  • — Z (S) $2217

1910.134 C01 II

Other-than-serious 1 instance 2 exposed
Issued
Nov 6, 2018
Abate by
Dec 26, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.134(c)(1)(ii): The written program did not contain provisions for medical evaluations of employees required to use respirators    Location: Site    On or about 7/19/18 medical evaluations were not provided to employees required to use respirators.
Recent events (2)
  • — I (O) $0
  • — Z (S) $0

1910.134 C01 III

Other-than-serious 1 instance 2 exposed
Issued
Nov 6, 2018
Abate by
Dec 26, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.134(c)(1)(iii): The written program did not contain fit test procedures for tight-fitting respirators:    Location: Site  On or about 7/19/18 the Employer did not provide fit testing for employees required to use respirators during spray operations.
Recent events (2)
  • — I (O) $0
  • — Z (S) $0

1910.134 C01 VIII

Other-than-serious 1 instance 2 exposed
Issued
Nov 6, 2018
Abate by
Dec 26, 2018
Penalty
Initial $0 · Current $0
29 CFR 1910.134(c)(1)(viii): The written program did not contain provisions for training of employees in the proper use of respirators, including putting on and removing them, any limitations on their use, and their maintenance:    Location: Site    On or about 7/19/18 the Employer did not provide training for employees required to use respirators during spray operations.
Recent events (2)
  • — I (O) $0
  • — Z (S) $0

1910.1200 E01

Serious Gravity 5 1 instance 4 exposed
Issued
Nov 6, 2018
Abate by
Dec 26, 2018
Penalty
Initial $2,772 · Current $1,040 Reduced
29 CFR 1910.1200(e)(1): Employer had not developed or implemented a written hazard communication program included the requirements outlined in 29 CFR 1910.1200(e)(1)(i) and (e)(1)(ii)    Location: site   On or about 7/19/18 The employer did not develop or implement a written hazard communication program when employees were using hazardous chemical to include but not limited to: Chemlease MPP 2180, 3M Hi-Tack Composite Spray Adhesive 71 Green, Acetone, Norox Azox and polyester Resign Solution (H834-WWH-28).
Recent events (2)
  • — I (S) $1040
  • — Z (S) $2772

View Deflex Innovations INC.'s full OSHA safety record →