SPRING, TX —
OSHA Inspection: MOISES GONZALEZ
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of MOISES GONZALEZ in 25422 ALDINE WESTFIELD RD., SPRING, TX 77373 (NAICS 238140). OSHA activity number 343860326.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- MOISES GONZALEZ
- Site address
- 25422 ALDINE WESTFIELD RD.
- City
- SPRING
- State
- TX
- ZIP
- 77373
- Mailing
- 89 FONDREN RD. APT. 245, HOUSTON, TX 77063
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 6
- Ownership type
- A
Citations
6 citations on file for this inspection.
1926.451 E01
- Issued
- Jun 28, 2019
- Penalty
- Initial $2,842 · Current $2,842
General-duty citation text
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Crossbraces were used as a means of access. On or about March 19, 2019 employees were exposed to a fall hazard when climbing the scaffold crossbraces.
Recent events (1)
- — Z (S) $2842
1926.451 G01 VII
- Issued
- Jun 28, 2019
- Penalty
- Initial $2,842 · Current $2,842
General-duty citation text
29 CFR 1926.451(g)(1)(vii): Each employee on a scaffold, not otherwise specified in paragraphs (g)(1)(i) through (g)(1)(vi) of this section, more than 10 feet (3.1 m) above lower level was not protected from falls by the use of personal fall arrest systems or guardrail systems meeting the requirements of paragraph (g)(4) of this section. On or about March 19, 2019 where employees were exposed to a fall hazard of more than 10 feet while working from a tubular welded frame scaffold without the use of a fall protection system.
Recent events (1)
- — Z (S) $2842
1926.452 C02
- Issued
- Jun 28, 2019
- Penalty
- Initial $2,842 · Current $2,842
General-duty citation text
29 CFR 1926.452(c)(2): Tubular welded frames and panels were not braced by cross, horizontal, or diagonal braces, or combination thereof, which would have secured vertical members together laterally: On or about March 19, 2019, at the construction site where employees were exposed to a fall hazard when they were permitted to work on a tubular welded scaffold that did not have all of the cross bracing.
Recent events (1)
- — Z (S) $2842
1910.1200 E01
- Issued
- Jun 28, 2019
- Abate by
- Aug 1, 2019
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.1200(e)(1): The employer did not develop, implement, and/or maintain at the workplace a written hazard communication program which describes how the criteria specified in 29 CFR 1910.1200(f), (g), and (h) will be met: (Construction Reference: 1926.59) On or about March 19, 2019, at the construction site, where employees were using chemicals such as but not limited to, water based acrylic coating and acrylic paint, without a written hazard communication program in place.
Recent events (1)
- — Z (O) $0
1910.1200 G01
- Issued
- Jun 28, 2019
- Abate by
- Jul 18, 2019
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.1200(g)(1): The employer did not have a material safety data sheet for each hazardous chemical which they used: (Construction Reference: 1926.59) On or about March 19, 2019, where employees did not have safety data sheets for the water based acrylic coating and acrylic paint that was in use.
Recent events (1)
- — Z (O) $0
1910.1200 H01
- Issued
- Jun 28, 2019
- Abate by
- Aug 1, 2019
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.1200(h)(1): Employees were not provided effective information and training on hazardous chemicals in their work area at the time of their initial assignment and whenever a new hazard that the employees had not been previously trained about was introduced into their work area: (Construction Reference: 1926.59) On or about March 19, 2019, at the construction site, where employees were using chemicals such as but not limited to, water based acrylic coating and acrylic paint, and had not been trained on the hazards of the chemicals they use.
Recent events (1)
- — Z (O) $0
More inspections at Moises Gonzalez
View Moises Gonzalez's full OSHA safety record →
More inspections in this industry (NAICS 238140)
More inspections in TX
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 343860326.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.