OSHA Inspection: PAINTERS IN ACTION, LLC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of PAINTERS IN ACTION, LLC in CLUBHOUSE AT 1450 NEWNAN CROSSING BLVD., NEWNAN, GA 30265 (NAICS 238320). OSHA activity number 343763991.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Painters in Action, LLC — free Get an email when a new federal OSHA severe-injury report for Painters in Action, LLC is published. One employer, no account, unsubscribe in one click.
Site address
CLUBHOUSE AT 1450 NEWNAN CROSSING BLVD.
City
NEWNAN
State
GA
ZIP
30265
Mailing
140 VERNON DRIVE, WARNER ROBINS, GA 31088
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238320
Employees
11
Ownership type
A

4 citations on file for this inspection.

1926.21 B02

Serious Gravity 5 1 instance 3 exposed
Issued
Apr 1, 2019
Abate by
Apr 25, 2019
Penalty
Initial $3,031 · Current $1,819 Reduced
29 CFR 1926.21(b)(2): The employer did not instruct each employee in the recognition and avoidance of unsafe conditions and the regulations applicable to his/her environment to control or eliminate any hazards or other exposure to illness or injury:  (a) New clubhouse construction in Serenade at Newnan Crossing Subdivision, Roof: On or about February 5, 2019, and at times prior, the employer failed to provide training to employees in the recognition of hazards related to elevated walking/working surfaces and aerial lift equipment, in that employees were not provided with the Personal Protective Equipment and training needed to perform tasks on these working surfaces and equipment.
Recent events (2)
  • — I (S) $1818.6
  • — Z (S) $3031

1926.501 B01

Serious Gravity 10 1 instance 3 exposed
Issued
Apr 1, 2019
Abate by
Apr 25, 2019
Penalty
Initial $5,304 · Current $3,182 Reduced
29 CFR 1926.501(b)(1): Each employee on a walking/working surface with an unprotected side or edge which was 6 feet (1.8 m) or more above a lower level was not protected from falling by the use of guardrail systems, safety net systems, or personal fall arrest systems.  (a) New clubhouse construction in Serenade at Newnan Crossing Subdivision, Roof: On or about February 5, 2019, and at times prior, the employer exposed employees to fall hazards of 12-feet, 11-inches to the lower level, in that a fall protection system was not provided to employees prepping and painting the cupola using the 7/12 pitched roof as a walking/working surface.
Recent events (2)
  • — I (S) $3182.4
  • — Z (S) $5304

1926.453 B02 V

Serious Gravity 5 1 instance 3 exposed
Issued
Apr 1, 2019
Penalty
Initial $0 · Current $0
29 CFR 1926.453(b)(2)(v): A body belt with lanyard attached to the boom or basket was not worn by employee(s) working from an aerial lift:  (a) New clubhouse construction in Serenade at Newnan Crossing Subdivision, Roof: On or about February 5, 2019, and at times prior, the employer exposed employees to ejection/fall hazards of more than 13-feet 12-feet to the lower level, in that a fall protection system was not provided to employees accessing the roof using a Genie S-60 Aerial Lift. Employees used the aerial lift to gain access to the roof to perform paint prep work on the cupola.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1904.29 A

Other-than-serious 1 instance 3 exposed
Issued
Apr 1, 2019
Abate by
Apr 25, 2019
Penalty
Initial $758 · Current $455 Reduced
29 CFR 1904.29(a): A Log of all Work-Related Injuries and Illnesses (OSHA Form 300), and/or Summary of Work-Related Injuries and Illnesses, (OSHA Form 300-A), and/or the Injury and Illness Incident Report (OSHA Form 301) or equivalent forms were not kept by the establishment:  (a) Throughout company, on or about February 5, 2019, and at times prior, the employer failed to provide Logs of all work-related injuries and illnesses (OSHA 300), and/or Summary or work-related injuries and illnesses, (OSHA Form 300-A) at the establishment when there were 11 employees working in the company.
Recent events (2)
  • — I (O) $454.8
  • — Z (O) $758

View Painters in Action, LLC's full OSHA safety record →